82 FR 35773 - Wallowa Resources Community Solutions Inc.; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 146 (August 1, 2017)

Page Range35773-35774
FR Document2017-16080

Federal Register, Volume 82 Issue 146 (Tuesday, August 1, 2017)
[Federal Register Volume 82, Number 146 (Tuesday, August 1, 2017)]
[Notices]
[Pages 35773-35774]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-16080]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD17-16-000]


Wallowa Resources Community Solutions Inc.; Notice of Preliminary 
Determination of a Qualifying Conduit Hydropower Facility and 
Soliciting Comments and Motions To Intervene

    On July 20, 2017, Wallowa Resources Community Solutions Inc. filed 
a notice of intent to construct a qualifying conduit hydropower 
facility, pursuant to section 30 of the Federal Power Act (FPA), as 
amended by section 4 of the Hydropower Regulatory Efficiency Act of 
2013 (HREA). The proposed Wallowa Lake County Service District Hydro 
Station Project would have an installed capacity of 20 kilowatts (kW), 
and would be located along the existing State Park Spring municipal 
water pipeline located near the town of Joseph, Wallowa County, Oregon.
    Applicant Contact: Kyle Petrocine, 401 NE 1st Street, Suite A, 
Enterprise, OR 97828, Phone No. (541) 398-0018.
    FERC Contact: Christopher Chaney, Phone No. (202) 502-6778, email: 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A new 20-kW impulse turbine and induction 
generator; (2) a new, approximately 13-foot by 14-foot powerhouse; and 
(3) appurtenant facilities. The proposed project would have an 
estimated annual generating capacity of 149,000 kilowatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

                          Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
                                                                                                  Satisfies  (Y/
              Statutory provision                                  Description                          N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by HREA...........  The conduit the facility uses is a tunnel,                     Y
                                                 canal, pipeline, aqueduct, flume, ditch, or
                                                 similar manmade water conveyance that is
                                                 operated for the distribution of water for
                                                 agricultural, municipal, or industrial
                                                 consumption and not primarily for the
                                                 generation of electricity.
FPA 30(a)(3)(C)(i), as amended by HREA........  The facility is constructed, operated, or                      Y
                                                 maintained for the generation of electric power
                                                 and uses for such generation only the
                                                 hydroelectric potential of a non-federally
                                                 owned conduit.
FPA 30(a)(3)(C)(ii), as amended by HREA.......  The facility has an installed capacity that does               Y
                                                 not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as amended by HREA......  On or before August 9, 2013, the facility is not               Y
                                                 licensed, or exempted from the licensing
                                                 requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------

    Preliminary Determination: The proposed addition of the 
hydroelectric project along the municipal water pipeline will not alter 
its primary purpose. Therefore, based upon the above information and 
criteria, Commission staff preliminarily determines that the proposal 
satisfies the requirements for a qualifying conduit hydropower 
facility, which is not required to be licensed or exempted from 
licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the COMMENTS CONTESTING QUALIFICATION FOR A 
CONDUIT HYDROPOWER FACILITY or MOTION TO INTERVENE, as applicable; (2) 
state in the heading the name of the applicant and the project number 
of the application to which the filing responds; (3) state the name, 
address, and telephone number of the person filing; and (4) otherwise 
comply with the requirements of sections 385.2001 through 385.2005 of 
the Commission's regulations.\1\ All comments contesting Commission 
staff's preliminary determination that the facility meets the 
qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2016).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp

[[Page 35774]]

using the ``eLibrary'' link. Enter the docket number (i.e., CD17-16) in 
the docket number field to access the document. For assistance, call 
toll-free 1-866-208-3676 or email [email protected]. For TTY, 
call (202) 502-8659.

    Dated: July 25, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-16080 Filed 7-31-17; 8:45 am]
BILLING CODE 6717-01-P



                                                                                Federal Register / Vol. 82, No. 146 / Tuesday, August 1, 2017 / Notices                                                  35773

                                                  888 First Street NE., Washington, DC                      DEPARTMENT OF ENERGY                                      State Park Spring municipal water
                                                  20426.                                                                                                              pipeline located near the town of
                                                     This filing is accessible on-line at                   Federal Energy Regulatory                                 Joseph, Wallowa County, Oregon.
                                                  http://www.ferc.gov, using the eLibrary                   Commission                                                  Applicant Contact: Kyle Petrocine,
                                                  link and is available for review in the                   [Docket No. CD17–16–000]                                  401 NE 1st Street, Suite A, Enterprise,
                                                  Commission’s Public Reference Room in                                                                               OR 97828, Phone No. (541) 398–0018.
                                                  Washington, DC. There is an                               Wallowa Resources Community                                 FERC Contact: Christopher Chaney,
                                                  eSubscription link on the Web site that                   Solutions Inc.; Notice of Preliminary                     Phone No. (202) 502–6778, email:
                                                  enables subscribers to receive email                      Determination of a Qualifying Conduit                     Christopher.Chaney@ferc.gov.
                                                  notification when a document is added                     Hydropower Facility and Soliciting                          Qualifying Conduit Hydropower
                                                  to a subscribed docket(s). For assistance                 Comments and Motions To Intervene                         Facility Description: The proposed
                                                  with any FERC Online service, please                        On July 20, 2017, Wallowa Resources                     project would consist of: (1) A new 20-
                                                  email FERCOnlineSupport@ferc.gov, or                      Community Solutions Inc. filed a notice                   kW impulse turbine and induction
                                                  call (866) 208–3676 (toll free). For TTY,                 of intent to construct a qualifying                       generator; (2) a new, approximately 13-
                                                  call (202) 502–8659.                                      conduit hydropower facility, pursuant                     foot by 14-foot powerhouse; and (3)
                                                     Comment Date: 5:00 p.m. Eastern                        to section 30 of the Federal Power Act                    appurtenant facilities. The proposed
                                                  Time on August 7, 2017.                                   (FPA), as amended by section 4 of the                     project would have an estimated annual
                                                                                                            Hydropower Regulatory Efficiency Act                      generating capacity of 149,000 kilowatt-
                                                    Dated: July 26, 2017.
                                                                                                            of 2013 (HREA). The proposed Wallowa                      hours.
                                                  Kimberly D. Bose,
                                                                                                            Lake County Service District Hydro                          A qualifying conduit hydropower
                                                  Secretary.                                                Station Project would have an installed                   facility is one that is determined or
                                                  [FR Doc. 2017–16163 Filed 7–31–17; 8:45 am]               capacity of 20 kilowatts (kW), and                        deemed to meet all of the criteria shown
                                                  BILLING CODE 6717–01–P                                    would be located along the existing                       in the table below.

                                                                                        TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                      Satisfies
                                                                   Statutory provision                                                                  Description                                    (Y/N)

                                                  FPA 30(a)(3)(A), as amended by HREA ...............             The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume,                    Y
                                                                                                                    ditch, or similar manmade water conveyance that is operated for the dis-
                                                                                                                    tribution of water for agricultural, municipal, or industrial consumption
                                                                                                                    and not primarily for the generation of electricity.
                                                  FPA 30(a)(3)(C)(i), as amended by HREA ............             The facility is constructed, operated, or maintained for the generation of                      Y
                                                                                                                    electric power and uses for such generation only the hydroelectric poten-
                                                                                                                    tial of a non-federally owned conduit.
                                                  FPA 30(a)(3)(C)(ii), as amended by HREA ...........             The facility has an installed capacity that does not exceed 5 megawatts .....                   Y
                                                  FPA 30(a)(3)(C)(iii), as amended by HREA ..........             On or before August 9, 2013, the facility is not licensed, or exempted from                     Y
                                                                                                                    the licensing requirements of Part I of the FPA.



                                                     Preliminary Determination: The                            Filing and Service of Responsive                       registration, using the eComment system
                                                  proposed addition of the hydroelectric                    Documents: All filings must (1) bear in                   at http://www.ferc.gov/docs-filing/
                                                  project along the municipal water                         all capital letters the COMMENTS                          ecomment.asp. You must include your
                                                  pipeline will not alter its primary                       CONTESTING QUALIFICATION FOR A                            name and contact information at the end
                                                  purpose. Therefore, based upon the                        CONDUIT HYDROPOWER FACILITY or                            of your comments. For assistance,
                                                  above information and criteria,                           MOTION TO INTERVENE, as                                   please contact FERC Online Support at
                                                  Commission staff preliminarily                            applicable; (2) state in the heading the                  FERCOnlineSupport@ferc.gov, (866)
                                                  determines that the proposal satisfies                    name of the applicant and the project                     208–3676 (toll free), or (202) 502–8659
                                                  the requirements for a qualifying                         number of the application to which the                    (TTY). In lieu of electronic filing, please
                                                  conduit hydropower facility, which is                     filing responds; (3) state the name,                      send a paper copy to: Secretary, Federal
                                                  not required to be licensed or exempted                   address, and telephone number of the                      Energy Regulatory Commission, 888
                                                  from licensing.                                           person filing; and (4) otherwise comply                   First Street NE., Washington, DC 20426.
                                                     Comments and Motions to Intervene:                     with the requirements of sections                         A copy of all other filings in reference
                                                  Deadline for filing comments contesting                   385.2001 through 385.2005 of the                          to this application must be accompanied
                                                  whether the facility meets the qualifying                 Commission’s regulations.1 All                            by proof of service on all persons listed
                                                  criteria is 45 days from the issuance                     comments contesting Commission staff’s                    in the service list prepared by the
                                                  date of this notice.                                      preliminary determination that the                        Commission in this proceeding, in
                                                     Deadline for filing motions to                         facility meets the qualifying criteria                    accordance with 18 CFR 4.34(b) and
                                                  intervene is 30 days from the issuance                    must set forth their evidentiary basis.                   385.2010.
                                                  date of this notice.                                         The Commission strongly encourages                        Locations of Notice of Intent: Copies
                                                     Anyone may submit comments or a                        electronic filing. Please file motions to                 of the notice of intent can be obtained
mstockstill on DSK30JT082PROD with NOTICES




                                                  motion to intervene in accordance with                    intervene and comments using the                          directly from the applicant or such
                                                  the requirements of Rules of Practice                     Commission’s eFiling system at http://                    copies can be viewed and reproduced at
                                                  and Procedure, 18 CFR 385.210 and                         www.ferc.gov/docs-filing/efiling.asp.                     the Commission in its Public Reference
                                                  385.214. Any motions to intervene must                    Commenters can submit brief comments                      Room, Room 2A, 888 First Street NE.,
                                                  be received on or before the specified                    up to 6,000 characters, without prior                     Washington, DC 20426. The filing may
                                                  deadline date for the particular                                                                                    also be viewed on the web at http://
                                                  proceeding.                                                    1 18   CFR 385.2001–2005 (2016).                     www.ferc.gov/docs-filing/elibrary.asp


                                             VerDate Sep<11>2014   20:13 Jul 31, 2017    Jkt 241001   PO 00000     Frm 00031    Fmt 4703   Sfmt 4703   E:\FR\FM\01AUN1.SGM   01AUN1


                                                  35774                         Federal Register / Vol. 82, No. 146 / Tuesday, August 1, 2017 / Notices

                                                  using the ‘‘eLibrary’’ link. Enter the                      This filing is accessible online at                1902–0169, should be sent via email to
                                                  docket number (i.e., CD17–16) in the                     http://www.ferc.gov, using the eLibrary               the Office of Information and Regulatory
                                                  docket number field to access the                        link and is available for review in the               Affairs: oira_submission@omb.gov.
                                                  document. For assistance, call toll-free                 Commission’s Public Reference Room in                 Attention: Federal Energy Regulatory
                                                  1–866–208–3676 or email FERCOnline                       Washington, DC. There is an                           Commission Desk Officer. The Desk
                                                  Support@ferc.gov. For TTY, call (202)                    eSubscription link on the Web site that               Officer may also be reached via
                                                  502–8659.                                                enables subscribers to receive email                  telephone at 202–395–0710.
                                                    Dated: July 25, 2017.                                  notification when a document is added                    A copy of the comments should also
                                                                                                           to a subscribed docket(s). For assistance             be sent to the Commission, in Docket
                                                  Kimberly D. Bose,
                                                                                                           with any FERC Online service, please                  No. IC17–11–000, by either of the
                                                  Secretary.                                               email FERCOnlineSupport@ferc.gov, or                  following methods:
                                                  [FR Doc. 2017–16080 Filed 7–31–17; 8:45 am]              call (866) 208–3676 (toll free). For TTY,                • eFiling at Commission’s Web site:
                                                  BILLING CODE 6717–01–P                                   call (202) 502–8659.                                  http://www.ferc.gov/docs-filing/efiling
                                                                                                              Comment Date: 5:00 p.m. Eastern time               .asp.
                                                                                                           on August 21, 2017.                                      • Mail/Hand Delivery/Courier:
                                                  DEPARTMENT OF ENERGY                                                                                           Federal Energy Regulatory Commission,
                                                                                                             Dated: July 26, 2017.
                                                  Federal Energy Regulatory                                Kimberly D. Bose,                                     Secretary of the Commission, 888 First
                                                  Commission                                               Secretary.                                            Street NE., Washington, DC 20426.
                                                                                                           [FR Doc. 2017–16164 Filed 7–31–17; 8:45 am]
                                                                                                                                                                    Instructions: All submissions must be
                                                                                                                                                                 formatted and filed in accordance with
                                                  [Docket No. OR17–18–000]                                 BILLING CODE 6717–01–P
                                                                                                                                                                 submission guidelines at: http://
                                                  Medallion Pipeline Company, LLC;                                                                               www.ferc.gov/help/submission-
                                                  Notice of Petition For Declaratory                       DEPARTMENT OF ENERGY                                  guide.asp. For user assistance contact
                                                  Order                                                                                                          FERC Online Support by email at
                                                                                                           Federal Energy Regulatory                             ferconlinesupport@ferc.gov, or by phone
                                                    Take notice that on July 21, 2017,                     Commission                                            at: (866) 208–3676 (toll-free), or (202)
                                                  pursuant to Rule 207(a)(2) of the Federal                                                                      502–8659 for TTY.
                                                                                                           [Docket No. IC17–11–000]
                                                  Energy Regulatory Commission’s                                                                                    Docket: Users interested in receiving
                                                  (Commission) Rules of Practice and                       Commission Information Collection                     automatic notification of activity in this
                                                  Procedure, 18 CFR 385.207(a)(2) (2016),                  Activities (FERC–549b); Comment                       docket or in viewing/downloading
                                                  Medallion Pipeline Company, LLC                          Request                                               comments and issuances in this docket
                                                  (Medallion), filed a petition for a                                                                            may do so at http://www.ferc.gov/docs-
                                                  declaratory order seeking approval of                    AGENCY:  Federal Energy Regulatory                    filing/docs-filing.asp.
                                                  the overall tariff and rate structure, and               Commission, Department of Energy.                     FOR FURTHER INFORMATION CONTACT:
                                                  open-season procedures for Medallion’s                   ACTION: Comment request.                              Ellen Brown may be reached by email
                                                  proposed Wolfcamp Connector                              SUMMARY:   In compliance with the                     at DataClearance@FERC.gov, by
                                                  expansion and Howard Lateral                             requirements of the Paperwork                         telephone at (202) 502–8663, and by fax
                                                  expansion to transport crude oil from                    Reduction Act of 1995, the Federal                    at (202) 273–0873.
                                                  Midland Basin in West Texas to                           Energy Regulatory Commission                          SUPPLEMENTARY INFORMATION:
                                                  Colorado City Hub, as more fully                         (Commission or FERC) is submitting its                   Title: FERC–549B (Gas Pipeline Rates:
                                                  explained in the petition.                               information collection [FERC–549B (Gas                Capacity Reports and Index of
                                                    Any person desiring to intervene or to                 Pipeline Rates: Capacity Reports and                  Customers).
                                                  protest this filing must file in                         Index of Customers)] to the Office of                    OMB Control No.: 1902–0169.
                                                  accordance with Rules 211 and 214 of                     Management and Budget (OMB) for                          Type of Request: Three-year extension
                                                  the Commission’s Rules of Practice and                   review of the information collection                  of the FERC–549B information
                                                  Procedure (18 CFR 385.211, 385.214).                     requirements. Any interested person                   collection requirements with no changes
                                                  Protests will be considered by the                       may file comments directly with OMB                   to the current reporting requirements.
                                                  Commission in determining the                            and should address a copy of those                       Abstract: The information collected
                                                  appropriate action to be taken, but will                 comments to the Commission as                         under the requirements of FERC–549B
                                                  not serve to make protestants parties to                 explained below. The Commission                       includes both the Index of Customers
                                                  the proceeding. Any person wishing to                    previously issued a Notice in the                     (IOC) report under Commission
                                                  become a party must file a notice of                     Federal Register (82 FR 18635, 4/20/                  regulations at 18 Code of Federal
                                                  intervention or motion to intervene, as                  2017) requesting public comments. The                 Regulations (CFR) 284.13(c) and three
                                                  appropriate. Such notices, motions, or                   Commission received one comment on                    capacity reporting requirements. One of
                                                  protests must be filed on or before the                  the FERC–549B and is making this                      these is in Commission regulations at 18
                                                  comment date. Anyone filing a motion                     notation in its submittal to OMB. The                 CFR 284.13(b) and requires reports on
                                                  to intervene or protest must serve a copy                sole comment, however, does not                       firm and interruptible services. The
                                                  of that document on the Petitioner.                      pertain to this information collection                second is at 18 CFR 284.13(d)(1) and
                                                    The Commission encourages                              and is immaterial to the renewal effort               requires pipelines make information on
                                                  electronic submission of protests and                    for the FERC–549B.1                                   capacity and flow information available
                                                  interventions in lieu of paper using the                                                                       on their Internet Web sites. The third is
mstockstill on DSK30JT082PROD with NOTICES




                                                                                                           DATES: Comments on the collection of
                                                  eFiling link at http://www.ferc.gov.                     information are due by August 31, 2017.               at 18 CFR 284.13(d)(2) and requires an
                                                  Persons unable to file electronically                                                                          annual filing of peak day capacity.
                                                                                                           ADDRESSES: Comments filed with OMB,
                                                  should submit an original and 5 copies
                                                                                                           identified by the OMB Control No.                     Capacity Reports Under 284.13(b) and
                                                  of the protest or intervention to the
                                                  Federal Energy Regulatory Commission,                                                                          284.13(d)(1)
                                                                                                              1 The comment can be found here: https://
                                                  888 First Street NE., Washington, DC                     elibrary.ferc.gov/idmws/common/OpenNat.asp?             On April 4, 1992, in Order No. 636
                                                  20426.                                                   fileID=14615693.                                      (RM91–11–000), the Commission


                                             VerDate Sep<11>2014   20:13 Jul 31, 2017   Jkt 241001   PO 00000   Frm 00032   Fmt 4703   Sfmt 4703   E:\FR\FM\01AUN1.SGM   01AUN1



Document Created: 2018-10-24 11:42:46
Document Modified: 2018-10-24 11:42:46
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 35773 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR