82_FR_45194 82 FR 45008 - Notice of Availability of The Great Lakes and Mississippi River Interbasin Study-Brandon Road Draft Integrated Feasibility Study and Environmental Impact Statement-Will County, Illinois

82 FR 45008 - Notice of Availability of The Great Lakes and Mississippi River Interbasin Study-Brandon Road Draft Integrated Feasibility Study and Environmental Impact Statement-Will County, Illinois

DEPARTMENT OF DEFENSE
Department of the Army, Corps of Engineers

Federal Register Volume 82, Issue 186 (September 27, 2017)

Page Range45008-45008
FR Document2017-20680

The U.S. Army Corps of Engineers (USACE) is extending the comment period for the report ``The Great Lakes and Mississippi River Interbasin Study--Brandon Road Draft Integrated Feasibility Study and Environmental Impact Statement--Will County, Illinois'' (GLMRIS-Brandon Road) for 45 days in response to stakeholder requests for an extension, from October 2, 2017 to November 16, 2017.

Federal Register, Volume 82 Issue 186 (Wednesday, September 27, 2017)
[Federal Register Volume 82, Number 186 (Wednesday, September 27, 2017)]
[Notices]
[Page 45008]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-20680]


-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army, Corps of Engineers


Notice of Availability of The Great Lakes and Mississippi River 
Interbasin Study--Brandon Road Draft Integrated Feasibility Study and 
Environmental Impact Statement--Will County, Illinois

AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.

ACTION: Extension of public comment period.

-----------------------------------------------------------------------

SUMMARY: The U.S. Army Corps of Engineers (USACE) is extending the 
comment period for the report ``The Great Lakes and Mississippi River 
Interbasin Study--Brandon Road Draft Integrated Feasibility Study and 
Environmental Impact Statement--Will County, Illinois'' (GLMRIS-Brandon 
Road) for 45 days in response to stakeholder requests for an extension, 
from October 2, 2017 to November 16, 2017.

DATES: The comment period is extended for the draft GLMRIS-Brandon Road 
report published in the Federal Register on August 7, 2017 (82 FR 
36760). Comments must be received or postmarked by November 16, 2017.

ADDRESSES: Comments may be submitted in the following ways:
    GLMRIS Project Web site: Use the Web comment function found at 
http://glmris.anl.gov.
    Mail: Send comments to U.S. Army Corps of Engineers, Chicago 
District, ATTN: GLMRIS-Brandon Road Comments, 231 S. LaSalle St., Suite 
1500, Chicago, IL 60604.

FOR FURTHER INFORMATION CONTACT: Contact Andrew Leichty, Program 
Manager, by mail: U.S. Army Corps of Engineers, Rock Island District, 
Clock Tower Building (ATTN: Leichty), P.O. Box 2004, Rock Island, IL 
61204-2004, by phone: 309-794-5399; or by email: 
[email protected].

SUPPLEMENTARY INFORMATION: The GLMRIS authority directed USACE to 
identify the range of options and technologies available to prevent the 
spread of aquatic nuisance species between the Great Lakes and 
Mississippi River Basins through the Chicago Sanitary and Ship Canal 
and other aquatic pathways. The goal of the GLMRIS-Brandon Road Study 
is to prevent the upstream transfer of aquatic nuisance species while 
minimizing impacts to existing waterways uses and users.
    Comments, including the names and addresses of those who comment, 
received during the comment period will be posted on the GLMRIS project 
Web site. Comments submitted anonymously will be accepted, considered, 
and posted. Commenters may indicate that they do not wish to have their 
name or other personal information made available on the Web site. 
However, USACE cannot guarantee that information withheld from the Web 
site will be maintained as confidential. Persons requesting 
confidentiality should be aware that, under the Freedom of Information 
Act, confidentiality may be granted in only limited circumstances.

    Dated: September 18, 2017.
Dennis W. Hamilton,
Chief, Programs and Project Management Division.
[FR Doc. 2017-20680 Filed 9-26-17; 8:45 am]
 BILLING CODE 3720-58-P



                                                    45008                    Federal Register / Vol. 82, No. 186 / Wednesday, September 27, 2017 / Notices

                                                    authorized for release and export to the                nuisance species while minimizing                     Construction Alternative (hereafter, the
                                                    Government of Bahrain.                                  impacts to existing waterways uses and                Selected Plan).
                                                    [FR Doc. 2017–20700 Filed 9–26–17; 8:45 am]             users.                                                DATES: The USACE Mississippi Valley
                                                    BILLING CODE 5001–06–P                                     Comments, including the names and                  Division Commander, Major General
                                                                                                            addresses of those who comment,                       Michael C. Wehr, signed the ROD on
                                                                                                            received during the comment period                    August 31, 2017.
                                                    DEPARTMENT OF DEFENSE                                   will be posted on the GLMRIS project                  ADDRESSES: U.S. Army Corps of
                                                                                                            Web site. Comments submitted                          Engineers, Regional Planning and
                                                    Department of the Army, Corps of                        anonymously will be accepted,                         Environmental Division North, CEMVP–
                                                    Engineers                                               considered, and posted. Commenters                    PD–P (Attn: Mr. Kip Runyon), 1222
                                                                                                            may indicate that they do not wish to                 Spruce St., St. Louis, MO 63103–2833.
                                                    Notice of Availability of The Great
                                                                                                            have their name or other personal                     FOR FURTHER INFORMATION CONTACT: Kip
                                                    Lakes and Mississippi River Interbasin
                                                                                                            information made available on the Web                 Runyon, Environmental Planner,
                                                    Study—Brandon Road Draft Integrated
                                                                                                            site. However, USACE cannot guarantee                 Regional Planning and Environmental
                                                    Feasibility Study and Environmental
                                                                                                            that information withheld from the Web                Division North, at 314–331–8396 or by
                                                    Impact Statement—Will County, Illinois
                                                                                                            site will be maintained as confidential.              email at RegWorksSEIS@
                                                    AGENCY:  Department of the Army, U.S.                   Persons requesting confidentiality                    usace.army.mil.
                                                    Army Corps of Engineers, DoD.                           should be aware that, under the                       SUPPLEMENTARY INFORMATION: USACE is
                                                    ACTION: Extension of public comment                     Freedom of Information Act,                           charged with obtaining and maintaining
                                                    period.                                                 confidentiality may be granted in only                a navigation channel on the Middle
                                                                                                            limited circumstances.                                Mississippi River (MMR) that is nine
                                                    SUMMARY:   The U.S. Army Corps of
                                                    Engineers (USACE) is extending the                        Dated: September 18, 2017.                          feet deep and 300 feet wide with
                                                    comment period for the report ‘‘The                     Dennis W. Hamilton,                                   additional width in bends as necessary
                                                    Great Lakes and Mississippi River                       Chief, Programs and Project Management                (commonly called the Regulating Works
                                                    Interbasin Study—Brandon Road Draft                     Division.                                             Project). As authorized by Congress, the
                                                    Integrated Feasibility Study and                        [FR Doc. 2017–20680 Filed 9–26–17; 8:45 am]           Regulating Works Project is obtained by
                                                    Environmental Impact Statement—Will                     BILLING CODE 3720–58–P                                construction of revetment, rock removal,
                                                    County, Illinois’’ (GLMRIS-Brandon                                                                            and river training structures to maintain
                                                    Road) for 45 days in response to                                                                              bank stability and ensure adequate,
                                                    stakeholder requests for an extension,                  DEPARTMENT OF DEFENSE                                 reliable navigation depth and width.
                                                                                                                                                                  The Regulating Works Project is
                                                    from October 2, 2017 to November 16,
                                                                                                            Department of the Army, Corps of                      maintained through dredging and any
                                                    2017.
                                                                                                            Engineers                                             needed maintenance to constructed
                                                    DATES: The comment period is extended
                                                                                                                                                                  features. The long-term goal of the
                                                    for the draft GLMRIS-Brandon Road                       Record of Decision for Final                          Regulating Works Project, as authorized
                                                    report published in the Federal Register                Supplement I to the Final                             by Congress, is to obtain and maintain
                                                    on August 7, 2017 (82 FR 36760).                        Environmental Statement, Mississippi                  a navigation channel at the authorized
                                                    Comments must be received or                            River Between the Ohio and Missouri                   dimensions and to reduce federal
                                                    postmarked by November 16, 2017.                        Rivers (Regulating Works), Missouri                   expenditures by alleviating the amount
                                                    ADDRESSES: Comments may be                              and Illinois                                          of annual maintenance dredging
                                                    submitted in the following ways:                                                                              through the construction of river
                                                      GLMRIS Project Web site: Use the                      AGENCY:Department of the Army, U.S.                   training structures. The Selected Plan
                                                    Web comment function found at http://                   Army Corps of Engineers, DoD.                         consists of continuing with construction
                                                    glmris.anl.gov.                                         ACTION:   Record of Decision.                         of new river training structures and
                                                      Mail: Send comments to U.S. Army                                                                            revetment for navigation purposes until
                                                    Corps of Engineers, Chicago District,                   SUMMARY:   The U.S. Army Corps of                     such time as the costs of placing more
                                                    ATTN: GLMRIS-Brandon Road                               Engineers (USACE), St. Louis District, is             structures, including costs for any
                                                    Comments, 231 S. LaSalle St., Suite                     issuing this notice to advise Federal,                mitigation, are no longer justified by the
                                                    1500, Chicago, IL 60604.                                state, and local government agencies,                 resultant reduction in repetitive
                                                    FOR FURTHER INFORMATION CONTACT:                        affected Tribes, and the public that                  dredging quantities and associated
                                                    Contact Andrew Leichty, Program                         USACE has signed a Record of Decision                 costs. The Selected Plan also involves
                                                    Manager, by mail: U.S. Army Corps of                    (ROD) for Final Supplement I to the                   continuing to dredge as necessary,
                                                    Engineers, Rock Island District, Clock                  Final Environmental Statement,                        completing known bankline
                                                    Tower Building (ATTN: Leichty), P.O.                    Mississippi River between the Ohio and                stabilization work to reduce the risk of
                                                    Box 2004, Rock Island, IL 61204–2004,                   Missouri Rivers (Regulating Works). The               a channel cutoff, placing additional
                                                    by phone: 309–794–5399; or by email:                    ROD was rendered to declare that, after               revetment, and continuing to maintain
                                                    Andrew.L.Leichty@usace.army.mil.                        careful consideration of the purpose of               existing structures.
                                                    SUPPLEMENTARY INFORMATION: The                          and need for the Regulating Works                        The remaining construction
                                                    GLMRIS authority directed USACE to                      Project, the analysis contained in Final              associated with the Selected Plan is
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    identify the range of options and                       Supplement I, input from the public,                  currently estimated from programmatic
                                                    technologies available to prevent the                   affected Tribes, state and Federal                    analysis to require approximately 4.4
                                                    spread of aquatic nuisance species                      agencies, and other interested parties,               million tons (2.9 million cubic yards) of
                                                    between the Great Lakes and                             and based on the Regulating Works                     rock. Dredge quantities are expected to
                                                    Mississippi River Basins through the                    Project’s Congressional authority and                 decrease from their current average
                                                    Chicago Sanitary and Ship Canal and                     continued benefit of remaining                        annual quantity of approximately 4
                                                    other aquatic pathways. The goal of the                 construction, USACE has determined                    million cubic yards to approximately
                                                    GLMRIS-Brandon Road Study is to                         that the public interest will best be                 2.4 million cubic yards after
                                                    prevent the upstream transfer of aquatic                served by implementing the Continue                   construction of new river training


                                               VerDate Sep<11>2014   18:59 Sep 26, 2017   Jkt 241001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\27SEN1.SGM   27SEN1



Document Created: 2018-10-24 14:49:05
Document Modified: 2018-10-24 14:49:05
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionExtension of public comment period.
DatesThe comment period is extended for the draft GLMRIS-Brandon Road report published in the Federal Register on August 7, 2017 (82 FR 36760). Comments must be received or postmarked by November 16, 2017.
ContactContact Andrew Leichty, Program Manager, by mail: U.S. Army Corps of Engineers, Rock Island District, Clock Tower Building (ATTN: Leichty), P.O. Box 2004, Rock Island, IL 61204-2004, by phone: 309-794-5399; or by email: [email protected]
FR Citation82 FR 45008 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR