The U.S. Nuclear Regulatory Commission (NRC) issued a confirmatory order (Order) to Westinghouse Electric Company, LLC, (the licensee), confirming the agreement reached in an Alternative Dispute Resolution mediation session held on May 19, 2017, and follow-up discussions held between May 19, 2017, and August 3, 2017. This Order will ensure the licensee restores compliance with NRC's regulations.

Federal Register, Volume 82 Issue 155 (Monday, August 14, 2017)
[Federal Register Volume 82, Number 155 (Monday, August 14, 2017)]
[Notices]
[Pages 37903-37908]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-17101]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 70-1151; License No. SNM-1107; EA-16-173; NRC-2017-0176]


Westinghouse Electric Company, LLC

AGENCY: Nuclear Regulatory Commission.

ACTION: Confirmatory order; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) issued a 
confirmatory order (Order) to Westinghouse Electric Company, LLC, (the 
licensee), confirming the agreement reached in an Alternative Dispute 
Resolution mediation session held on May 19, 2017, and follow-up 
discussions held between May 19, 2017, and August 3, 2017. This Order 
will ensure the licensee restores compliance with NRC's regulations.

DATES: The Order was issued on August 9, 2017.

ADDRESSES: Please refer to Docket ID NRC-2017-0176 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2017-0176. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it is available 
in

[[Page 37904]]

ADAMS) is provided the first time that it is mentioned in this 
document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Scott Sparks, Region II, U.S. Nuclear 
Regulatory Commission, Atlanta, Georgia 30303-1257; telephone: 404-997-
4422; email: [email protected].

SUPPLEMENTARY INFORMATION: The text of the Order is attached.

    Dated at Atlanta, Georgia, this 9th day of August, 2017.

    For the Nuclear Regulatory Commission.
Catherine Haney,
Regional Administrator.

NUCLEAR REGULATORY COMMISSION

[Docket No. 70-1151; License No. SNM-1107; EA-16-173; NRC-2017-0176]
In the Matter of Westinghouse Electric Company, LLC
CONFIRMATORY ORDER (EFFECTIVE UPON ISSUANCE)

I

    Westinghouse Electric Company (Westinghouse, or the licensee) is 
the holder of NRC License No. SNM-1107, issued by the U.S. Nuclear 
Regulatory Commission (NRC or Commission) pursuant to 10 CFR part 70 on 
September 30, 2007. The license authorizes the operation of the 
Columbia Fuel Fabrication Facility (CFFF) in accordance with the 
conditions specified therein. The facility is located on the licensee's 
site in Hopkins, South Carolina.
    This Confirmatory Order (CO) is the result of an agreement reached 
during an alternative dispute resolution (ADR) mediation session 
conducted on May 19, 2017, and follow-up discussions held between May 
19, 2017, and August 3, 2017.

II

    On May 28, 2016, as part of the licensee's routine maintenance 
activities, the licensee started the S-1030 scrubber inspection and 
cleanout activities. The licensee completed the S-1030 scrubber 
cleanout activities on June 1, 2016, removing a total of 197 kilograms 
(kg) of material. The scrubber was subsequently restarted following the 
maintenance outage on June 2, 2016. On July 13, 2016, the preliminary 
results of samples taken of the material removed from the S-1030 
scrubber indicated a 40-50% concentration of uranium (U) enriched to 
less than 5%. This equates to approximately 100 kg of U in the 
scrubber, exceeding the mass limit in the Criticality Safety Evaluation 
(CSE) of 29 kg U.
    The scrubber was shut down on July 14, 2016, when the determination 
was made by the licensee that the mass limit in the CSE had been 
exceeded. The licensee reported this event to the NRC as a 24-hour 
event due to a high consequence event being ``unlikely'' (EN 52090). On 
July 31, 2016, the event report was updated to a one hour report per 10 
CFR 70 Appendix A (a)(4) because no items relied upon for safety 
(IROFS) remained available and reliable to perform their function.
    On August 11, 2016, the NRC issued a Confirmatory Action Letter 
(CAL) to Westinghouse (ML16224B082). The purpose of the CAL was to 
confirm the commitments made by Westinghouse regarding additional 
actions Westinghouse will take in response to the U buildup reported to 
the NRC in July 2016. These actions were intended to ensure that the 
causes of the U buildup have been adequately identified and evaluated 
and that appropriate corrective actions have been implemented to 
improve the performance of the Nuclear Criticality Safety (NCS) 
program.
    On September 27, 2016, the NRC completed an Augmented Inspection at 
the Westinghouse facility, the details of which are documented in NRC 
Inspection Report 70-1151/2016-007 (ML16301A001).
    A follow-up NRC inspection (70-1151/2017-007) was also conducted, 
the results of which were issued on February 27, 2017 (ML17058A448). 
This inspection report identified the following four Apparent 
Violations (AVs), all of which were considered for escalated 
enforcement in accordance with the NRC's Enforcement Policy:
    1. An AV was identified for failure to ensure criticality accident 
sequences remain highly unlikely, as required by Title 10 of the Code 
of Federal Regulations (10 CFR) 10 CFR 70.61(b).
    2. An AV was identified for failure to assure that under normal and 
credible abnormal conditions, all nuclear processes were subcritical 
including use of an approved margin of subcriticality, as required by 
10 CFR 70.61(d).
    3. An AV was identified for failure to establish adequate 
management measures to ensure that items relied on for safety (IROFS) 
perform their function when needed, as required by 10 CFR 70.62(d).
    4. An AV was identified for failure to make a one hour report, as 
required by Appendix A (a)(4) of 10 CFR part 70.
    In response to the NRC's inspection report of February 27, 2017, 
Westinghouse advised the NRC of its desire to participate in the 
Agency's ADR program to resolve the enforcement aspects of this matter.

III

    On May 19, 2017, the NRC and Westinghouse met in an ADR session 
mediated by a professional mediator, arranged through Cornell 
University's Institute on Conflict Resolution. Additional discussions 
were held between the NRC and Westinghouse between May 19, 2017, and 
August 3, 2017, to resolve the enforcement aspects of this matter. ADR 
is a process in which a neutral mediator with no decision-making 
authority assists the parties in reaching an agreement or resolving any 
differences regarding their dispute. This CO is issued pursuant to the 
agreement reached during the ADR process. The elements of the agreement 
consist of the following:
    1. Westinghouse acknowledges that four violations occurred, as 
stated in NRC Inspection Report 70-1151/2017-007.
    2. Based on ADR, the parties agreed that the safety significance of 
violations described in Section II above is characterized as escalated 
enforcement as described in the NRC Enforcement Policy.
    3. Approximately two years (+/- 6 months) after issuance of the CO, 
Westinghouse shall conduct an additional Nuclear Safety Culture (NSC) 
survey by the Westinghouse corporate nuclear safety culture 
organization or an experienced independent third party, consistent with 
the depth and scope of the NSC survey completed under the CAL dated 
August 11, 2016. Identified deficiencies shall be entered into the 
corrective action program (CAP) for tracking corrective actions to 
completion.
    4. Westinghouse shall implement improvements to reduce uranium 
carryover from the Calciner scrubbers, and implement additional design 
changes to reduce U carryover from the Blue M oven filtration system. 
Specifically:
    (1) For the calciner scrubbers, within eighteen (18) months of 
issuance of the CO, an engineering evaluation of the calciner and 
calciner off-gas scrubber design and operation shall be completed to 
determine methods to reduce uranium carry-over into the S-1030 
scrubber.
    (2) For the Blue M oven, within eighteen (18) months of issuance of 
the CO, an engineering evaluation of the Conversion Scrap Cage Blue M 
oven shall be completed to determine methods to improve the 
functionality of

[[Page 37905]]

the Blue M oven in a wet environment and improve accessibility for 
inspection and maintenance activities.
    (3) Within three (3) years of issuance of the CO, improvements 
based on the engineering evaluations described above shall be 
implemented.
    5. In response to the May 2016 event, Westinghouse implemented 
several modifications to the S-1030 scrubber system, as part of its 
overall corrective actions to preclude recurrence and enhance 
performance. These modifications were considered by the NRC, under the 
CAL, in support of a safety basis to authorize restart of conversion 
process equipment and the S-1030 scrubber system, as documented in the 
NRC's letter to Westinghouse dated October 20, 2016 (ML16294A296). The 
modifications included but were not limited to:
    (1) The plenums for the scrap cage Blue M oven hoods were equipped 
with a filter to capture at least 95% of the mass entrained in the air 
stream based on particle size distribution and the manufacturer's 
published efficiency data.
    (2) Packing baskets were implemented to permit complete removal and 
inspection of the packed media and to maintain clearance between the 
packed media and the scrubber floor.
    (3) A feed and bleed system for the scrubber recirculating liquid 
was maintained at a minimum output flow of 0.5 gallons per minute. If 
feed and bleed is not available, a controlled shutdown of the scrubber 
would be initiated in accordance with plant procedures.
    (4) The scrubber was opened to remove the packed media baskets, to 
clean and inspect the inlet transition and scrubber body on a quarterly 
basis.
    (5) Weekly visual inspections of the scrubber inlet transition were 
to be conducted.
    6. Within two (2) years of issuance of the CO, Westinghouse shall 
develop and implement additional methods to monitor system parameters 
that are early indicators of an abnormal accumulation in the S-1030 
scrubber from a process upset that could challenge the accumulation 
rate and/or criticality safety mass limits. The methods will provide 
timely indications to enable the operators to take appropriate actions 
in accordance with approved procedures.
    7. A member of senior Westinghouse leadership shall present 
training on lessons learned from the scrubber event at an industry 
forum, including NSC and criticality safety standards aspects.
    This item was completed on June 14, 2017, when the site vice 
president of CFFF presented training on lessons learned from the 
scrubber event at Fuel Cycle Information Exchange (an industry-wide 
forum), including NSC and criticality safety standards aspects.
    8. Within eighteen (18) months of issuance of the CO, Westinghouse 
shall develop and implement a criticality safety basis/IROFS database 
to help maintain the proper flow down of the safety basis into 
implementing documents.
    9. Within six (6) months of issuance of the CO, Westinghouse shall 
develop a method to reinforce positive NSC leadership behavior and 
monitor for effectiveness in the NSC monitoring panel. Westinghouse 
shall implement such method for three years, after which it may 
evaluate the need to continue this item.
    10. Within three (3) months of issuance of the CO, Westinghouse 
shall develop and implement a new metric or periodic report that 
creates an aggregate picture of the health of the criticality safety 
program. This shall include items such as IROFS challenges, trends, 
audit and inspection finding status, violations, and health of 
management measures and be made available for inspection. Identified 
deficiencies shall be evaluated in accordance with the CAP.
    11. Within nine (9) months, Westinghouse shall implement risk-
informed standards for the preparation of procedures and data sheets 
informed by appropriate guidance in INPO 11-003, ``Guideline for 
Excellence in Procedure and Work Instruction Use and Adherence.'' This 
will consist of issuance of a procedure writers' guide, procedure 
format template, and a procedure use and adherence standard.
    12. The NRC agrees that issuance of this CO serves to close the CAL 
issued to Westinghouse on August 11, 2016. NRC acknowledges that 
Westinghouse has taken extensive actions to address items in the CAL 
including completing a root cause analysis (RCA), completing a review 
of criticality safety evaluations, performing inspections to validate 
system design and operating parameters, installing physical 
modifications to support the safety basis to improve safety 
performance, conducting an independent third party nuclear safety 
culture assessment, and completing several corrective actions designed 
to preclude recurrence.
    NRC also acknowledges that Westinghouse has taken some actions to 
close post-restart CAL items 1, 3, and 5, but are not yet complete. 
Therefore, post-restart CAL items 1, 3, and 5, as modified below, are 
transferred to this CO. Upon completion of these items, Westinghouse 
will notify the NRC Region II Administrator.
    a. CAL Item 1--Westinghouse shall implement the remaining 
corrective actions to prevent recurrence identified in their RCA.
    b. CAL Item 3--Westinghouse shall conduct effectiveness reviews of 
corrective actions to prevent recurrence specified in their RCA.
    c. CAL Item 5--Westinghouse shall evaluate the results of the 
independent third party nuclear safety culture assessment, and any 
identified deficiencies will be entered into the CAP to track to 
completion.
    The NRC concludes that CAL post-restart items 2 and 4 are closed 
because these items will be sampled as part of the NRC's inspection 
program.
    The NRC concludes that CAL post-restart item 6 is closed because of 
the extensive corrective actions completed by Westinghouse to date.
    13. Within three (3) months of completion of the terms of the CO, 
Westinghouse will provide the NRC with a letter discussing its basis 
for concluding that the CO has been satisfied.
    14. In consideration of the commitments delineated herein, the NRC 
agrees to refrain from proposing a civil penalty or issuing a Notice of 
Violation for all four AVs identified in NRC Inspection Report 70-1151/
2017-007 (EA-16-173).
    15. The NRC and Westinghouse agree that the above elements will be 
incorporated into a CO.
    16. This agreement is binding upon successors and assigns of 
Westinghouse.
    On August 8, 2017, Westinghouse consented to issuance of this CO 
with the commitments, as described in Section V below. Westinghouse 
further agreed that this CO is to be effective upon issuance and that 
it has waived its right to a hearing.

IV

    Because Westinghouse has taken corrective actions to address NRC 
concerns, as set forth in Section III above, and has agreed to take 
additional corrective actions as set forth in Section V below, the NRC 
has concluded that its concerns can be resolved through issuance of 
this CO.
    I find that Westinghouse's commitments as set forth in Section V 
are acceptable and necessary and conclude that with these commitments, 
the public health and safety are reasonably assured. In view of the 
foregoing, I have determined that public health and safety require that 
Westinghouse's commitments be confirmed by this CO. Based on the

[[Page 37906]]

above and Westinghouse's consent, this CO is effective upon issuance.

V

    Accordingly, pursuant to Sections 104b., 161b., 161i., 161o., 182, 
and 186 of the Atomic Energy Act of 1954, as amended, and the 
Commission's regulations in 10 CFR 2.202 and 10 CFR part 70, it is 
hereby ordered, that License No. SNM-1107 is modified as follows:
    1. In recognition of the corrective actions taken in response to 
the four violations, as discussed at the ADR, and in response to the 
Confirmatory Action Letter dated August 11, 2016 (ML16224B082), 
Westinghouse agrees to submit a written statement or explanation to the 
Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, 
with a copy to the Document Control Desk, Washington, DC 20555-0001, 
within 30 days of the date of the CO. This reply should include for 
each of the four violations: (1) The reason for the violation; (2) the 
corrective steps that have been taken to restore compliance; and (3) 
additional corrective actions and enhancements taken to preclude 
repetition.
    2. Approximately two years (+/- 6 months) after issuance of the CO, 
Westinghouse shall conduct an additional NSC survey by the Westinghouse 
corporate nuclear safety culture organization or an experienced 
independent third party, consistent with the depth and scope of the NSC 
survey completed under the CAL dated August 11, 2016. Identified 
deficiencies shall be entered into the CAP for tracking corrective 
actions to completion.
    3. Westinghouse shall implement improvements to reduce uranium 
carryover from the Calciner scrubbers, and implement additional design 
changes to reduce U carryover from the Blue M oven filtration system. 
Specifically:
    (1) For the calciner scrubbers, within eighteen (18) months of 
issuance of the CO, an engineering evaluation of the calciner and 
calciner off-gas scrubber design and operation shall be completed to 
determine methods to reduce uranium carry-over into the S-1030 
scrubber.
    (2) For the Blue M oven, within eighteen (18) months of issuance of 
the CO, an engineering evaluation of the Conversion Scrap Cage Blue M 
oven shall be completed to determine methods to improve the 
functionality of the Blue M oven in a wet environment and improve 
accessibility for inspection and maintenance activities.
    (3) Within three (3) years of issuance of the CO, improvements 
based on the engineering evaluations described above shall be 
implemented.
    4. Westinghouse shall notify the NRC within fifteen (15) working 
days prior to implementing changes to the modifications to the S-1030 
scrubber system, as discussed below. This requirement ends once the 
Regional Administrator determines that the CO has been satisfied. These 
modifications were incorporated as corrective actions prior to the 
October 20, 2016, system restart authorization (ML16294A296) and 
support, in part, the safety basis for the S-1030 scrubber. 
Specifically, these modifications are:
    (1) The plenums for the scrap cage Blue M oven hoods shall be 
equipped with a filter to capture at least 95% of the mass entrained in 
the air stream based on particle size distribution and the 
manufacturer's published efficiency data.
    (2) Packing baskets were implemented to permit complete removal and 
inspection of the packed media and to maintain clearance between the 
packed media and the scrubber floor.
    (3) A feed and bleed system for the scrubber recirculating liquid 
shall be maintained at a minimum output flow of 0.5 gallons per minute. 
If feed and bleed is not available, a controlled shutdown of the 
scrubber shall be initiated in accordance with plant procedures.
    (4) The scrubber shall be opened to remove the packed media 
baskets, to clean and inspect the inlet transition and scrubber body on 
a quarterly basis.
    (5) Weekly visual inspections of the scrubber inlet transition 
shall be conducted.
    5. Within two (2) years of issuance of the CO, Westinghouse shall 
develop and implement additional methods to monitor system parameters 
that are early indicators of an abnormal accumulation in the S-1030 
scrubber from a process upset that could challenge the accumulation 
rate and/or criticality safety mass limits. The methods will provide 
timely indications to enable the operators to take appropriate actions 
in accordance with approved procedures.
    6. Within eighteen (18) months of issuance of the CO, Westinghouse 
shall develop and implement a criticality safety basis/IROFS database 
to maintain the proper flow down of the safety basis into implementing 
documents.
    7. Within six (6) months of issuance of the CO, Westinghouse shall 
develop a method to reinforce positive NSC leadership behavior and 
monitor for effectiveness in the NSC monitoring panel. Westinghouse 
shall implement such method for three (3) years, after which it may 
evaluate the need to continue this item.
    8. Within three (3) months of issuance of the CO, Westinghouse 
shall develop and implement a new metric or periodic report that 
creates an aggregate picture of the health of the criticality safety 
program. This shall include items such as IROFS challenges, trends, 
audit and inspection finding status, violations, and health of 
management measures and be made available for inspection. Identified 
deficiencies shall be evaluated in accordance with the CAP.
    9. Within nine (9) months of issuance of the CO, Westinghouse shall 
implement risk-informed standards for the preparation of procedures and 
data sheets informed by appropriate guidance in INPO 11-003, 
``Guideline for Excellence in Procedure and Work Instruction Use and 
Adherence.'' This shall consist of issuance of a procedure writers' 
guide, procedure format template, and a procedure use and adherence 
standard.
    10. The NRC agrees that issuance of this CO serves to close the CAL 
issued to Westinghouse on August 11, 2016. NRC acknowledges that 
Westinghouse has taken extensive actions to address items in the CAL 
including completing an RCA, completing a review of criticality safety 
evaluations, performing inspections to validate system design and 
operating parameters, installing physical modifications to support the 
safety basis to improve safety performance, conducting an independent 
third party nuclear safety culture assessment, and completing several 
corrective actions designed to preclude recurrence.
    The NRC also acknowledges that Westinghouse has taken some actions 
to close post-restart CAL items 1, 3, and 5, but are not yet complete. 
Therefore, post-restart CAL items 1, 3, and 5, as modified below, are 
transferred to this CO. Upon completion of these items, Westinghouse 
will notify the NRC Region II Administrator.
    a. CAL Item 1--Westinghouse shall implement the remaining 
corrective actions to prevent recurrence identified in their RCA.
    b. CAL Item 3--Westinghouse shall conduct effectiveness reviews of 
corrective actions to prevent recurrence specified in their RCA.
    c. CAL Item 5--Westinghouse shall evaluate the results of the 
independent third party nuclear safety culture assessment, and any 
identified deficiencies will be entered into the CAP to track to 
completion.
    This CO supersedes the CAL issued to Westinghouse on August 11, 
2016. Post -restart CAL items 2 and 4 will be

[[Page 37907]]

sampled as part of the NRC's inspection program.
    Post-restart CAL item 6 is closed because of the extensive 
corrective actions completed by Westinghouse to date.
    11. Within three (3) months of completing implementation of the 
terms of the CO, Westinghouse will provide the NRC with a letter 
discussing its basis for concluding that the CO has been satisfied.
    This agreement is binding upon successors and assigns of 
Westinghouse.
    Unless otherwise specified, all dates are from the date of issuance 
of the CO.
    The Regional Administrator, NRC Region II, may relax or rescind, in 
writing, any of the above conditions upon a showing by Westinghouse of 
good cause.

VI

    In accordance with 10 CFR 2.202 and 10 CFR 2.309, any person 
adversely affected by this CO, other than Westinghouse, may request a 
hearing within 30 calendar days of the date of issuance of this CO. 
Where good cause is shown, consideration will be given to extending the 
time to request a hearing. A request for extension of time must be made 
in writing to the Director, Office of Enforcement, U.S. Nuclear 
Regulatory Commission, Washington, DC 20555, and include a statement of 
good cause for the extension.
    All documents filed in the NRC adjudicatory proceedings, including 
a request for hearing, a petition for leave to intervene, any motion or 
other document filed in the proceeding prior to the submission of a 
request for hearing or petition to intervene, and documents filed by 
interested governmental entities participating under 10 CFR 2.315(c), 
must be filed in accordance with the NRC's E-Filing rule (72 FR 49139, 
August 28, 2007, as amended at 77 FR 46562, August 3, 2012). The E-
Filing process requires participants to submit and serve all 
adjudicatory documents over the internet, or in some cases to mail 
copies on electronic storage media. Detailed guidance on making 
electronic submissions may be found in the Guidance for Electronic 
Submissions to the NRC and on the NRC's Web site at http://www.nrc.gov/site-help/e-submittals.html. Participants may not submit paper copies 
of their filings unless they seek an exemption in accordance with the 
procedures described below.
    To comply with the procedural requirements of E-Filing, at least 10 
days prior to the filing deadline, the participant should contact the 
Office of the Secretary by email at [email protected], or by 
telephone at 301-415-1677, to (1) request a digital identification (ID) 
certificate, which allows the participant (or its counsel or 
representative) to digitally sign submissions and access the E-Filing 
system for any proceeding in which it is participating; and (2) advise 
the Secretary that the participant will be submitting a petition or 
other adjudicatory document (even in instances in which the 
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the 
Secretary will establish an electronic docket for the hearing in this 
proceeding if the Secretary has not already established an electronic 
docket.
    Information about applying for a digital ID certificate is 
available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals/getting-started.html. Once a participant has obtained a 
digital ID certificate and a docket has been created, the participant 
can then submit adjudicatory documents. Submissions must be in Portable 
Document Format (PDF). Additional guidance on PDF submissions is 
available on the NRC's public Web site at http://www.nrc.gov/site-help/electronic-sub-ref-mat.html. A filing is considered complete at the 
time the document is submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E-Filing system 
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of 
a transmission, the E-Filing system time-stamps the document and sends 
the submitter an email notice confirming receipt of the document. The 
E-Filing system also distributes an email notice that provides access 
to the document to the NRC's Office of the General Counsel and any 
others who have advised the Office of the Secretary that they wish to 
participate in the proceeding, so that the filer need not serve the 
document on those participants separately. Therefore, applicants and 
other participants (or their counsel or representative) must apply for 
and receive a digital ID certificate before adjudicatory documents are 
filed so that they can obtain access to the documents via the E-Filing 
system.
    A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC's Electronic 
Filing Help Desk through the ``Contact Us'' link located on the NRC's 
public Web site at http://www.nrc.gov/site-help/e-submittals.html, by 
email to [email protected], or by a toll-free call at 1-866-672-
7640. The NRC Electronic Filing Help Desk is available between 9 a.m. 
and 6 p.m., Eastern Time, Monday through Friday, excluding government 
holidays.
    Once a participant has obtained a digital ID certificate and a 
docket has been created, the participant can then submit a request for 
hearing or petition for leave to intervene through the EIE System. 
Submissions should be in Portable Document Format (PDF) in accordance 
with NRC guidance available on the NRC public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered 
complete at the time the documents are submitted through the NRC's E-
Filing system. To be timely, an electronic filing must be submitted to 
the E-Filing system no later than 11:59 p.m. Eastern Time on the due 
date. Upon receipt of a transmission, the E-Filing system time-stamps 
the document and sends the submitter an email notice confirming receipt 
of the document. The E-Filing system also distributes an email notice 
that provides access to the document to the NRC Office of the General 
Counsel and any others who have advised the Office of the Secretary 
that they wish to participate in the proceeding, so that the filer need 
not serve the documents on those participants separately. Therefore, 
applicants and other participants (or their counsel or representative) 
must apply for and receive a digital ID certificate before a hearing 
request/petition to intervene is filed so that they can obtain access 
to the document via the E-Filing system.
    A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC's Electronic 
Filing Help Desk through the ``Contact Us'' link located on the NRC's 
public Web site at http://www.nrc.gov/site-help/e-submittals.html, by 
email to [email protected], or by a toll-free call at 1-866-672-
7640. The NRC Electronic Filing Help Desk is available between 9 a.m. 
and 6 p.m., Eastern Time, Monday through Friday, excluding government 
holidays.
    Participants who believe that they have a good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
stating why there is good cause for not filing electronically and 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted by: (1) First class mail 
addressed to the Office of the Secretary of the Commission, U.S. 
Nuclear Regulatory Commission,

[[Page 37908]]

Washington, DC 20555-0001, Attention: Rulemaking and Adjudications 
Staff; or (2) courier, express mail, or expedited delivery service to 
the Office of the Secretary, 11555 Rockville Pike, Rockville, Maryland, 
20852, Attention: Rulemaking and Adjudications Staff. Participants 
filing adjudicatory documents in this manner are responsible for 
serving the document on all other participants. Filing is considered 
complete by first-class mail as of the time of deposit in the mail, or 
by courier, express mail, or expedited delivery service upon depositing 
the document with the provider of the service. A presiding officer, 
having granted an exemption request from using E-Filing, may require a 
participant or party to use E-Filing if the presiding officer 
subsequently determines that the reason for granting the exemption from 
use of E-Filing no longer exists.
    Documents submitted in adjudicatory proceedings will appear in the 
NRC's electronic hearing docket which is available to the public at 
https://adams.nrc.gov/ehd, unless excluded pursuant to an order of the 
Commission or the presiding officer. If you do not have an NRC-issued 
digital ID certificate as described above, click cancel when the link 
requests certificates and you will be automatically directed to the 
NRC's electronic hearing dockets where you will be able to access any 
publicly available documents in a particular hearing docket. 
Participants are requested not to include personal privacy information, 
such as social security numbers, home addresses, or personal phone 
numbers in their filings, unless an NRC regulation or other law 
requires submission of such information. For example, in some 
instances, individuals provide home addresses in order to demonstrate 
proximity to a facility or site. With respect to copyrighted works, 
except for limited excerpts that serve the purpose of the adjudicatory 
filings and would constitute a Fair Use application, participants are 
requested not to include copyrighted materials in their submission.
    If a person (other than Westinghouse) requests a hearing, that 
person shall set forth with particularity the manner in which his 
interest is adversely affected by this CO and shall address the 
criteria set forth in 10 CFR 2.309(d) and (f).
    If a hearing is requested by a person whose interest is adversely 
affected, the Commission will issue an order designating the time and 
place of any hearing. If a hearing is held, the issue to be considered 
at such hearing shall be whether this CO should be sustained.
    In the absence of any request for hearing, or written approval of 
an extension of time in which to request a hearing, the provisions 
specified in Section V above shall be final 30 days from the date of 
this CO without further order or proceedings. If an extension of time 
for requesting a hearing has been approved, the provisions specified in 
Section V shall be final when the extension expires if a hearing 
request has not been received.

    Dated at Atlanta, Georgia, this 9th day of August, 2017.

    For the Nuclear Regulatory Commission.
Catherine Haney,
Regional Administrator.
[FR Doc. 2017-17101 Filed 8-11-17; 8:45 am]
 BILLING CODE 7590-01-P



                                                                             Federal Register / Vol. 82, No. 155 / Monday, August 14, 2017 / Notices                                                  37903

                                                I. Obtaining Information and                            information that they do not want to be                 Dated at Rockville, Maryland, this 9th day
                                                Submitting Comments                                     publicly disclosed in their comment                   of August, 2017.
                                                                                                        submission. Your request should state                   For the Nuclear Regulatory Commission.
                                                A. Obtaining Information
                                                                                                        that the NRC does not routinely edit                  Dave Cullison,
                                                   Please refer to Docket ID NRC–2016–                  comment submissions to remove such                    NRC Clearance Officer, Office of the Chief
                                                0203 when contacting the NRC about                      information before making the comment                 Information Officer.
                                                the availability of information for this                submissions available to the public or                [FR Doc. 2017–17124 Filed 8–11–17; 8:45 am]
                                                action. You may obtain publicly-                        entering the comment submissions into                 BILLING CODE 7590–01–P
                                                available information related to this                   ADAMS.
                                                action by any of the following methods:
                                                   • Federal Rulemaking Web site: Go to                 II. Background
                                                                                                                                                              NUCLEAR REGULATORY
                                                http://www.regulations.gov and search                      Under the provisions of the                        COMMISSION
                                                for Docket ID NRC–2016–0203.                            Paperwork Reduction Act of 1995 (44
                                                   • NRC’s Agencywide Documents                         U.S.C. Chapter 35), the NRC recently                  [Docket No. 70–1151; License No. SNM–
                                                Access and Management System                            submitted a request for renewal of an                 1107; EA–16–173; NRC–2017–0176]
                                                (ADAMS): You may obtain publicly-                       existing collection of information to
                                                available documents online in the                                                                             Westinghouse Electric Company, LLC
                                                                                                        OMB for review entitled, NRC Form 64,
                                                ADAMS Public Documents collection at                    ‘‘Travel Voucher’’ (Part 1); NRC Form                 AGENCY:  Nuclear Regulatory
                                                http://www.nrc.gov/reading-rm/                          64A, ‘‘Travel Voucher’’ (Part 2); and                 Commission.
                                                adams.html. To begin the search, select                 NRC Form 64B, ‘‘Optional Travel                       ACTION: Confirmatory order; issuance.
                                                ‘‘ADAMS Public Documents’’ and then                     Voucher’’ (Part 2). The NRC hereby
                                                select ‘‘Begin Web-based ADAMS                          informs potential respondents that an                 SUMMARY:   The U.S. Nuclear Regulatory
                                                Search.’’ For problems with ADAMS,                      agency may not conduct or sponsor, and                Commission (NRC) issued a
                                                please contact the NRC’s Public                         that a person is not required to respond              confirmatory order (Order) to
                                                Document Room (PDR) reference staff at                  to, a collection of information unless it             Westinghouse Electric Company, LLC,
                                                1–800–397–4209, 301–415–4737, or by                     displays a currently valid OMB control                (the licensee), confirming the agreement
                                                email to pdr.resource@nrc.gov. A copy                   number.                                               reached in an Alternative Dispute
                                                of the collection of information and                       The NRC published a Federal                        Resolution mediation session held on
                                                related instructions may be obtained                    Register notice with a 60-day comment                 May 19, 2017, and follow-up
                                                without charge by accessing ADAMS                       period on this information collection on              discussions held between May 19, 2017,
                                                Accession ML17179A612.                                  March 31, 2017; 82 FR16074.                           and August 3, 2017. This Order will
                                                   • NRC’s PDR: You may examine and                        1. The title of the information                    ensure the licensee restores compliance
                                                purchase copies of public documents at                  collection: NRC Form 64, ‘‘Travel                     with NRC’s regulations.
                                                the NRC’s PDR, Room O1–F21, One                         Voucher’’ (Part 1); NRC Form 64A,                     DATES: The Order was issued on August
                                                White Flint North, 11555 Rockville                      ‘‘Travel Voucher’’ (Part 2); and NRC                  9, 2017.
                                                Pike, Rockville, Maryland 20852.                        Form 64B, ‘‘Optional Travel Voucher’’
                                                   • NRC’s Clearance Officer: A copy of                                                                       ADDRESSES: Please refer to Docket ID
                                                                                                        (Part 2).
                                                the collection of information and related                  2. OMB approval number: 3150–0192.                 NRC–2017–0176 when contacting the
                                                instructions may be obtained without                       3. Type of submission: Extension.                  NRC about the availability of
                                                charge by contacting the NRC’s                             4. The form number if applicable:                  information regarding this document.
                                                Clearance Officer, David Cullison,                      NRC Forms 64, 64A and 64B.                            You may obtain publicly-available
                                                Office of the Chief Information Officer,                   5. How often the collection is required            information related to this document
                                                U.S. Nuclear Regulatory Commission,                     or requested: On occasion.                            using any of the following methods:
                                                Washington, DC 20555–0001; telephone:                      6. Who will be required or asked to                   • Federal Rulemaking Web site: Go to
                                                301–415–2084; email:                                    respond: Contractors, consultants and                 http://www.regulations.gov and search
                                                INFOCOLLECTS.Resource@NRC.GOV.                          invited                                               for Docket ID NRC–2017–0176. Address
                                                                                                           NRC travelers who travel in the                    questions about NRC dockets to Carol
                                                B. Submitting Comments                                  course of conducting business for the                 Gallagher; telephone: 301–415–3463;
                                                  Please include Docket ID NRC–2016–                    NRC.                                                  email: Carol.Gallagher@nrc.gov. For
                                                0203 in the subject line of your                           7. The estimated number of annual                  technical questions, contact the
                                                comment submission, in order to ensure                  responses: 100.                                       individual listed in the FOR FURTHER
                                                that the NRC is able to make your                          8. The estimated number of annual                  INFORMATION CONTACT section of this
                                                comment submission available to the                     respondents: 100.                                     document.
                                                public in this docket.                                     9. An estimate of the total number of                 • NRC’s Agencywide Documents
                                                  The NRC cautions you not to include                   hours needed annually to comply with                  Access and Management System
                                                identifying or contact information in                   the information collection requirement                (ADAMS): You may obtain publicly-
                                                comment submissions that you do not                     or request: 100 (1 hour per form).                    available documents online in the
                                                want to be publicly disclosed in your                      10. Abstract: Consultants, contractors,            ADAMS Public Documents collection at
                                                comment submission. All comment                         and those invited by the NRC to travel                http://www.nrc.gov/reading-rm/
                                                submissions are posted at http://                       (e.g., prospective employees) must file               adams.html. To begin the search, select
                                                www.regulations.gov and entered into                    travel vouchers and trip reports in order             ‘‘ADAMS Public Documents’’ and then
                                                                                                        to be reimbursed for their travel                     select ‘‘Begin Web-based ADAMS
sradovich on DSK3GMQ082PROD with NOTICES




                                                ADAMS. Comment submissions are not
                                                routinely edited to remove identifying                  expenses. The information collected                   Search.’’ For problems with ADAMS,
                                                or contact information.                                 includes the name, address, social                    please contact the NRC’s Public
                                                  If you are requesting or aggregating                  security number, and the amount to be                 Document Room (PDR) reference staff at
                                                comments from other persons for                         reimbursed. Travel expenses that are                  1–800–397–4209, 301–415–4737, or by
                                                submission to the OMB, then you                         reimbursed are confined to those                      email to pdr.resource@nrc.gov. The
                                                should inform those persons not to                      expenses essential to the transaction of              ADAMS accession number for each
                                                include identifying or contact                          official business for an approved trip.               document referenced (if it is available in


                                           VerDate Sep<11>2014   16:45 Aug 11, 2017   Jkt 241001   PO 00000   Frm 00065   Fmt 4703   Sfmt 4703   E:\FR\FM\14AUN1.SGM   14AUN1


                                                37904                        Federal Register / Vol. 82, No. 155 / Monday, August 14, 2017 / Notices

                                                ADAMS) is provided the first time that                  U in the scrubber, exceeding the mass                 Westinghouse advised the NRC of its
                                                it is mentioned in this document.                       limit in the Criticality Safety Evaluation            desire to participate in the Agency’s
                                                   • NRC’s PDR: You may examine and                     (CSE) of 29 kg U.                                     ADR program to resolve the
                                                purchase copies of public documents at                     The scrubber was shut down on July                 enforcement aspects of this matter.
                                                the NRC’s PDR, Room O1–F21, One                         14, 2016, when the determination was
                                                                                                        made by the licensee that the mass limit              III
                                                White Flint North, 11555 Rockville
                                                Pike, Rockville, Maryland 20852.                        in the CSE had been exceeded. The                        On May 19, 2017, the NRC and
                                                FOR FURTHER INFORMATION CONTACT:                        licensee reported this event to the NRC               Westinghouse met in an ADR session
                                                Scott Sparks, Region II, U.S. Nuclear                   as a 24-hour event due to a high                      mediated by a professional mediator,
                                                Regulatory Commission, Atlanta,                         consequence event being ‘‘unlikely’’ (EN              arranged through Cornell University’s
                                                Georgia 30303–1257; telephone: 404–                     52090). On July 31, 2016, the event                   Institute on Conflict Resolution.
                                                997–4422; email: Scott.Sparks@nrc.gov.                  report was updated to a one hour report               Additional discussions were held
                                                                                                        per 10 CFR 70 Appendix A (a)(4)                       between the NRC and Westinghouse
                                                SUPPLEMENTARY INFORMATION: The text of
                                                                                                        because no items relied upon for safety               between May 19, 2017, and August 3,
                                                the Order is attached.                                                                                        2017, to resolve the enforcement aspects
                                                                                                        (IROFS) remained available and reliable
                                                  Dated at Atlanta, Georgia, this 9th day of            to perform their function.                            of this matter. ADR is a process in
                                                August, 2017.                                              On August 11, 2016, the NRC issued                 which a neutral mediator with no
                                                  For the Nuclear Regulatory Commission.                a Confirmatory Action Letter (CAL) to                 decision-making authority assists the
                                                Catherine Haney,                                        Westinghouse (ML16224B082). The                       parties in reaching an agreement or
                                                Regional Administrator.                                 purpose of the CAL was to confirm the                 resolving any differences regarding their
                                                                                                        commitments made by Westinghouse                      dispute. This CO is issued pursuant to
                                                NUCLEAR REGULATORY                                                                                            the agreement reached during the ADR
                                                                                                        regarding additional actions
                                                COMMISSION                                                                                                    process. The elements of the agreement
                                                                                                        Westinghouse will take in response to
                                                [Docket No. 70–1151; License No. SNM–                   the U buildup reported to the NRC in                  consist of the following:
                                                  1107; EA–16–173; NRC–2017–0176]                       July 2016. These actions were intended                   1. Westinghouse acknowledges that
                                                In the Matter of Westinghouse Electric                  to ensure that the causes of the U                    four violations occurred, as stated in
                                                  Company, LLC                                          buildup have been adequately identified               NRC Inspection Report 70–1151/2017–
                                                CONFIRMATORY ORDER (EFFECTIVE                           and evaluated and that appropriate                    007.
                                                  UPON ISSUANCE)                                        corrective actions have been                             2. Based on ADR, the parties agreed
                                                                                                        implemented to improve the                            that the safety significance of violations
                                                I
                                                                                                        performance of the Nuclear Criticality                described in Section II above is
                                                   Westinghouse Electric Company                        Safety (NCS) program.                                 characterized as escalated enforcement
                                                (Westinghouse, or the licensee) is the                     On September 27, 2016, the NRC                     as described in the NRC Enforcement
                                                holder of NRC License No. SNM–1107,                     completed an Augmented Inspection at                  Policy.
                                                issued by the U.S. Nuclear Regulatory                   the Westinghouse facility, the details of                3. Approximately two years (+/¥ 6
                                                Commission (NRC or Commission)                          which are documented in NRC                           months) after issuance of the CO,
                                                pursuant to 10 CFR part 70 on                           Inspection Report 70–1151/2016–007                    Westinghouse shall conduct an
                                                September 30, 2007. The license                         (ML16301A001).                                        additional Nuclear Safety Culture (NSC)
                                                authorizes the operation of the                            A follow-up NRC inspection (70–                    survey by the Westinghouse corporate
                                                Columbia Fuel Fabrication Facility                      1151/2017–007) was also conducted, the                nuclear safety culture organization or an
                                                (CFFF) in accordance with the                           results of which were issued on                       experienced independent third party,
                                                conditions specified therein. The                       February 27, 2017 (ML17058A448). This                 consistent with the depth and scope of
                                                facility is located on the licensee’s site              inspection report identified the                      the NSC survey completed under the
                                                in Hopkins, South Carolina.                             following four Apparent Violations                    CAL dated August 11, 2016. Identified
                                                   This Confirmatory Order (CO) is the                  (AVs), all of which were considered for               deficiencies shall be entered into the
                                                result of an agreement reached during                   escalated enforcement in accordance                   corrective action program (CAP) for
                                                an alternative dispute resolution (ADR)                 with the NRC’s Enforcement Policy:                    tracking corrective actions to
                                                mediation session conducted on May                         1. An AV was identified for failure to             completion.
                                                19, 2017, and follow-up discussions                     ensure criticality accident sequences                    4. Westinghouse shall implement
                                                held between May 19, 2017, and August                   remain highly unlikely, as required by                improvements to reduce uranium
                                                3, 2017.                                                Title 10 of the Code of Federal                       carryover from the Calciner scrubbers,
                                                                                                        Regulations (10 CFR) 10 CFR 70.61(b).                 and implement additional design
                                                II
                                                                                                           2. An AV was identified for failure to             changes to reduce U carryover from the
                                                   On May 28, 2016, as part of the                      assure that under normal and credible                 Blue M oven filtration system.
                                                licensee’s routine maintenance                          abnormal conditions, all nuclear                      Specifically:
                                                activities, the licensee started the S–                 processes were subcritical including use                 (1) For the calciner scrubbers, within
                                                1030 scrubber inspection and cleanout                   of an approved margin of subcriticality,              eighteen (18) months of issuance of the
                                                activities. The licensee completed the                  as required by 10 CFR 70.61(d).                       CO, an engineering evaluation of the
                                                S–1030 scrubber cleanout activities on                     3. An AV was identified for failure to             calciner and calciner off-gas scrubber
                                                June 1, 2016, removing a total of 197                   establish adequate management                         design and operation shall be completed
                                                kilograms (kg) of material. The scrubber                measures to ensure that items relied on               to determine methods to reduce
                                                was subsequently restarted following
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                        for safety (IROFS) perform their                      uranium carry-over into the S–1030
                                                the maintenance outage on June 2, 2016.                 function when needed, as required by                  scrubber.
                                                On July 13, 2016, the preliminary                       10 CFR 70.62(d).                                         (2) For the Blue M oven, within
                                                results of samples taken of the material                   4. An AV was identified for failure to             eighteen (18) months of issuance of the
                                                removed from the S–1030 scrubber                        make a one hour report, as required by                CO, an engineering evaluation of the
                                                indicated a 40–50% concentration of                     Appendix A (a)(4) of 10 CFR part 70.                  Conversion Scrap Cage Blue M oven
                                                uranium (U) enriched to less than 5%.                      In response to the NRC’s inspection                shall be completed to determine
                                                This equates to approximately 100 kg of                 report of February 27, 2017,                          methods to improve the functionality of


                                           VerDate Sep<11>2014   16:45 Aug 11, 2017   Jkt 241001   PO 00000   Frm 00066   Fmt 4703   Sfmt 4703   E:\FR\FM\14AUN1.SGM   14AUN1


                                                                             Federal Register / Vol. 82, No. 155 / Monday, August 14, 2017 / Notices                                            37905

                                                the Blue M oven in a wet environment                    CFFF presented training on lessons                    Westinghouse will notify the NRC
                                                and improve accessibility for inspection                learned from the scrubber event at Fuel               Region II Administrator.
                                                and maintenance activities.                             Cycle Information Exchange (an                           a. CAL Item 1—Westinghouse shall
                                                   (3) Within three (3) years of issuance               industry-wide forum), including NSC                   implement the remaining corrective
                                                of the CO, improvements based on the                    and criticality safety standards aspects.             actions to prevent recurrence identified
                                                engineering evaluations described above                    8. Within eighteen (18) months of                  in their RCA.
                                                shall be implemented.                                   issuance of the CO, Westinghouse shall                   b. CAL Item 3—Westinghouse shall
                                                   5. In response to the May 2016 event,                develop and implement a criticality                   conduct effectiveness reviews of
                                                Westinghouse implemented several                        safety basis/IROFS database to help                   corrective actions to prevent recurrence
                                                modifications to the S–1030 scrubber                    maintain the proper flow down of the                  specified in their RCA.
                                                system, as part of its overall corrective               safety basis into implementing                           c. CAL Item 5—Westinghouse shall
                                                actions to preclude recurrence and                      documents.                                            evaluate the results of the independent
                                                enhance performance. These                                 9. Within six (6) months of issuance               third party nuclear safety culture
                                                modifications were considered by the                    of the CO, Westinghouse shall develop                 assessment, and any identified
                                                NRC, under the CAL, in support of a                     a method to reinforce positive NSC                    deficiencies will be entered into the
                                                safety basis to authorize restart of                    leadership behavior and monitor for                   CAP to track to completion.
                                                conversion process equipment and the                    effectiveness in the NSC monitoring                      The NRC concludes that CAL post-
                                                S–1030 scrubber system, as documented                   panel. Westinghouse shall implement                   restart items 2 and 4 are closed because
                                                in the NRC’s letter to Westinghouse                     such method for three years, after which              these items will be sampled as part of
                                                dated October 20, 2016 (ML16294A296).                   it may evaluate the need to continue                  the NRC’s inspection program.
                                                The modifications included but were                     this item.                                               The NRC concludes that CAL post-
                                                not limited to:                                            10. Within three (3) months of                     restart item 6 is closed because of the
                                                   (1) The plenums for the scrap cage                   issuance of the CO, Westinghouse shall                extensive corrective actions completed
                                                Blue M oven hoods were equipped with                    develop and implement a new metric or                 by Westinghouse to date.
                                                a filter to capture at least 95% of the                 periodic report that creates an aggregate                13. Within three (3) months of
                                                mass entrained in the air stream based                  picture of the health of the criticality              completion of the terms of the CO,
                                                on particle size distribution and the                   safety program. This shall include items              Westinghouse will provide the NRC
                                                manufacturer’s published efficiency                     such as IROFS challenges, trends, audit               with a letter discussing its basis for
                                                data.                                                   and inspection finding status,                        concluding that the CO has been
                                                   (2) Packing baskets were implemented                 violations, and health of management                  satisfied.
                                                to permit complete removal and                          measures and be made available for                       14. In consideration of the
                                                inspection of the packed media and to                   inspection. Identified deficiencies shall             commitments delineated herein, the
                                                maintain clearance between the packed                   be evaluated in accordance with the                   NRC agrees to refrain from proposing a
                                                media and the scrubber floor.                           CAP.                                                  civil penalty or issuing a Notice of
                                                   (3) A feed and bleed system for the                     11. Within nine (9) months,                        Violation for all four AVs identified in
                                                scrubber recirculating liquid was                       Westinghouse shall implement risk-                    NRC Inspection Report 70–1151/2017–
                                                maintained at a minimum output flow                     informed standards for the preparation                007 (EA–16–173).
                                                of 0.5 gallons per minute. If feed and                  of procedures and data sheets informed                   15. The NRC and Westinghouse agree
                                                bleed is not available, a controlled                    by appropriate guidance in INPO 11–                   that the above elements will be
                                                shutdown of the scrubber would be                       003, ‘‘Guideline for Excellence in                    incorporated into a CO.
                                                initiated in accordance with plant                      Procedure and Work Instruction Use                       16. This agreement is binding upon
                                                procedures.                                             and Adherence.’’ This will consist of                 successors and assigns of Westinghouse.
                                                   (4) The scrubber was opened to                       issuance of a procedure writers’ guide,                  On August 8, 2017, Westinghouse
                                                remove the packed media baskets, to                     procedure format template, and a                      consented to issuance of this CO with
                                                clean and inspect the inlet transition                  procedure use and adherence standard.                 the commitments, as described in
                                                and scrubber body on a quarterly basis.                    12. The NRC agrees that issuance of                Section V below. Westinghouse further
                                                   (5) Weekly visual inspections of the                 this CO serves to close the CAL issued                agreed that this CO is to be effective
                                                scrubber inlet transition were to be                    to Westinghouse on August 11, 2016.                   upon issuance and that it has waived its
                                                conducted.                                              NRC acknowledges that Westinghouse                    right to a hearing.
                                                   6. Within two (2) years of issuance of               has taken extensive actions to address
                                                                                                        items in the CAL including completing                 IV
                                                the CO, Westinghouse shall develop and
                                                implement additional methods to                         a root cause analysis (RCA), completing                  Because Westinghouse has taken
                                                monitor system parameters that are                      a review of criticality safety evaluations,           corrective actions to address NRC
                                                early indicators of an abnormal                         performing inspections to validate                    concerns, as set forth in Section III
                                                accumulation in the S–1030 scrubber                     system design and operating parameters,               above, and has agreed to take additional
                                                from a process upset that could                         installing physical modifications to                  corrective actions as set forth in Section
                                                challenge the accumulation rate and/or                  support the safety basis to improve                   V below, the NRC has concluded that its
                                                criticality safety mass limits. The                     safety performance, conducting an                     concerns can be resolved through
                                                methods will provide timely indications                 independent third party nuclear safety                issuance of this CO.
                                                to enable the operators to take                         culture assessment, and completing                       I find that Westinghouse’s
                                                appropriate actions in accordance with                  several corrective actions designed to                commitments as set forth in Section V
                                                                                                                                                              are acceptable and necessary and
sradovich on DSK3GMQ082PROD with NOTICES




                                                approved procedures.                                    preclude recurrence.
                                                   7. A member of senior Westinghouse                      NRC also acknowledges that                         conclude that with these commitments,
                                                leadership shall present training on                    Westinghouse has taken some actions to                the public health and safety are
                                                lessons learned from the scrubber event                 close post-restart CAL items 1, 3, and 5,             reasonably assured. In view of the
                                                at an industry forum, including NSC                     but are not yet complete. Therefore,                  foregoing, I have determined that public
                                                and criticality safety standards aspects.               post-restart CAL items 1, 3, and 5, as                health and safety require that
                                                   This item was completed on June 14,                  modified below, are transferred to this               Westinghouse’s commitments be
                                                2017, when the site vice president of                   CO. Upon completion of these items,                   confirmed by this CO. Based on the


                                           VerDate Sep<11>2014   16:45 Aug 11, 2017   Jkt 241001   PO 00000   Frm 00067   Fmt 4703   Sfmt 4703   E:\FR\FM\14AUN1.SGM   14AUN1


                                                37906                        Federal Register / Vol. 82, No. 155 / Monday, August 14, 2017 / Notices

                                                above and Westinghouse’s consent, this                  engineering evaluations described above               which it may evaluate the need to
                                                CO is effective upon issuance.                          shall be implemented.                                 continue this item.
                                                                                                           4. Westinghouse shall notify the NRC                  8. Within three (3) months of issuance
                                                V                                                       within fifteen (15) working days prior to             of the CO, Westinghouse shall develop
                                                  Accordingly, pursuant to Sections                     implementing changes to the                           and implement a new metric or periodic
                                                104b., 161b., 161i., 161o., 182, and 186                modifications to the S–1030 scrubber                  report that creates an aggregate picture
                                                of the Atomic Energy Act of 1954, as                    system, as discussed below. This                      of the health of the criticality safety
                                                amended, and the Commission’s                           requirement ends once the Regional                    program. This shall include items such
                                                regulations in 10 CFR 2.202 and 10 CFR                  Administrator determines that the CO                  as IROFS challenges, trends, audit and
                                                part 70, it is hereby ordered, that                     has been satisfied. These modifications               inspection finding status, violations,
                                                License No. SNM–1107 is modified as                     were incorporated as corrective actions               and health of management measures
                                                follows:                                                prior to the October 20, 2016, system                 and be made available for inspection.
                                                  1. In recognition of the corrective                   restart authorization (ML16294A296)                   Identified deficiencies shall be
                                                actions taken in response to the four                   and support, in part, the safety basis for            evaluated in accordance with the CAP.
                                                violations, as discussed at the ADR, and                the S–1030 scrubber. Specifically, these                 9. Within nine (9) months of issuance
                                                in response to the Confirmatory Action                  modifications are:                                    of the CO, Westinghouse shall
                                                Letter dated August 11, 2016                               (1) The plenums for the scrap cage                 implement risk-informed standards for
                                                (ML16224B082), Westinghouse agrees to                   Blue M oven hoods shall be equipped                   the preparation of procedures and data
                                                submit a written statement or                           with a filter to capture at least 95% of              sheets informed by appropriate
                                                explanation to the Director, Office of                  the mass entrained in the air stream                  guidance in INPO 11–003, ‘‘Guideline
                                                Enforcement, U.S. Nuclear Regulatory                    based on particle size distribution and               for Excellence in Procedure and Work
                                                Commission, with a copy to the                          the manufacturer’s published efficiency               Instruction Use and Adherence.’’ This
                                                Document Control Desk, Washington,                      data.                                                 shall consist of issuance of a procedure
                                                DC 20555–0001, within 30 days of the                       (2) Packing baskets were implemented               writers’ guide, procedure format
                                                date of the CO. This reply should                       to permit complete removal and                        template, and a procedure use and
                                                include for each of the four violations:                inspection of the packed media and to                 adherence standard.
                                                (1) The reason for the violation; (2) the               maintain clearance between the packed                    10. The NRC agrees that issuance of
                                                corrective steps that have been taken to                media and the scrubber floor.                         this CO serves to close the CAL issued
                                                restore compliance; and (3) additional                     (3) A feed and bleed system for the                to Westinghouse on August 11, 2016.
                                                corrective actions and enhancements                     scrubber recirculating liquid shall be                NRC acknowledges that Westinghouse
                                                taken to preclude repetition.                           maintained at a minimum output flow                   has taken extensive actions to address
                                                  2. Approximately two years (+/¥ 6                     of 0.5 gallons per minute. If feed and                items in the CAL including completing
                                                months) after issuance of the CO,                       bleed is not available, a controlled                  an RCA, completing a review of
                                                Westinghouse shall conduct an                           shutdown of the scrubber shall be                     criticality safety evaluations, performing
                                                additional NSC survey by the                            initiated in accordance with plant                    inspections to validate system design
                                                Westinghouse corporate nuclear safety                   procedures.                                           and operating parameters, installing
                                                culture organization or an experienced                     (4) The scrubber shall be opened to                physical modifications to support the
                                                independent third party, consistent with                remove the packed media baskets, to                   safety basis to improve safety
                                                the depth and scope of the NSC survey                   clean and inspect the inlet transition                performance, conducting an
                                                completed under the CAL dated August                    and scrubber body on a quarterly basis.               independent third party nuclear safety
                                                11, 2016. Identified deficiencies shall be                 (5) Weekly visual inspections of the               culture assessment, and completing
                                                entered into the CAP for tracking                       scrubber inlet transition shall be                    several corrective actions designed to
                                                corrective actions to completion.                       conducted.                                            preclude recurrence.
                                                  3. Westinghouse shall implement                          5. Within two (2) years of issuance of                The NRC also acknowledges that
                                                improvements to reduce uranium                          the CO, Westinghouse shall develop and                Westinghouse has taken some actions to
                                                carryover from the Calciner scrubbers,                  implement additional methods to                       close post-restart CAL items 1, 3, and 5,
                                                and implement additional design                         monitor system parameters that are                    but are not yet complete. Therefore,
                                                changes to reduce U carryover from the                  early indicators of an abnormal                       post-restart CAL items 1, 3, and 5, as
                                                Blue M oven filtration system.                          accumulation in the S–1030 scrubber                   modified below, are transferred to this
                                                Specifically:                                           from a process upset that could                       CO. Upon completion of these items,
                                                  (1) For the calciner scrubbers, within                challenge the accumulation rate and/or                Westinghouse will notify the NRC
                                                eighteen (18) months of issuance of the                 criticality safety mass limits. The                   Region II Administrator.
                                                CO, an engineering evaluation of the                    methods will provide timely indications                  a. CAL Item 1—Westinghouse shall
                                                calciner and calciner off-gas scrubber                  to enable the operators to take                       implement the remaining corrective
                                                design and operation shall be completed                 appropriate actions in accordance with                actions to prevent recurrence identified
                                                to determine methods to reduce                          approved procedures.                                  in their RCA.
                                                uranium carry-over into the S–1030                         6. Within eighteen (18) months of                     b. CAL Item 3—Westinghouse shall
                                                scrubber.                                               issuance of the CO, Westinghouse shall                conduct effectiveness reviews of
                                                  (2) For the Blue M oven, within                       develop and implement a criticality                   corrective actions to prevent recurrence
                                                eighteen (18) months of issuance of the                 safety basis/IROFS database to maintain               specified in their RCA.
                                                CO, an engineering evaluation of the                    the proper flow down of the safety basis                 c. CAL Item 5—Westinghouse shall
sradovich on DSK3GMQ082PROD with NOTICES




                                                Conversion Scrap Cage Blue M oven                       into implementing documents.                          evaluate the results of the independent
                                                shall be completed to determine                            7. Within six (6) months of issuance               third party nuclear safety culture
                                                methods to improve the functionality of                 of the CO, Westinghouse shall develop                 assessment, and any identified
                                                the Blue M oven in a wet environment                    a method to reinforce positive NSC                    deficiencies will be entered into the
                                                and improve accessibility for inspection                leadership behavior and monitor for                   CAP to track to completion.
                                                and maintenance activities.                             effectiveness in the NSC monitoring                      This CO supersedes the CAL issued to
                                                  (3) Within three (3) years of issuance                panel. Westinghouse shall implement                   Westinghouse on August 11, 2016. Post
                                                of the CO, improvements based on the                    such method for three (3) years, after                -restart CAL items 2 and 4 will be


                                           VerDate Sep<11>2014   16:45 Aug 11, 2017   Jkt 241001   PO 00000   Frm 00068   Fmt 4703   Sfmt 4703   E:\FR\FM\14AUN1.SGM   14AUN1


                                                                             Federal Register / Vol. 82, No. 155 / Monday, August 14, 2017 / Notices                                             37907

                                                sampled as part of the NRC’s inspection                 the Secretary by email at                             free call at 1–866–672–7640. The NRC
                                                program.                                                hearing.docket@nrc.gov, or by telephone               Electronic Filing Help Desk is available
                                                  Post-restart CAL item 6 is closed                     at 301–415–1677, to (1) request a digital             between 9 a.m. and 6 p.m., Eastern
                                                because of the extensive corrective                     identification (ID) certificate, which                Time, Monday through Friday,
                                                actions completed by Westinghouse to                    allows the participant (or its counsel or             excluding government holidays.
                                                date.                                                   representative) to digitally sign                        Once a participant has obtained a
                                                  11. Within three (3) months of                        submissions and access the E-Filing                   digital ID certificate and a docket has
                                                completing implementation of the terms                  system for any proceeding in which it                 been created, the participant can then
                                                of the CO, Westinghouse will provide                    is participating; and (2) advise the                  submit a request for hearing or petition
                                                the NRC with a letter discussing its                    Secretary that the participant will be                for leave to intervene through the EIE
                                                basis for concluding that the CO has                    submitting a petition or other                        System. Submissions should be in
                                                been satisfied.                                         adjudicatory document (even in                        Portable Document Format (PDF) in
                                                  This agreement is binding upon                        instances in which the participant, or its            accordance with NRC guidance
                                                successors and assigns of Westinghouse.                 counsel or representative, already holds              available on the NRC public Web site at
                                                  Unless otherwise specified, all dates                 an NRC-issued digital ID certificate).                https://www.nrc.gov/site-help/e-
                                                are from the date of issuance of the CO.                Based upon this information, the                      submittals.html. A filing is considered
                                                  The Regional Administrator, NRC                       Secretary will establish an electronic                complete at the time the documents are
                                                Region II, may relax or rescind, in                     docket for the hearing in this proceeding             submitted through the NRC’s E-Filing
                                                writing, any of the above conditions                    if the Secretary has not already                      system. To be timely, an electronic
                                                upon a showing by Westinghouse of                       established an electronic docket.                     filing must be submitted to the E-Filing
                                                good cause.                                                Information about applying for a                   system no later than 11:59 p.m. Eastern
                                                VI                                                      digital ID certificate is available on the            Time on the due date. Upon receipt of
                                                                                                        NRC’s public Web site at http://                      a transmission, the E-Filing system
                                                   In accordance with 10 CFR 2.202 and                  www.nrc.gov/site-help/e-submittals/                   time-stamps the document and sends
                                                10 CFR 2.309, any person adversely                      getting-started.html. Once a participant              the submitter an email notice
                                                affected by this CO, other than                         has obtained a digital ID certificate and             confirming receipt of the document. The
                                                Westinghouse, may request a hearing                     a docket has been created, the                        E-Filing system also distributes an email
                                                within 30 calendar days of the date of                  participant can then submit                           notice that provides access to the
                                                issuance of this CO. Where good cause                   adjudicatory documents. Submissions                   document to the NRC Office of the
                                                is shown, consideration will be given to                must be in Portable Document Format                   General Counsel and any others who
                                                extending the time to request a hearing.                (PDF). Additional guidance on PDF                     have advised the Office of the Secretary
                                                A request for extension of time must be                 submissions is available on the NRC’s                 that they wish to participate in the
                                                made in writing to the Director, Office                 public Web site at http://www.nrc.gov/                proceeding, so that the filer need not
                                                of Enforcement, U.S. Nuclear Regulatory                 site-help/electronic-sub-ref-mat.html. A              serve the documents on those
                                                Commission, Washington, DC 20555,                       filing is considered complete at the time             participants separately. Therefore,
                                                and include a statement of good cause                   the document is submitted through the                 applicants and other participants (or
                                                for the extension.                                      NRC’s E-Filing system. To be timely, an               their counsel or representative) must
                                                   All documents filed in the NRC                       electronic filing must be submitted to                apply for and receive a digital ID
                                                adjudicatory proceedings, including a                   the E-Filing system no later than 11:59               certificate before a hearing request/
                                                request for hearing, a petition for leave               p.m. Eastern Time on the due date.                    petition to intervene is filed so that they
                                                to intervene, any motion or other                       Upon receipt of a transmission, the E-                can obtain access to the document via
                                                document filed in the proceeding prior                  Filing system time-stamps the document                the E-Filing system.
                                                to the submission of a request for                      and sends the submitter an email notice                  A person filing electronically using
                                                hearing or petition to intervene, and                   confirming receipt of the document. The               the NRC’s adjudicatory E-Filing system
                                                documents filed by interested                           E-Filing system also distributes an email             may seek assistance by contacting the
                                                governmental entities participating                     notice that provides access to the                    NRC’s Electronic Filing Help Desk
                                                under 10 CFR 2.315(c), must be filed in                 document to the NRC’s Office of the                   through the ‘‘Contact Us’’ link located
                                                accordance with the NRC’s E-Filing rule                 General Counsel and any others who                    on the NRC’s public Web site at http://
                                                (72 FR 49139, August 28, 2007, as                       have advised the Office of the Secretary              www.nrc.gov/site-help/e-
                                                amended at 77 FR 46562, August 3,                       that they wish to participate in the                  submittals.html, by email to
                                                2012). The E-Filing process requires                    proceeding, so that the filer need not                MSHD.Resource@nrc.gov, or by a toll-
                                                participants to submit and serve all                    serve the document on those                           free call at 1–866–672–7640. The NRC
                                                adjudicatory documents over the                         participants separately. Therefore,                   Electronic Filing Help Desk is available
                                                internet, or in some cases to mail copies               applicants and other participants (or                 between 9 a.m. and 6 p.m., Eastern
                                                on electronic storage media. Detailed                   their counsel or representative) must                 Time, Monday through Friday,
                                                guidance on making electronic                           apply for and receive a digital ID                    excluding government holidays.
                                                submissions may be found in the                         certificate before adjudicatory                          Participants who believe that they
                                                Guidance for Electronic Submissions to                  documents are filed so that they can                  have a good cause for not submitting
                                                the NRC and on the NRC’s Web site at                    obtain access to the documents via the                documents electronically must file an
                                                http://www.nrc.gov/site-help/e-                         E-Filing system.                                      exemption request, in accordance with
                                                submittals.html. Participants may not                      A person filing electronically using               10 CFR 2.302(g), with their initial paper
                                                                                                                                                              filing stating why there is good cause for
sradovich on DSK3GMQ082PROD with NOTICES




                                                submit paper copies of their filings                    the NRC’s adjudicatory E-Filing system
                                                unless they seek an exemption in                        may seek assistance by contacting the                 not filing electronically and requesting
                                                accordance with the procedures                          NRC’s Electronic Filing Help Desk                     authorization to continue to submit
                                                described below.                                        through the ‘‘Contact Us’’ link located               documents in paper format. Such filings
                                                   To comply with the procedural                        on the NRC’s public Web site at http://               must be submitted by: (1) First class
                                                requirements of E-Filing, at least 10                   www.nrc.gov/site-help/e-                              mail addressed to the Office of the
                                                days prior to the filing deadline, the                  submittals.html, by email to                          Secretary of the Commission, U.S.
                                                participant should contact the Office of                MSHD.Resource@nrc.gov, or by a toll-                  Nuclear Regulatory Commission,


                                           VerDate Sep<11>2014   16:45 Aug 11, 2017   Jkt 241001   PO 00000   Frm 00069   Fmt 4703   Sfmt 4703   E:\FR\FM\14AUN1.SGM   14AUN1


                                                37908                        Federal Register / Vol. 82, No. 155 / Monday, August 14, 2017 / Notices

                                                Washington, DC 20555–0001, Attention:                     In the absence of any request for                   (ADAMS): You may obtain publicly-
                                                Rulemaking and Adjudications Staff; or                  hearing, or written approval of an                    available documents online in the
                                                (2) courier, express mail, or expedited                 extension of time in which to request a               ADAMS Public Documents collection at
                                                delivery service to the Office of the                   hearing, the provisions specified in                  http://www.nrc.gov/reading-rm/
                                                Secretary, 11555 Rockville Pike,                        Section V above shall be final 30 days                adams.html. To begin the search, select
                                                Rockville, Maryland, 20852, Attention:                  from the date of this CO without further              ‘‘ADAMS Public Documents’’ and then
                                                Rulemaking and Adjudications Staff.                     order or proceedings. If an extension of              select ‘‘Begin Web-based ADAMS
                                                Participants filing adjudicatory                        time for requesting a hearing has been                Search.’’ For problems with ADAMS,
                                                documents in this manner are                            approved, the provisions specified in                 please contact the NRC’s Public
                                                responsible for serving the document on                 Section V shall be final when the                     Document Room (PDR) reference staff at
                                                all other participants. Filing is                       extension expires if a hearing request                1–800–397–4209, 301–415–4737, or by
                                                considered complete by first-class mail                 has not been received.                                email to pdr.resource@nrc.gov. The
                                                as of the time of deposit in the mail, or                 Dated at Atlanta, Georgia, this 9th day of          License Renewal Application is
                                                by courier, express mail, or expedited                  August, 2017.                                         available in ADAMS under Accession
                                                delivery service upon depositing the                      For the Nuclear Regulatory Commission.              No. ML17153A282.
                                                document with the provider of the                       Catherine Haney,
                                                                                                                                                                 • NRC’s PDR: You may examine and
                                                service. A presiding officer, having                                                                          purchase copies of public documents at
                                                                                                        Regional Administrator.
                                                granted an exemption request from                                                                             the NRC’s PDR, Room O1–F21, One
                                                                                                        [FR Doc. 2017–17101 Filed 8–11–17; 8:45 am]
                                                using E-Filing, may require a participant                                                                     White Flint North, 11555 Rockville
                                                or party to use E-Filing if the presiding               BILLING CODE 7590–01–P                                Pike, Rockville, Maryland 20852.
                                                officer subsequently determines that the                                                                      FOR FURTHER INFORMATION CONTACT:
                                                reason for granting the exemption from                                                                        Emmanuel Sayoc, Office of Nuclear
                                                                                                        NUCLEAR REGULATORY
                                                use of E-Filing no longer exists.                                                                             Reactor Regulation, U.S. Nuclear
                                                                                                        COMMISSION
                                                   Documents submitted in adjudicatory                                                                        Regulatory Commission, Washington DC
                                                proceedings will appear in the NRC’s                    [Docket No. 50–458; NRC–2017–0141]                    20555–0001; telephone: 301–415–4084;
                                                electronic hearing docket which is                                                                            email: Emmanuel.Sayoc@nrc.gov.
                                                available to the public at https://                     Entergy Operations, Inc.; River Bend
                                                                                                                                                              SUPPLEMENTARY INFORMATION:
                                                adams.nrc.gov/ehd, unless excluded                      Station, Unit 1
                                                pursuant to an order of the Commission                  AGENCY:  Nuclear Regulatory                           I. Introduction
                                                or the presiding officer. If you do not                 Commission.                                              The NRC received a license renewal
                                                have an NRC-issued digital ID certificate               ACTION: License renewal application;                  application (LRA) from Entergy
                                                as described above, click cancel when                   opportunity to request a hearing and to               Operations, Inc., dated May 25, 2017,
                                                the link requests certificates and you                  petition for leave to intervene.                      requesting renewal of operating license
                                                will be automatically directed to the                                                                         No. NPF–47, which authorizes Entergy
                                                NRC’s electronic hearing dockets where                  SUMMARY:   The U.S. Nuclear Regulatory                Operations, Inc., to operate RBS at 3091
                                                you will be able to access any publicly                 Commission (NRC) is considering an                    megawatts thermal. The RBS is a
                                                available documents in a particular                     application for the renewal of operating              boiling-water reactor designed by
                                                hearing docket. Participants are                        license NPF–47, which authorizes                      General Electric and is located in St.
                                                requested not to include personal                       Entergy Operations, Inc., (the applicant),            Francisville, Louisiana. Entergy
                                                privacy information, such as social                     to operate River Bend Station, Unit 1                 Operations, Inc., submitted the
                                                security numbers, home addresses, or                    (RBS). The renewed license would                      application, pursuant to part 54 of title
                                                personal phone numbers in their filings,                authorize the applicant to operate RBS                10 of the Code of Federal Regulations
                                                unless an NRC regulation or other law                   for an additional 20 years beyond the                 (10 CFR). A notice of receipt of the LRA
                                                requires submission of such                             period specified in the current license.              was published in the Federal Register
                                                information. For example, in some                       The current operating license for RBS                 on June 28, 2017 (82 FR 29344).
                                                instances, individuals provide home                     expires at midnight on August 29, 2025.                  The NRC’s staff has determined that
                                                addresses in order to demonstrate                       DATES: A request for a hearing or                     Entergy Operations, Inc. has submitted
                                                proximity to a facility or site. With                   petition for leave to intervene must be               sufficient information in accordance
                                                respect to copyrighted works, except for                filed by October 13, 2017.                            with 10 CFR 54.19, 54.21, 54.22, 54.23,
                                                limited excerpts that serve the purpose                 ADDRESSES: Please refer to Docket ID                  51.45, and 51.53(c), to enable the staff
                                                of the adjudicatory filings and would                   NRC–2017–0141 when contacting the                     to undertake a review of the application,
                                                constitute a Fair Use application,                      NRC about the availability of                         and that the application is, therefore,
                                                participants are requested not to include               information regarding this document.                  acceptable for docketing. The current
                                                copyrighted materials in their                          You may obtain publicly-available                     docket No., 50–458, for operating
                                                submission.                                             information related to this document                  license No. NPF–47, will be retained.
                                                   If a person (other than Westinghouse)                using any of the following methods:                   The determination to accept the LRA for
                                                requests a hearing, that person shall set                  • Federal Rulemaking Web site: Go to               docketing does not constitute a
                                                forth with particularity the manner in                  http://www.regulations.gov and search                 determination that a renewed license
                                                which his interest is adversely affected                for Docket ID NRC–2017–0141. Address                  should be issued, and does not preclude
                                                by this CO and shall address the criteria               questions about NRC dockets to Carol                  the NRC staff from requesting additional
                                                set forth in 10 CFR 2.309(d) and (f).                                                                         information as the review proceeds.
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                        Gallagher; telephone: 301–415–3463;
                                                   If a hearing is requested by a person                email: Carol.Gallagher@nrc.gov. For                      Before issuance of the requested
                                                whose interest is adversely affected, the               technical questions, contact the                      renewed license, the NRC will have
                                                Commission will issue an order                          individual listed in the FOR FURTHER                  made the findings required by the
                                                designating the time and place of any                   INFORMATION CONTACT section of this                   Atomic Energy Act of 1954, as amended
                                                hearing. If a hearing is held, the issue to             document.                                             (the Act), and the Commission’s rules
                                                be considered at such hearing shall be                     • NRC’s Agencywide Documents                       and regulations. In accordance with 10
                                                whether this CO should be sustained.                    Access and Management System                          CFR 54.29, the NRC may issue a


                                           VerDate Sep<11>2014   16:45 Aug 11, 2017   Jkt 241001   PO 00000   Frm 00070   Fmt 4703   Sfmt 4703   E:\FR\FM\14AUN1.SGM   14AUN1



Document Created: 2018-10-24 11:51:18
Document Modified: 2018-10-24 11:51:18
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionConfirmatory order; issuance.
DatesThe Order was issued on August 9, 2017.
ContactScott Sparks, Region II, U.S. Nuclear Regulatory Commission, Atlanta, Georgia 30303-1257; telephone: 404-997- 4422; email: [email protected]