82_FR_43974 82 FR 43794 - Department of the Air Force; Robins Air Force Base, Georgia

82 FR 43794 - Department of the Air Force; Robins Air Force Base, Georgia

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 82, Issue 180 (September 19, 2017)

Page Range43794-43797
FR Document2017-19799

The U.S. Nuclear Regulatory Commission (NRC) is considering an amendment to Materials License 42-23539-01AF, issued to the Department of the Air Force (licensee), Docket No. 030-28641, to approve a decommissioning plan (DP) for Building 181 at Robins Air Force Base (AFB), Georgia. If the DP is approved by the NRC, the licensee would be authorized to remediate residual depleted uranium (DU) from the building, prior to partial demolition of the building. As part of its review, the NRC conducted an assessment of the environmental impacts of the proposed decommissioning action. The NRC concluded that the proposed decommissioning project will have minimal impacts on the environment. This Notice provides details of the NRC's environmental assessment. Based in part on this assessment, the NRC plans to approve the proposed DP by amending the license.

Federal Register, Volume 82 Issue 180 (Tuesday, September 19, 2017)
[Federal Register Volume 82, Number 180 (Tuesday, September 19, 2017)]
[Notices]
[Pages 43794-43797]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-19799]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 030-28641; NRC-2017-0095]


Department of the Air Force; Robins Air Force Base, Georgia

AGENCY: Nuclear Regulatory Commission.

ACTION: Environmental assessment and finding of no significant impact; 
issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering an 
amendment to Materials License 42-23539-01AF, issued to the Department 
of the Air Force (licensee), Docket No. 030-28641, to approve a 
decommissioning plan (DP) for Building 181 at Robins Air Force Base 
(AFB), Georgia. If the DP is approved by the NRC, the licensee would be 
authorized to remediate residual depleted uranium (DU) from the 
building, prior to partial demolition of the building. As part of its 
review, the NRC conducted an assessment of the environmental impacts of 
the proposed decommissioning action. The NRC concluded that the 
proposed decommissioning project will have minimal impacts on the 
environment. This Notice provides details of the NRC's environmental 
assessment. Based in part on this assessment, the NRC plans to approve 
the proposed DP by amending the license.

DATES: Materials License 42-23539-01AF, Docket No. 030-28641, will be 
amended to approve the DP on or after September 19, 2017.

ADDRESSES: Please refer to Docket ID NRC-2017-0095 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2017-0095. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public

[[Page 43795]]

Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to pdr.resource@nrc.gov. The ADAMS accession number for each 
document referenced (if it is available in ADAMS) is provided the first 
time that it is mentioned in this document. In addition, for the 
convenience of the reader, the ADAMS accession numbers are provided in 
a table in the ``Availability of Documents'' section of this document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Vivian Campbell, Region IV Office, 
U.S. Nuclear Regulatory Commission, 1600 E. Lamar Blvd., Arlington, TX 
76011; telephone: 817-200-1455, email: Vivian.Campbell@nrc.gov.

SUPPLEMENTARY INFORMATION: 

I. Introduction

    The NRC is considering issuance of an amendment to Materials 
License 42-23539-01AF, issued to Department of the Air Force, approving 
the proposed DP for remediation of Building 181 at Robins AFB, Georgia 
(ADAMS Accession Nos. ML17094A481 and ML17167A420, respectively). If 
approved by the NRC, the licensee would be allowed to remediate 
residual DU from inside and underneath the building as necessary to 
meet the NRC's criteria for unrestricted use. Therefore, as required by 
part 51 of title 10 of the Code of Federal Regulations (CFR), the NRC 
performed an environmental assessment (EA) of the proposed 
decommissioning activity. Based on the results of the EA that follows, 
the NRC has determined not to prepare an environmental impact statement 
for the licensing action and is issuing a finding of no significant 
impact (FONSI).

II. Environmental Assessment

Description of the Proposed Action

    The NRC's proposed action is to amend License 42-23539-01AF to 
approve the proposed DP, as revised. The licensee would then be 
authorized to conduct decommissioning work as specified in the NRC-
approved DP. Concurrently with the approval of the proposed 
decommissioning work instructions, the NRC plans to approve the 
licensee's proposed site-specific radiological release criteria and 
final status survey plan.
    If approved, the licensee's contractor will remediate residual 
radioactive contamination and lead-based paint from the interior of the 
building using instructions provided in the DP. After completion of 
decommissioning, the contractor will conduct a final status survey of 
the building surfaces in accordance with the instructions provided in 
the DP. The residual radioactive and hazardous waste material will be 
disposed at an authorized disposal site based on sample results of the 
removed material. During building demolition, the contractor will 
radiologically survey the soil underneath portions of the building to 
ensure that the soil is not contaminated with radioactive material. If 
contaminated, the soil will be removed for disposal.
    After completion of building demolition, the contractor will 
conduct a final status survey of the land underneath the area where 
Cells 5 and 6 were previously located, to ensure that the soil does not 
contain contamination greater than the NRC-approved release criteria. 
The NRC staff plans to conduct routine inspections during 
decommissioning and the final status surveys. The NRC will also review 
and approve the licensee's final status survey results after completion 
of the decommissioning process. The NRC may elect to conduct an 
independent radiological confirmatory survey to confirm the licensee's 
final status survey results.

Need for the Proposed Action

    The purpose of the proposed action is to reduce the residual 
radioactivity within Building 181 to levels that allow the release of 
the property for unrestricted use. If the licensee conducts site 
remediation in accordance with instructions provided in the DP, the 
licensee will be in compliance with the radiological criteria for 
license termination as specified in regulation 10 CFR part 20, subpart 
E. Approval of the DP would allow the NRC to fulfill its 
responsibilities under the Atomic Energy Act to ensure protection of 
public health and safety and the environment.

Environmental Impacts of the Proposed Action

    The NRC staff considered the possible environmental impacts of the 
proposed action. The staff considered the impacts on the following 
environmental resources: (1) Land use; (2) transportation; (3) geology 
and soils; (4) water resources; (5) ecology; (6) meteorology, 
climatology, and air quality; (7) noise; (8) historical and cultural 
resources; (9) visual/scenic resources; (10) socioeconomic; (11) public 
and occupational health; and (12) waste management.
    Building 181 is located within the boundary of Robins AFB. Other 
structures and paved roads are located around the property. An airfield 
and tarmac are located nearby. The property will remain under the 
control of the Air Force during and after decommissioning. Upon 
completion of decommissioning and NRC approval of the final status 
survey results, the licensee is expected to release the land and 
remainder of the building for unrestricted use. The land use is not 
expected to change significantly as a result of this decommissioning 
project.
    The transportation resource will be impacted slightly during 
demolition of the building. Additional vehicles will be needed to 
demolish the building and to remove the demolished debris. This 
increase in transportation resources will only exist as long as 
building demolition is in progress. After completion of demolition, the 
transportation resource should return to normal. A few additional 
trucks will be needed for shipment of the radiologically contaminated 
material to a disposal site. The number of additional trucks is 
expected to be small, based on the low volume of material required to 
be disposed.
    The local geology and soils are not expected to be impacted by 
building demolition. The local soils were already impacted by the 
construction of the building and surrounding infrastructure. Although 
unlikely, if the licensee discovers contaminated soil underneath the 
building, the soil with contamination above the NRC-approved cleanup 
criteria will have to be excavated and packaged for shipment. Clean 
backfill may be needed to fill any soil removed during decommissioning. 
The area of the demolition project is small when compared to the 
overall size of the military base.
    The water resources are not expected to be impacted by building 
demolition. Based on the depth of the unsaturated zone (25 feet/7.6 
meter) and the thickness of the floor (5-6 feet/1.5-1.8 meters), the 
licensee concluded that it was unlikely that DU contamination within 
Building 181 has migrated into the groundwater. As noted in the DP, the 
contractor will try to prevent potentially contaminated water from 
exiting the building. The contractor will plug building drains during 
decommissioning work. If the buildup of water occurs in the building, 
the contractor will install containments at exit points, such as 
doorways, to prevent releases of potentially contaminated water from 
leaving the building.

[[Page 43796]]

    The demolition of the building is not expected to have an impact on 
local ecology. No critical or endangered species or habitats are 
expected to be impacted, since the building is surrounded by other 
buildings and pavement.
    The demolition of the building may have short-term impacts on air 
quality. These potential impacts include possible release of airborne 
radioactive particulates during decommissioning, airborne dust during 
demolition, and vehicle exhaust. To protect against releases of 
potentially radioactive airborne effluents, the licensee's contractor 
plans to collect outdoor air samples during decommissioning work. If 
the airborne particulate action level is exceeded, the building doors 
will be shut to minimize airborne effluents. With regards to the 
potential for airborne dust during building demolition, the demolition 
contractor is expected to take typical industrial precautions to 
minimize airborne dust including use of water suppression or 
discontinuing work during windy conditions. Finally, the work will 
result in a short term increase of vehicle exhaust during building 
demolition work. The percent increase in vehicle exhaust is expected to 
be small compared to the relative size of the Air Force base.
    Noise will increase during building demolition work. The increase 
in noise is expected to be limited to daytime hours and will last only 
for the duration of the work.
    No historical, cultural, visual, or scenic resources are expected 
to be impacted. Any cultural or historical resource would have been 
impacted during the construction of the building. The demolition of the 
building is not expected to impact any resources beyond the area 
already impacted by current development. The decommissioning and 
demolition of the building will not impact scenic or visual resources. 
The building is not considered historically significant, otherwise, the 
Air Force would not be demolishing it.
    The decommissioning and demolition of the building will not impact 
any social groups, and the economic impacts of the work activities are 
expected to be minimal. The Air Force has not stated what it plans to 
do with the area once the building has been partially demolished, but 
the land use will most likely be similar to what is already in place. 
The Air Force does not plan to relinquish control of the area after 
building demolition, and the footprint of the building will continue to 
remain within the boundary of Robins AFB.
    The decommissioning contractor will provide measures to control 
public and occupational health during work. For example, the 
decommissioning contractor will monitoring workers for exposure to 
airborne radioactivity. The demolition contractor is expected to 
implement typical industrial safety controls such as issuance of safety 
equipment to workers, control of work area boundaries, and suppression 
of dust. As part of its review, the NRC considered the impacts of 
residual radioactivity that may remain within building rubble or 
subsurface soil. The licensee proposed cleanup criteria that is 
protective of human health and safety. The licensee's contractor is 
expected to remove the residual radioactive contamination to levels 
that are at or below the cleanup criteria, an action that is protective 
of public health and safety. Details about the NRC's analysis of the 
cleanup criteria are provided in a separate Safety Evaluation Report 
(ADAMS Accession No. ML17193A222).
    Finally, the decommissioning contractor established procedures for 
disposal of waste material. The DP indicates that the contractor plans 
to sample the waste material, to identify the levels of radiological 
and hazardous materials present. As noted earlier, the contractor will 
also remove lead-based paint as part of the work project. The 
concentrations of radioactive and hazardous wastes in the material will 
dictate how the material will be packaged and transported, and the 
concentrations will be used to identify the disposal sites that can 
accept this material for disposal. The demolition contractor is 
expected to sample the rubble to ensure that the material meets the 
standards for the chosen waste landfill. Liquid wastes are not expected 
to be created.
    In summary, the proposed decommissioning and building demolition 
are not expected to have significant, long-term impacts on 
environmental resources. Additional details about the NRC's 
environmental review are provided in an expanded EA (ADAMS Accession 
No. ML17207A232).

Environmental Impacts of the Alternatives to the Proposed Action

    As an alternative to the proposed action, the staff considered 
denial of the proposed action (i.e., the ``no-action'' alternative). 
The no-action alternative assumes that the status quo is maintained. 
With respect to the Building 181 project, the no-action alternative 
means that the licensee would not be allowed to conduct decommissioning 
work, and the contaminated building surfaces will continue to remain 
onsite at Robins AFB.
    The no-action alternative is not acceptable because it violates the 
NRC's Timeliness Rule regulations specified in 10 CFR 30.36. The 
Timeliness Rule requires licensees to decommission their facilities in 
a timely manner when licensed activities have permanently ceased. In 
addition, the radioactive contamination at Building 181 currently 
exceeds the radiological criteria for license termination as specified 
in 10 CFR part 20, subpart E. Approval of the no-action alternative 
will prevent the licensee from conducting decommissioning work as 
necessary to release the site for unrestricted use under Subpart E 
requirements. Accordingly, the NRC staff eliminated the no-action 
alternative from consideration.

Agencies and Persons Consulted

    The NRC staff consulted with the Georgia Department of Natural 
Resources, Radioactive Materials Program, regarding the EA of the 
proposed action (ADAMS Accession No. ML17193A244). The State's comments 
are discussed below.
    The NRC staff determined that the proposed action will not affect 
endangered species or critical habitats, because the project is located 
within an area that was fully developed. Therefore, no further 
consultations were deemed necessary under Section 7 of the Endangered 
Species Act. Likewise, the NRC staff determined that the proposed 
action is not the type of activity that has the potential to impact 
historic properties, in part, because the building has not been 
designated as a historic property by the Air Force. Therefore, no 
further consultation was determined to be necessary under Section 106 
of the National Historic Preservation Act.

Discussion of Comments

    By email dated August 14, 2017 (ADAMS Accession No. ML17227A184), 
the State of Georgia suggested that once demolition is complete and 
soil contamination surveys are accomplished, if these surveys reveal 
any soil contamination, a groundwater survey should be conducted. In 
the past, the State has seen instances of groundwater contamination, 
for example, around a contaminated vault that had to be remediated. 
While there is no evidence of soil contamination beneath Building 181, 
the State believes that sampling of the groundwater is prudent if the 
soil is contaminated. The NRC staff informed the licensee of the

[[Page 43797]]

State's comments, and the NRC plans to review the results of the 
licensee's soil contamination survey.

III. Finding of No Significant Impact

    The NRC staff have concluded that the proposed decommissioning 
project at Robins AFB, Georgia, will have minimal impacts on the 
environment. The NRC staff considered the impacts on land use, 
transportation, geology and soils, water resources, ecology, air 
quality, noise, historical and cultural resources, visual and scenic 
resources, socioeconomic resources, public and occupational health, and 
waste management. The staff also determined that the affected 
environment and the environmental impacts associated with the 
decommissioning of Building 181 are bounded by the impacts evaluated by 
NUREG-1496, Volume 1, ``Generic Environmental Impact Statement in 
Support of Rulemaking on Radiological Criteria for License Termination 
of NRC-Licensed Nuclear Facilities'' (ADAMS Accession No. ML042310492).
    The staff finds that the proposed decommissioning complies with 10 
CFR 20.1402, which provides the radiological criteria for unrestricted 
use. Further, the licensee will perform the remediation work under an 
NRC license, using an NRC-approved decommissioning plan, which will 
help ensure that the licensee and its contractor will establish and 
implement programs to protect workers, the public, and the environment. 
Further, the NRC plans to conduct inspections during work activities. 
Past NRC experiences with decommissioning activities at similar sites 
suggest that public and worker exposures to radioactivity will be far 
below the limits specified in 10 CFR part 20.
    The NRC staff have prepared this EA in support of the proposed 
action to amend NRC Materials License 42-23539-01AF to approve the 
licensee's proposed DP for Building 181 at Robins AFB. On the basis of 
this EA, the NRC has concluded that there are no significant 
environmental impacts and the license amendment does not warrant the 
preparation of an environmental impact statement. Accordingly, it has 
been determined that a FONSI is appropriate.

IV. Availability of Documents

    The documents identified in the following table are available to 
interested persons through one or more of the following methods, as 
indicated.

------------------------------------------------------------------------
                   Document                       ADAMS  Accession No.
------------------------------------------------------------------------
U.S. Department of the Air Force, ``Updated    ML17094A481
 Decommissioning Plan dated February 2017 for
 Building 181 at Robins Air Force Base,
 Georgia,'' March 21, 2017.
U.S. Department of the Air Force, ``Building   ML17167A420
 181 Robins Air Force Base Decommissioning
 Plan,'' June 13, 2017.
U.S. Nuclear Regulatory Commission, ``Robins   ML17193A244
 AFB Consultation Letter with State of
 Georgia,'' July 24, 2017.
U.S. Nuclear Regulatory Commission, ``Memo to  ML17207A232
 File--Building 181 Robins AFB Georgia
 Environmental Assessment,'' September 19,
 2017.
U.S. Nuclear Regulatory Commission, ``Memo to  ML17193A222
 File--Building 181, Robins AFB Georgia
 Safety Evaluation Report,'' September 19,
 2017.
State of Georgia, ``State of Georgia's Review  ML17227A184
 and Comments on Proposed EA and SER for
 Robins AFB, Georgia,'' August 14, 2017.
U.S. Nuclear Regulatory Commission, NUREG-     ML042310492
 1496, Volume 1, Generic Environmental Impact
 Statement in Support of Rulemaking on
 Radiological Criteria for License
 Termination of NRC-Licensed Nuclear
 Facilities, Main Report, July 31, 1997.
------------------------------------------------------------------------


    Dated at Arlington, Texas, this 31st day of August 2017.

    For the Nuclear Regulatory Commission.
Mark R. Shaffer,
Director, Division of Nuclear Materials Safety, Region IV Office.
[FR Doc. 2017-19799 Filed 9-18-17; 8:45 am]
 BILLING CODE 7590-01-P



                                                    43794                               Federal Register / Vol. 82, No. 180 / Tuesday, September 19, 2017 / Notices

                                                      Burden estimates for each reporting
                                                    institution type are shown in Table 2.

                                                                                                                    TABLE 2—BURDEN ESTIMATES FOR THE 2017 GSS
                                                                                                                                                                                                       Respondents                   Average               Total burden
                                                                                                                  School type                                                                           (number of                   burden                  (hours)
                                                                                                                                                                                                         schools)                    (hours)

                                                    Master’s Only ...............................................................................................................................                      339                       5.9              2,000
                                                    Master’s/Doctorate: 15 or fewer units .........................................................................................                                    205                      17.1              3,506
                                                    Master’s/Doctorate: More than 15 units ......................................................................................                                      282                      86.6             24,421
                                                    FFRDCs .......................................................................................................................................                      43                       3.7                159

                                                          Estimated total ......................................................................................................................                       869      ........................         30,086



                                                      The number of units in the                                               2019, and the estimated burden for                                         respectively (see Table 3). Estimates of
                                                    subsequent survey cycle will include                                       those years will increase by 159 hours                                     the 2018 GSS burden are 30,262 hours.
                                                    the institutions in the previous year                                      from 43 FFRDCs (based on 100 percent                                       An additional 800 hours across three
                                                    plus an approximate 1 percent increase                                     response rate in 2015 with the average                                     years are requested to conduct
                                                    in institutions. The FFRDC postdoc data                                    burden of 3.7 hours per FFRDC) to a                                        methodological testing.
                                                    collection will take place in 2017 and                                     total of 30,086 and 30,738 hours,

                                                                                                              TABLE 3—TOTAL BURDEN ESTIMATES FOR 2017–19 GSS
                                                                                                                                                                                                                                 Respondents               Total burden
                                                                                                                              Survey cycle                                                                                        (number of                 (hours)
                                                                                                                                                                                                                                   schools)

                                                    2017 GSS ................................................................................................................................................................                     869            30,086
                                                        GSS Institutions ................................................................................................................................................                         826            29,927
                                                        FFRDCs ............................................................................................................................................................                         43              159
                                                    2018 GSS ................................................................................................................................................................                     836            30,262
                                                    2019 GSS ................................................................................................................................................................                     888            30,738
                                                        GSS Institutions ................................................................................................................................................                         845            30,579
                                                        FFRDCs ............................................................................................................................................................                         43              159
                                                    Future methodological testing (across all 3 years) .................................................................................................                        ........................            800

                                                        Total estimated burden .....................................................................................................................................                          2,593              91,886
                                                    Estimated average annual burden ..........................................................................................................................                                  864              30,629



                                                      The total estimated respondent                                           amendment to Materials License 42–                                         ADDRESSES:   Please refer to Docket ID
                                                    burden of the GSS, including 800 hours                                     23539–01AF, issued to the Department                                       NRC–2017–0095 when contacting the
                                                    for the methodological studies, will be                                    of the Air Force (licensee), Docket No.                                    NRC about the availability of
                                                    91,886 hours over the 3-survey                                             030–28641, to approve a                                                    information regarding this document.
                                                    clearance period.                                                          decommissioning plan (DP) for Building                                     You may obtain publicly-available
                                                      Dated: September 14, 2017.                                               181 at Robins Air Force Base (AFB),                                        information related to this document
                                                    Suzanne H. Plimpton,                                                       Georgia. If the DP is approved by the                                      using any of the following methods:
                                                    Reports Clearance Officer, National Science                                NRC, the licensee would be authorized                                         • Federal Rulemaking Web site: Go to
                                                    Foundation.                                                                to remediate residual depleted uranium                                     http://www.regulations.gov and search
                                                    [FR Doc. 2017–19889 Filed 9–18–17; 8:45 am]                                (DU) from the building, prior to partial                                   for Docket ID NRC–2017–0095. Address
                                                                                                                               demolition of the building. As part of its                                 questions about NRC dockets to Carol
                                                    BILLING CODE 7555–01–P
                                                                                                                               review, the NRC conducted an                                               Gallagher; telephone: 301–415–3463;
                                                                                                                               assessment of the environmental                                            email: Carol.Gallagher@nrc.gov. For
                                                                                                                               impacts of the proposed                                                    technical questions, contact the
                                                    NUCLEAR REGULATORY                                                                                                                                    individual listed in the FOR FURTHER
                                                    COMMISSION                                                                 decommissioning action. The NRC
                                                                                                                               concluded that the proposed                                                INFORMATION CONTACT section of this
                                                    [Docket No. 030–28641; NRC–2017–0095]                                      decommissioning project will have                                          document.
                                                                                                                               minimal impacts on the environment.                                           • NRC’s Agencywide Documents
                                                    Department of the Air Force; Robins                                                                                                                   Access and Management System
                                                    Air Force Base, Georgia                                                    This Notice provides details of the
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                                                                                               NRC’s environmental assessment. Based                                      (ADAMS): You may obtain publicly-
                                                    AGENCY:  Nuclear Regulatory                                                in part on this assessment, the NRC                                        available documents online in the
                                                    Commission.                                                                plans to approve the proposed DP by                                        ADAMS Public Documents collection at
                                                    ACTION: Environmental assessment and                                       amending the license.                                                      http://www.nrc.gov/reading-rm/
                                                    finding of no significant impact;                                                                                                                     adams.html. To begin the search, select
                                                    issuance.                                                                  DATES:Materials License 42–23539–                                          ‘‘ADAMS Public Documents’’ and then
                                                                                                                               01AF, Docket No. 030–28641, will be                                        select ‘‘Begin Web-based ADAMS
                                                    SUMMARY:The U.S. Nuclear Regulatory                                        amended to approve the DP on or after                                      Search.’’ For problems with ADAMS,
                                                    Commission (NRC) is considering an                                         September 19, 2017.                                                        please contact the NRC’s Public


                                               VerDate Sep<11>2014         17:12 Sep 18, 2017         Jkt 241001      PO 00000        Frm 00057       Fmt 4703       Sfmt 4703      E:\FR\FM\19SEN1.SGM              19SEN1


                                                                              Federal Register / Vol. 82, No. 180 / Tuesday, September 19, 2017 / Notices                                          43795

                                                    Document Room (PDR) reference staff at                  instructions provided in the DP. After                   Building 181 is located within the
                                                    1–800–397–4209, 301–415–4737, or by                     completion of decommissioning, the                    boundary of Robins AFB. Other
                                                    email to pdr.resource@nrc.gov. The                      contractor will conduct a final status                structures and paved roads are located
                                                    ADAMS accession number for each                         survey of the building surfaces in                    around the property. An airfield and
                                                    document referenced (if it is available in              accordance with the instructions                      tarmac are located nearby. The property
                                                    ADAMS) is provided the first time that                  provided in the DP. The residual                      will remain under the control of the Air
                                                    it is mentioned in this document. In                    radioactive and hazardous waste                       Force during and after
                                                    addition, for the convenience of the                    material will be disposed at an                       decommissioning. Upon completion of
                                                    reader, the ADAMS accession numbers                     authorized disposal site based on                     decommissioning and NRC approval of
                                                    are provided in a table in the                          sample results of the removed material.               the final status survey results, the
                                                    ‘‘Availability of Documents’’ section of                During building demolition, the                       licensee is expected to release the land
                                                    this document.                                          contractor will radiologically survey the             and remainder of the building for
                                                       • NRC’s PDR: You may examine and                     soil underneath portions of the building              unrestricted use. The land use is not
                                                    purchase copies of public documents at                  to ensure that the soil is not                        expected to change significantly as a
                                                    the NRC’s PDR, Room O1–F21, One                         contaminated with radioactive material.               result of this decommissioning project.
                                                    White Flint North, 11555 Rockville                      If contaminated, the soil will be                        The transportation resource will be
                                                    Pike, Rockville, Maryland 20852.                        removed for disposal.                                 impacted slightly during demolition of
                                                    FOR FURTHER INFORMATION CONTACT:                           After completion of building                       the building. Additional vehicles will be
                                                    Vivian Campbell, Region IV Office, U.S.                 demolition, the contractor will conduct               needed to demolish the building and to
                                                    Nuclear Regulatory Commission, 1600                     a final status survey of the land                     remove the demolished debris. This
                                                    E. Lamar Blvd., Arlington, TX 76011;                    underneath the area where Cells 5 and                 increase in transportation resources will
                                                    telephone: 817–200–1455, email:                         6 were previously located, to ensure that             only exist as long as building
                                                    Vivian.Campbell@nrc.gov.                                the soil does not contain contamination               demolition is in progress. After
                                                                                                            greater than the NRC-approved release                 completion of demolition, the
                                                    SUPPLEMENTARY INFORMATION:
                                                                                                            criteria. The NRC staff plans to conduct              transportation resource should return to
                                                    I. Introduction                                         routine inspections during                            normal. A few additional trucks will be
                                                       The NRC is considering issuance of an                decommissioning and the final status                  needed for shipment of the
                                                    amendment to Materials License 42–                      surveys. The NRC will also review and                 radiologically contaminated material to
                                                    23539–01AF, issued to Department of                     approve the licensee’s final status                   a disposal site. The number of
                                                    the Air Force, approving the proposed                   survey results after completion of the                additional trucks is expected to be
                                                    DP for remediation of Building 181 at                   decommissioning process. The NRC                      small, based on the low volume of
                                                    Robins AFB, Georgia (ADAMS                              may elect to conduct an independent                   material required to be disposed.
                                                    Accession Nos. ML17094A481 and                          radiological confirmatory survey to
                                                                                                                                                                     The local geology and soils are not
                                                    ML17167A420, respectively). If                          confirm the licensee’s final status
                                                                                                                                                                  expected to be impacted by building
                                                    approved by the NRC, the licensee                       survey results.
                                                                                                                                                                  demolition. The local soils were already
                                                    would be allowed to remediate residual                  Need for the Proposed Action                          impacted by the construction of the
                                                    DU from inside and underneath the                         The purpose of the proposed action is               building and surrounding infrastructure.
                                                    building as necessary to meet the NRC’s                 to reduce the residual radioactivity                  Although unlikely, if the licensee
                                                    criteria for unrestricted use. Therefore,               within Building 181 to levels that allow              discovers contaminated soil underneath
                                                    as required by part 51 of title 10 of the               the release of the property for                       the building, the soil with
                                                    Code of Federal Regulations (CFR), the                  unrestricted use. If the licensee                     contamination above the NRC-approved
                                                    NRC performed an environmental                          conducts site remediation in accordance               cleanup criteria will have to be
                                                    assessment (EA) of the proposed                         with instructions provided in the DP,                 excavated and packaged for shipment.
                                                    decommissioning activity. Based on the                  the licensee will be in compliance with               Clean backfill may be needed to fill any
                                                    results of the EA that follows, the NRC                 the radiological criteria for license                 soil removed during decommissioning.
                                                    has determined not to prepare an                        termination as specified in regulation 10             The area of the demolition project is
                                                    environmental impact statement for the                  CFR part 20, subpart E. Approval of the               small when compared to the overall size
                                                    licensing action and is issuing a finding               DP would allow the NRC to fulfill its                 of the military base.
                                                    of no significant impact (FONSI).                       responsibilities under the Atomic                        The water resources are not expected
                                                    II. Environmental Assessment                            Energy Act to ensure protection of                    to be impacted by building demolition.
                                                                                                            public health and safety and the                      Based on the depth of the unsaturated
                                                    Description of the Proposed Action                      environment.                                          zone (25 feet/7.6 meter) and the
                                                       The NRC’s proposed action is to                                                                            thickness of the floor (5–6 feet/1.5–1.8
                                                    amend License 42–23539–01AF to                          Environmental Impacts of the Proposed                 meters), the licensee concluded that it
                                                    approve the proposed DP, as revised.                    Action                                                was unlikely that DU contamination
                                                    The licensee would then be authorized                      The NRC staff considered the possible              within Building 181 has migrated into
                                                    to conduct decommissioning work as                      environmental impacts of the proposed                 the groundwater. As noted in the DP,
                                                    specified in the NRC-approved DP.                       action. The staff considered the impacts              the contractor will try to prevent
                                                    Concurrently with the approval of the                   on the following environmental                        potentially contaminated water from
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    proposed decommissioning work                           resources: (1) Land use; (2)                          exiting the building. The contractor will
                                                    instructions, the NRC plans to approve                  transportation; (3) geology and soils; (4)            plug building drains during
                                                    the licensee’s proposed site-specific                   water resources; (5) ecology; (6)                     decommissioning work. If the buildup
                                                    radiological release criteria and final                 meteorology, climatology, and air                     of water occurs in the building, the
                                                    status survey plan.                                     quality; (7) noise; (8) historical and                contractor will install containments at
                                                       If approved, the licensee’s contractor               cultural resources; (9) visual/scenic                 exit points, such as doorways, to
                                                    will remediate residual radioactive                     resources; (10) socioeconomic; (11)                   prevent releases of potentially
                                                    contamination and lead-based paint                      public and occupational health; and (12)              contaminated water from leaving the
                                                    from the interior of the building using                 waste management.                                     building.


                                               VerDate Sep<11>2014   17:12 Sep 18, 2017   Jkt 241001   PO 00000   Frm 00058   Fmt 4703   Sfmt 4703   E:\FR\FM\19SEN1.SGM   19SEN1


                                                    43796                     Federal Register / Vol. 82, No. 180 / Tuesday, September 19, 2017 / Notices

                                                       The demolition of the building is not                   The decommissioning contractor will                contaminated building surfaces will
                                                    expected to have an impact on local                     provide measures to control public and                continue to remain onsite at Robins
                                                    ecology. No critical or endangered                      occupational health during work. For                  AFB.
                                                    species or habitats are expected to be                  example, the decommissioning                             The no-action alternative is not
                                                    impacted, since the building is                         contractor will monitoring workers for                acceptable because it violates the NRC’s
                                                    surrounded by other buildings and                       exposure to airborne radioactivity. The               Timeliness Rule regulations specified in
                                                    pavement.                                               demolition contractor is expected to                  10 CFR 30.36. The Timeliness Rule
                                                       The demolition of the building may                   implement typical industrial safety                   requires licensees to decommission
                                                    have short-term impacts on air quality.                 controls such as issuance of safety                   their facilities in a timely manner when
                                                    These potential impacts include                         equipment to workers, control of work                 licensed activities have permanently
                                                    possible release of airborne radioactive                area boundaries, and suppression of                   ceased. In addition, the radioactive
                                                    particulates during decommissioning,                    dust. As part of its review, the NRC                  contamination at Building 181 currently
                                                    airborne dust during demolition, and                    considered the impacts of residual                    exceeds the radiological criteria for
                                                    vehicle exhaust. To protect against                     radioactivity that may remain within                  license termination as specified in 10
                                                    releases of potentially radioactive                     building rubble or subsurface soil. The               CFR part 20, subpart E. Approval of the
                                                    airborne effluents, the licensee’s                      licensee proposed cleanup criteria that               no-action alternative will prevent the
                                                    contractor plans to collect outdoor air                 is protective of human health and                     licensee from conducting
                                                    samples during decommissioning work.                    safety. The licensee’s contractor is                  decommissioning work as necessary to
                                                    If the airborne particulate action level is             expected to remove the residual                       release the site for unrestricted use
                                                    exceeded, the building doors will be                    radioactive contamination to levels that              under Subpart E requirements.
                                                    shut to minimize airborne effluents.                    are at or below the cleanup criteria, an              Accordingly, the NRC staff eliminated
                                                    With regards to the potential for                       action that is protective of public health            the no-action alternative from
                                                    airborne dust during building                           and safety. Details about the NRC’s                   consideration.
                                                    demolition, the demolition contractor is                analysis of the cleanup criteria are                  Agencies and Persons Consulted
                                                    expected to take typical industrial                     provided in a separate Safety Evaluation
                                                    precautions to minimize airborne dust                   Report (ADAMS Accession No.                             The NRC staff consulted with the
                                                    including use of water suppression or                   ML17193A222).                                         Georgia Department of Natural
                                                    discontinuing work during windy                            Finally, the decommissioning                       Resources, Radioactive Materials
                                                    conditions. Finally, the work will result               contractor established procedures for                 Program, regarding the EA of the
                                                    in a short term increase of vehicle                     disposal of waste material. The DP                    proposed action (ADAMS Accession No.
                                                    exhaust during building demolition                      indicates that the contractor plans to                ML17193A244). The State’s comments
                                                    work. The percent increase in vehicle                   sample the waste material, to identify                are discussed below.
                                                    exhaust is expected to be small                         the levels of radiological and hazardous                The NRC staff determined that the
                                                    compared to the relative size of the Air                materials present. As noted earlier, the              proposed action will not affect
                                                    Force base.                                             contractor will also remove lead-based                endangered species or critical habitats,
                                                       Noise will increase during building                  paint as part of the work project. The                because the project is located within an
                                                    demolition work. The increase in noise                  concentrations of radioactive and                     area that was fully developed.
                                                    is expected to be limited to daytime                    hazardous wastes in the material will                 Therefore, no further consultations were
                                                    hours and will last only for the duration               dictate how the material will be                      deemed necessary under Section 7 of
                                                    of the work.                                            packaged and transported, and the                     the Endangered Species Act. Likewise,
                                                       No historical, cultural, visual, or                  concentrations will be used to identify               the NRC staff determined that the
                                                    scenic resources are expected to be                     the disposal sites that can accept this               proposed action is not the type of
                                                    impacted. Any cultural or historical                    material for disposal. The demolition                 activity that has the potential to impact
                                                    resource would have been impacted                       contractor is expected to sample the                  historic properties, in part, because the
                                                    during the construction of the building.                rubble to ensure that the material meets              building has not been designated as a
                                                    The demolition of the building is not                   the standards for the chosen waste                    historic property by the Air Force.
                                                    expected to impact any resources                        landfill. Liquid wastes are not expected              Therefore, no further consultation was
                                                    beyond the area already impacted by                     to be created.                                        determined to be necessary under
                                                    current development. The                                   In summary, the proposed                           Section 106 of the National Historic
                                                    decommissioning and demolition of the                   decommissioning and building                          Preservation Act.
                                                    building will not impact scenic or visual               demolition are not expected to have
                                                    resources. The building is not                                                                                Discussion of Comments
                                                                                                            significant, long-term impacts on
                                                    considered historically significant,                    environmental resources. Additional                      By email dated August 14, 2017
                                                    otherwise, the Air Force would not be                   details about the NRC’s environmental                 (ADAMS Accession No. ML17227A184),
                                                    demolishing it.                                         review are provided in an expanded EA                 the State of Georgia suggested that once
                                                       The decommissioning and demolition                   (ADAMS Accession No. ML17207A232).                    demolition is complete and soil
                                                    of the building will not impact any                                                                           contamination surveys are
                                                    social groups, and the economic impacts                 Environmental Impacts of the                          accomplished, if these surveys reveal
                                                    of the work activities are expected to be               Alternatives to the Proposed Action                   any soil contamination, a groundwater
                                                    minimal. The Air Force has not stated                      As an alternative to the proposed                  survey should be conducted. In the past,
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    what it plans to do with the area once                  action, the staff considered denial of the            the State has seen instances of
                                                    the building has been partially                         proposed action (i.e., the ‘‘no-action’’              groundwater contamination, for
                                                    demolished, but the land use will most                  alternative). The no-action alternative               example, around a contaminated vault
                                                    likely be similar to what is already in                 assumes that the status quo is                        that had to be remediated. While there
                                                    place. The Air Force does not plan to                   maintained. With respect to the                       is no evidence of soil contamination
                                                    relinquish control of the area after                    Building 181 project, the no-action                   beneath Building 181, the State believes
                                                    building demolition, and the footprint                  alternative means that the licensee                   that sampling of the groundwater is
                                                    of the building will continue to remain                 would not be allowed to conduct                       prudent if the soil is contaminated. The
                                                    within the boundary of Robins AFB.                      decommissioning work, and the                         NRC staff informed the licensee of the


                                               VerDate Sep<11>2014   17:12 Sep 18, 2017   Jkt 241001   PO 00000   Frm 00059   Fmt 4703   Sfmt 4703   E:\FR\FM\19SEN1.SGM   19SEN1


                                                                              Federal Register / Vol. 82, No. 180 / Tuesday, September 19, 2017 / Notices                                          43797

                                                    State’s comments, and the NRC plans to                  Environmental Impact Statement in                     be far below the limits specified in 10
                                                    review the results of the licensee’s soil               Support of Rulemaking on Radiological                 CFR part 20.
                                                    contamination survey.                                   Criteria for License Termination of NRC-                The NRC staff have prepared this EA
                                                                                                            Licensed Nuclear Facilities’’ (ADAMS                  in support of the proposed action to
                                                    III. Finding of No Significant Impact
                                                                                                            Accession No. ML042310492).                           amend NRC Materials License 42–
                                                       The NRC staff have concluded that                       The staff finds that the proposed
                                                    the proposed decommissioning project                                                                          23539–01AF to approve the licensee’s
                                                                                                            decommissioning complies with 10 CFR
                                                    at Robins AFB, Georgia, will have                                                                             proposed DP for Building 181 at Robins
                                                                                                            20.1402, which provides the
                                                    minimal impacts on the environment.                                                                           AFB. On the basis of this EA, the NRC
                                                                                                            radiological criteria for unrestricted use.
                                                    The NRC staff considered the impacts                                                                          has concluded that there are no
                                                                                                            Further, the licensee will perform the
                                                    on land use, transportation, geology and                remediation work under an NRC                         significant environmental impacts and
                                                    soils, water resources, ecology, air                    license, using an NRC-approved                        the license amendment does not warrant
                                                    quality, noise, historical and cultural                 decommissioning plan, which will help                 the preparation of an environmental
                                                    resources, visual and scenic resources,                 ensure that the licensee and its                      impact statement. Accordingly, it has
                                                    socioeconomic resources, public and                     contractor will establish and implement               been determined that a FONSI is
                                                    occupational health, and waste                          programs to protect workers, the public,              appropriate.
                                                    management. The staff also determined                   and the environment. Further, the NRC                 IV. Availability of Documents
                                                    that the affected environment and the                   plans to conduct inspections during
                                                    environmental impacts associated with                   work activities. Past NRC experiences                   The documents identified in the
                                                    the decommissioning of Building 181                     with decommissioning activities at                    following table are available to
                                                    are bounded by the impacts evaluated                    similar sites suggest that public and                 interested persons through one or more
                                                    by NUREG–1496, Volume 1, ‘‘Generic                      worker exposures to radioactivity will                of the following methods, as indicated.

                                                                                                                                                                                                ADAMS
                                                                                                                      Document                                                               Accession No.

                                                    U.S. Department of the Air Force, ‘‘Updated Decommissioning Plan dated February 2017 for Building 181 at Robins Air Force                ML17094A481
                                                      Base, Georgia,’’ March 21, 2017.
                                                    U.S. Department of the Air Force, ‘‘Building 181 Robins Air Force Base Decommissioning Plan,’’ June 13, 2017 ......................      ML17167A420
                                                    U.S. Nuclear Regulatory Commission, ‘‘Robins AFB Consultation Letter with State of Georgia,’’ July 24, 2017 ..........................   ML17193A244
                                                    U.S. Nuclear Regulatory Commission, ‘‘Memo to File—Building 181 Robins AFB Georgia Environmental Assessment,’’ Sep-                      ML17207A232
                                                      tember 19, 2017.
                                                    U.S. Nuclear Regulatory Commission, ‘‘Memo to File—Building 181, Robins AFB Georgia Safety Evaluation Report,’’ Sep-                     ML17193A222
                                                      tember 19, 2017.
                                                    State of Georgia, ‘‘State of Georgia’s Review and Comments on Proposed EA and SER for Robins AFB, Georgia,’’ August                      ML17227A184
                                                      14, 2017.
                                                    U.S. Nuclear Regulatory Commission, NUREG–1496, Volume 1, Generic Environmental Impact Statement in Support of Rule-                     ML042310492
                                                      making on Radiological Criteria for License Termination of NRC-Licensed Nuclear Facilities, Main Report, July 31, 1997.



                                                      Dated at Arlington, Texas, this 31st day of           collection is entitled, ‘‘Fitness-for-Duty               • Federal Rulemaking Web site: Go to
                                                    August 2017.                                            Programs.’’                                           http://www.regulations.gov and search
                                                      For the Nuclear Regulatory Commission.                                                                      for Docket ID NRC–2017–0107. A copy
                                                                                                            DATES: Submit comments by October 19,
                                                    Mark R. Shaffer,                                        2017.                                                 of the collection of information and
                                                    Director, Division of Nuclear Materials Safety,         ADDRESSES: Submit comments directly
                                                                                                                                                                  related instructions may be obtained
                                                    Region IV Office.
                                                                                                            to the OMB reviewer at: Aaron Szabo,                  without charge by accessing Docket ID
                                                    [FR Doc. 2017–19799 Filed 9–18–17; 8:45 am]             Desk Officer, Office of Information and               NRC–2017–0107 on this Web site.
                                                                                                                                                                     • NRC’s Agencywide Documents
                                                    BILLING CODE 7590–01–P                                  Regulatory Affairs (3150–0146), NEOB–
                                                                                                                                                                  Access and Management System
                                                                                                            10202, Office of Management and
                                                                                                                                                                  (ADAMS): You may obtain publicly-
                                                                                                            Budget, Washington, DC 20503;
                                                    NUCLEAR REGULATORY                                                                                            available documents online in the
                                                                                                            telephone: 202–395–3621, email: oira_
                                                    COMMISSION                                                                                                    ADAMS Public Documents collection at
                                                                                                            submission@omb.eop.gov.
                                                                                                                                                                  http://www.nrc.gov/reading-rm/
                                                                                                            FOR FURTHER INFORMATION CONTACT:
                                                    [NRC–2017–0107]                                                                                               adams.html. To begin the search, select
                                                                                                            David Cullison, NRC Clearance Officer,                ‘‘ADAMS Public Documents’’ and then
                                                                                                            U.S. Nuclear Regulatory Commission,                   select ‘‘Begin Web-based ADAMS
                                                    Information Collection: Fitness-for-                    Washington, DC 20555–0001; telephone:
                                                    Duty Programs                                                                                                 Search.’’ For problems with ADAMS,
                                                                                                            301–415–2084; email:
                                                                                                                                                                  please contact the NRC’s Public
                                                    AGENCY:  Nuclear Regulatory                             INFOCOLLECTS.Resource@nrc.gov.
                                                                                                                                                                  Document Room (PDR) reference staff at
                                                    Commission.                                             SUPPLEMENTARY INFORMATION:                            1–800–397–4209, 301–415–4737, or by
                                                    ACTION: Notice of submission to the                     I. Obtaining Information and                          email to pdr.resource@nrc.gov. The
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    Office of Management and Budget;                        Submitting Comments                                   supporting statement and NRC Forms
                                                    request for comment.                                                                                          890, 891, and 892 are available in
                                                                                                            A. Obtaining Information                              ADAMS under Accession Nos.
                                                    SUMMARY:   The U.S. Nuclear Regulatory                    Please refer to Docket ID NRC–2017–                 ML17236A379, ML17013A578,
                                                    Commission (NRC) has recently                           0107 when contacting the NRC about                    ML17013A598, and ML17024A436,
                                                    submitted a request for renewal of an                   the availability of information for this              respectively.
                                                    existing collection of information to the               action. You may obtain publicly-                         • NRC’s PDR: You may examine and
                                                    Office of Management and Budget                         available information related to this                 purchase copies of public documents at
                                                    (OMB) for review. The information                       action by any of the following methods:               the NRC’s PDR, Room O1–F21, One


                                               VerDate Sep<11>2014   17:12 Sep 18, 2017   Jkt 241001   PO 00000   Frm 00060   Fmt 4703   Sfmt 4703   E:\FR\FM\19SEN1.SGM   19SEN1



Document Created: 2018-10-24 14:18:18
Document Modified: 2018-10-24 14:18:18
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionEnvironmental assessment and finding of no significant impact; issuance.
DatesMaterials License 42-23539-01AF, Docket No. 030-28641, will be amended to approve the DP on or after September 19, 2017.
ContactVivian Campbell, Region IV Office, U.S. Nuclear Regulatory Commission, 1600 E. Lamar Blvd., Arlington, TX 76011; telephone: 817-200-1455, email: [email protected]
FR Citation82 FR 43794 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR