82 FR 35773 - Wallowa Resources Community Solutions Inc.; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 146 (August 1, 2017)

Page Range35773-35774
FR Document2017-16080

Federal Register, Volume 82 Issue 146 (Tuesday, August 1, 2017)
[Federal Register Volume 82, Number 146 (Tuesday, August 1, 2017)]
[Notices]
[Pages 35773-35774]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-16080]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD17-16-000]


Wallowa Resources Community Solutions Inc.; Notice of Preliminary 
Determination of a Qualifying Conduit Hydropower Facility and 
Soliciting Comments and Motions To Intervene

    On July 20, 2017, Wallowa Resources Community Solutions Inc. filed 
a notice of intent to construct a qualifying conduit hydropower 
facility, pursuant to section 30 of the Federal Power Act (FPA), as 
amended by section 4 of the Hydropower Regulatory Efficiency Act of 
2013 (HREA). The proposed Wallowa Lake County Service District Hydro 
Station Project would have an installed capacity of 20 kilowatts (kW), 
and would be located along the existing State Park Spring municipal 
water pipeline located near the town of Joseph, Wallowa County, Oregon.
    Applicant Contact: Kyle Petrocine, 401 NE 1st Street, Suite A, 
Enterprise, OR 97828, Phone No. (541) 398-0018.
    FERC Contact: Christopher Chaney, Phone No. (202) 502-6778, email: 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A new 20-kW impulse turbine and induction 
generator; (2) a new, approximately 13-foot by 14-foot powerhouse; and 
(3) appurtenant facilities. The proposed project would have an 
estimated annual generating capacity of 149,000 kilowatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

                          Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
                                                                                                  Satisfies  (Y/
              Statutory provision                                  Description                          N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by HREA...........  The conduit the facility uses is a tunnel,                     Y
                                                 canal, pipeline, aqueduct, flume, ditch, or
                                                 similar manmade water conveyance that is
                                                 operated for the distribution of water for
                                                 agricultural, municipal, or industrial
                                                 consumption and not primarily for the
                                                 generation of electricity.
FPA 30(a)(3)(C)(i), as amended by HREA........  The facility is constructed, operated, or                      Y
                                                 maintained for the generation of electric power
                                                 and uses for such generation only the
                                                 hydroelectric potential of a non-federally
                                                 owned conduit.
FPA 30(a)(3)(C)(ii), as amended by HREA.......  The facility has an installed capacity that does               Y
                                                 not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as amended by HREA......  On or before August 9, 2013, the facility is not               Y
                                                 licensed, or exempted from the licensing
                                                 requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------

    Preliminary Determination: The proposed addition of the 
hydroelectric project along the municipal water pipeline will not alter 
its primary purpose. Therefore, based upon the above information and 
criteria, Commission staff preliminarily determines that the proposal 
satisfies the requirements for a qualifying conduit hydropower 
facility, which is not required to be licensed or exempted from 
licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the COMMENTS CONTESTING QUALIFICATION FOR A 
CONDUIT HYDROPOWER FACILITY or MOTION TO INTERVENE, as applicable; (2) 
state in the heading the name of the applicant and the project number 
of the application to which the filing responds; (3) state the name, 
address, and telephone number of the person filing; and (4) otherwise 
comply with the requirements of sections 385.2001 through 385.2005 of 
the Commission's regulations.\1\ All comments contesting Commission 
staff's preliminary determination that the facility meets the 
qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2016).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp

[[Page 35774]]

using the ``eLibrary'' link. Enter the docket number (i.e., CD17-16) in 
the docket number field to access the document. For assistance, call 
toll-free 1-866-208-3676 or email [email protected]. For TTY, 
call (202) 502-8659.

    Dated: July 25, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-16080 Filed 7-31-17; 8:45 am]
BILLING CODE 6717-01-P


Current View
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 35773 