82_FR_57826 82 FR 57593 - Port Arthur Pipeline LLC; Notice of Amendment to Application

82 FR 57593 - Port Arthur Pipeline LLC; Notice of Amendment to Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 233 (December 6, 2017)

Page Range57593-57594
FR Document2017-26248

Federal Register, Volume 82 Issue 233 (Wednesday, December 6, 2017)
[Federal Register Volume 82, Number 233 (Wednesday, December 6, 2017)]
[Notices]
[Pages 57593-57594]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-26248]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP17-21-001, CP17-21-000, CP18-7-000]


Port Arthur Pipeline LLC; Notice of Amendment to Application

    Take notice that on November 7, 2017, Port Arthur Pipeline LLC 
(Port Arthur Pipeline), 2925 Briarpark, Suite 900, Houston, Texas 
77042, filed an amendment to its application in Docket No. CP17-21-000, 
pursuant to section 7(c) of the Natural Gas Act (NGA) and Part 157 of 
the Commission's regulations for a certificate of public convenience 
and necessity to construct and operate the Texas Connector Project 
located in Orange and Jefferson Counties, Texas and Cameron Parish, 
Louisiana.
    Specifically, Port Arthur Pipeline filed an amendment to its 
proposed Rate Schedules and General Terms and Conditions (GT&C) to 
reflect the pro forma tariff proposed by Port Arthur Pipeline in Docket 
No. CP18-7-000 for its Louisiana Connector Project. Further, Port 
Arthur Pipeline proposes changes to its initial rates for service 
through the Texas Connector Project to reflect changes to: (i) The 
Allowance for Funds Used During Construction, (ii) the rate for service 
under Port Arthur Pipeline's proposed Rate Schedule Enhanced Hourly 
Firm Transportation; and (iii) the precedent agreement between Port 
Arthur Pipeline and Port Arthur LNG, LLC (Port Arthur LNG) executed in 
association with the open seasons

[[Page 57594]]

conducted in November 2016 and in August and September 2017, under 
which Port Arthur LNG subscribed for all of the capacity of the Texas 
Connector Project. Port Arthur Pipeline submitted updated Exhibits I, 
K, N, O, and P, all as more fully set forth in the application which is 
on file with the Commission and open to public inspection.
    The filing may be viewed on the web at http://www.ferc.gov using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC at [email protected] or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
    Any questions regarding this application should be directed to 
Jerrod L. Harrison, Senior Counsel, Port Arthur Pipeline, LLC, 488 8th 
Avenue, San Diego, California 92101, by phone at (619) 696-2987, or by 
email to [email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental impact statement (EIS) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) for this proposal. The 
filing of the FEIS in the Commission's public record for this 
proceeding or the issuance of a Notice of Schedule will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit five copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
http://www.ferc.gov. Persons unable to file electronically should 
submit an original and five copies of the protest or intervention to 
the Federal Energy regulatory Commission, 888 First Street NE., 
Washington, DC 20426.
    Comment date: December 21, 2017.

    Dated: November 30, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-26248 Filed 12-5-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                        Federal Register / Vol. 82, No. 233 / Wednesday, December 6, 2017 / Notices                                                   57593

                                               FERCOnlineSupport@ferc.gov, (866)                       email of new filings and issuances                                Milestone               Target date
                                               208–3676 (toll free), or (202) 502–8659                 related to this or other pending projects.
                                               (TTY). In lieu of electronic filing, please             For assistance, contact FERC Online                    Commission Issues Final EIS      March 2019.
                                               send a paper copy to: Secretary, Federal                Support.
                                               Energy Regulatory Commission, 888                          n. Anyone may submit comments, a                       p. Final amendments to the
                                               First Street NE., Washington, DC 20426.                 protest, or a motion to intervene in                   application must be filed with the
                                               The first page of any filing should                     accordance with the requirements of                    Commission no later than 30 days from
                                               include docket number P–14581–002.                      Rules of Practice and Procedure, 18 CFR                the issuance date of this notice.
                                                  The Commission’s Rules of Practice                   385.210, .211, and .214. In determining                   q. A license applicant must file no
                                               require all intervenors filing documents                the appropriate action to take, the                    later than 60 days following the date of
                                               with the Commission to serve a copy of                  Commission will consider all protests or               issuance of the notice of acceptance and
                                               that document on each person on the                     other comments filed, but only those                   ready for environmental analysis
                                               official service list for the project.                  who file a motion to intervene in                      provided for in 5.22: (1) A copy of the
                                               Further, if an intervenor files comments                accordance with the Commission’s                       water quality certification; (2) a copy of
                                               or documents with the Commission                        Rules may become a party to the                        the request for certification, including
                                               relating to the merits of an issue that                 proceeding. Any comments, protests, or                 proof of the date on which the certifying
                                               may affect the responsibilities of a                    motions to intervene must be received                  agency received the request; or (3)
                                               particular resource agency, they must                   on or before the specified comment date                evidence of waiver of water quality
                                               also serve a copy of the document on                    for the particular application.                        certification.
                                               that resource agency.                                      All filings must (1) bear in all capital              Dated: November 30, 2017.
                                                  k. This application has been accepted                letters the title PROTEST, MOTION TO                   Nathaniel J. Davis, Sr.,
                                               for filing and is now ready for                         INTERVENE, COMMENTS, REPLY                             Deputy Secretary.
                                               environmental analysis.                                 COMMENTS, RECOMMENDATIONS,                             [FR Doc. 2017–26247 Filed 12–5–17; 8:45 am]
                                                  l. The La Grange Project consists of                 PRELIMINARY TERMS AND
                                                                                                                                                              BILLING CODE 6717–01–P
                                               the following existing facilities: (1) La               CONDITIONS, or PRELIMINARY
                                               Grange dam, a 310-foot-long, 131-foot-                  FISHWAY PRESCRIPTIONS; (2) set
                                               high, masonry arch dam; (2) La Grange                   forth in the heading the name of the                   DEPARTMENT OF ENERGY
                                               reservoir with a storage capacity of                    applicant and the project number of the
                                               about 500 acre-feet; (3) MID headworks,                 application to which the filing                        Federal Energy Regulatory
                                               canal, and sluice gates are part of MID’s               responds; (3) furnish the name, address,               Commission
                                               retired irrigation canal facilities; (4) TID            and telephone number of the person
                                               irrigation intake and tunnel; (5) a                                                                            [Docket Nos. CP17–21–001, CP17–21–000,
                                                                                                       protesting or intervening; and (4)                     CP18–7–000]
                                               powerhouse with two Francis turbine-                    otherwise comply with the requirements
                                               generator units with a maximum                          of 18 CFR 385.2001 through 385.2005.                   Port Arthur Pipeline LLC; Notice of
                                               capacity of 4.9 megawatts. The project’s                All comments, recommendations, terms                   Amendment to Application
                                               estimated average annual generation is                  and conditions or prescriptions must set
                                               about 19,638 megawatt-hours.                            forth their evidentiary basis and                         Take notice that on November 7,
                                                  The Districts propose to: (1) Provide                otherwise comply with the requirements                 2017, Port Arthur Pipeline LLC (Port
                                               a minimum flow of approximately 5 to                    of 18 CFR 4.34(b). Agencies may obtain                 Arthur Pipeline), 2925 Briarpark, Suite
                                               10 cubic feet per second to the plunge                  copies of the application directly from                900, Houston, Texas 77042, filed an
                                               pool downstream of La Grange diversion                  the applicant. A copy of any protest or                amendment to its application in Docket
                                               dam at all times; (2) install a fish                    motion to intervene must be served                     No. CP17–21–000, pursuant to section
                                               exclusion barrier at the TID sluice                     upon each representative of the                        7(c) of the Natural Gas Act (NGA) and
                                               channel entrance; (3) conduct dissolved                 applicant specified in the particular                  Part 157 of the Commission’s
                                               oxygen monitoring in the vicinity of the                application. A copy of all other filings               regulations for a certificate of public
                                               La Grange powerhouse; (4) construct a                   in reference to this application must be               convenience and necessity to construct
                                               recreational foot trail extending from the              accompanied by proof of service on all                 and operate the Texas Connector Project
                                               former Don Pedro Visitor Center parking                 persons listed in the service list                     located in Orange and Jefferson
                                               lot to the La Grange headpond; and (5)                  prepared by the Commission in this                     Counties, Texas and Cameron Parish,
                                               develop an HPMP in consultation with                    proceeding, in accordance with 18 CFR                  Louisiana.
                                               Tribes, Bureau of Land Management,                                                                                Specifically, Port Arthur Pipeline
                                                                                                       4.34(b) and 385.2010.
                                               and State Historical Preservation Officer                  o. Procedural Schedule:                             filed an amendment to its proposed Rate
                                               to manage potential effects on historic                    The application will be processed                   Schedules and General Terms and
                                               properties.                                             according to the following revised                     Conditions (GT&C) to reflect the pro
                                                  m. A copy of the application is                      Hydro Licensing Schedule. Revisions to                 forma tariff proposed by Port Arthur
                                               available for review at the Commission                  the schedule may be made as                            Pipeline in Docket No. CP18–7–000 for
                                               in the Public Reference Room or may be                  appropriate.                                           its Louisiana Connector Project. Further,
                                               viewed on the Commission’s Web site at                                                                         Port Arthur Pipeline proposes changes
                                               http://www.ferc.gov using the                                      Milestone                     Target date   to its initial rates for service through the
                                               ‘‘eLibrary’’ link. Enter the docket                                                                            Texas Connector Project to reflect
                                               number excluding the last three digits in               Filing of recommendations,          January 2018.      changes to: (i) The Allowance for Funds
                                               the docket number field to access the                      preliminary terms and con-                          Used During Construction, (ii) the rate
daltland on DSKBBV9HB2PROD with NOTICES




                                               document. For assistance, contact FERC                     ditions, and preliminary                            for service under Port Arthur Pipeline’s
                                                                                                          fishway prescriptions.                              proposed Rate Schedule Enhanced
                                               Online Support. A copy is also available                Commission issues Draft En-         August 2018.
                                               for inspection and reproduction at the                     vironmental Statement
                                                                                                                                                              Hourly Firm Transportation; and (iii)
                                               address in item h above.                                   (EIS).                                              the precedent agreement between Port
                                                  Register online at http://                           Comments on Draft EIS ........      October 2018.      Arthur Pipeline and Port Arthur LNG,
                                               www.ferc.gov/docs-filing/                               Modified Terms and Condi-           December           LLC (Port Arthur LNG) executed in
                                               esubscription.asp to be notified via                       tions.                             2018.            association with the open seasons


                                          VerDate Sep<11>2014   18:07 Dec 05, 2017   Jkt 244001   PO 00000   Frm 00025   Fmt 4703   Sfmt 4703    E:\FR\FM\06DEN1.SGM   06DEN1


                                               57594                    Federal Register / Vol. 82, No. 233 / Wednesday, December 6, 2017 / Notices

                                               conducted in November 2016 and in                       all documents filed by the applicant and              DEPARTMENT OF ENERGY
                                               August and September 2017, under                        by all other parties. A party must submit
                                               which Port Arthur LNG subscribed for                    five copies of filings made with the                  Federal Energy Regulatory
                                               all of the capacity of the Texas                        Commission and must mail a copy to                    Commission
                                               Connector Project. Port Arthur Pipeline                 the applicant and to every other party in             [Docket No. CP18–18–000]
                                               submitted updated Exhibits I, K, N, O,                  the proceeding. Only parties to the
                                               and P, all as more fully set forth in the               proceeding can ask for court review of                Transcontinental Gas Pipe Line
                                               application which is on file with the                   Commission orders in the proceeding.                  Company, LLC; Notice of Application
                                               Commission and open to public
                                                                                                          However, a person does not have to                    On November 15, 2017,
                                               inspection.
                                                  The filing may be viewed on the web                  intervene in order to have comments                   Transcontinental Gas Pipe Line
                                               at http://www.ferc.gov using the                        considered. The second way to                         Company, LLC (Transco), P.O. Box
                                               ‘‘eLibrary’’ link. Enter the docket                     participate is by filing with the                     1396, Houston, Texas 77251, filed an
                                               number excluding the last three digits in               Secretary of the Commission, as soon as               application pursuant to section 7(c) of
                                               the docket number field to access the                   possible, an original and two copies of               the Natural Gas Act (NGA) and the
                                               document. For assistance, contact FERC                  comments in support of or in opposition               Federal Energy Regulatory
                                               at FERCOnlineSupport@ferc.gov or call                   to this project. The Commission will                  Commission’s (Commission) regulations
                                               toll-free, (886) 208–3676 or TYY, (202)                 consider these comments in                            seeking for a certificate of public
                                               502–8659.                                               determining the appropriate action to be              convenience and necessity authorizing
                                                  Any questions regarding this                         taken, but the filing of a comment alone              Transco’s Gateway Expansion Project
                                               application should be directed to Jerrod                will not serve to make the filer a party              (Project), which is an expansion of
                                               L. Harrison, Senior Counsel, Port Arthur                to the proceeding. The Commission’s                   Transco’s existing interstate gas
                                               Pipeline, LLC, 488 8th Avenue, San                      rules require that persons filing                     transmission system in New Jersey that
                                               Diego, California 92101, by phone at                    comments in opposition to the project                 will enable Transco to provide an
                                               (619) 696–2987, or by email to                          provide copies of their protests only to              additional 65,000 dekatherms per day of
                                               jharrison@sempraglobal.com.                             the party or parties directly involved in             firm transportation service, all as more
                                                  Pursuant to section 157.9 of the                     the protest.                                          fully set forth in the application, which
                                               Commission’s rules, 18 CFR 157.9,                                                                             is open to the public for inspection. The
                                               within 90 days of this Notice the                          Persons who wish to comment only                   filing may also be viewed on the web at
                                               Commission staff will either: Complete                  on the environmental review of this                   http://www.ferc.gov using the
                                               its environmental impact statement                      project should submit an original and                 ‘‘eLibrary’’ link. Enter the docket
                                               (EIS) and place it into the Commission’s                two copies of their comments to the                   number excluding the last three digits in
                                               public record (eLibrary) for this                       Secretary of the Commission.                          the docket number field to access the
                                               proceeding, or issue a Notice of                        Environmental commenters will be                      document. For assistance, contact FERC
                                               Schedule for Environmental Review. If                   placed on the Commission’s                            at FERCOnlineSupport@ferc.gov or call
                                               a Notice of Schedule for Environmental                  environmental mailing list, will receive              toll-free, (866) 208–3676 or TTY, (202)
                                               Review is issued, it will indicate, among               copies of the environmental documents,                502–8659.
                                               other milestones, the anticipated date                  and will be notified of meetings                         Any questions regarding the Transco’s
                                               for the Commission staff’s issuance of                  associated with the Commission’s                      application should be directed to Jordan
                                               the final environmental impact                          environmental review process.                         Kirwin, P.O. Box 1396, Houston, Texas
                                               statement (FEIS) for this proposal. The                 Environmental commenters will not be                  77251, or (713) 215–2264, or by email
                                               filing of the FEIS in the Commission’s                  required to serve copies of filed                     PipelineExpansion@williams.com.
                                               public record for this proceeding or the                documents on all other parties.                          Specifically, the Project will involve:
                                               issuance of a Notice of Schedule will                   However, the non-party commenters                     (1) Installing 27,500 of additional
                                               serve to notify federal and state agencies              will not receive copies of all documents              horsepower at Transco’s existing Station
                                               of the timing for the completion of all                 filed by other parties or issued by the               303 located in Essex County, New
                                               necessary reviews, and the subsequent                   Commission (except for the mailing of                 Jersey; (2) replacing the existing 12-
                                               need to complete all federal                            environmental documents issued by the                 inch-diameter header, meter skid and
                                               authorizations within 90 days of the                    Commission) and will not have the right               associated equipment with two new 6-
                                               date of issuance of the Commission                      to seek court review of the                           inch-diameter ultrasonic meter skids
                                               staff’s FEIS.                                           Commission’s final order.                             and associated equipment at the existing
                                                  There are two ways to become                                                                               Paterson Meter and Regulator (M&R)
                                               involved in the Commission’s review of                     The Commission strongly encourages
                                                                                                                                                             facility located in Passaic County, New
                                               this project. First, any person wishing to              electronic filings of comments, protests
                                                                                                                                                             Jersey; (3) installing a 36-inch-diameter
                                               obtain legal status by becoming a party                 and interventions in lieu of paper using
                                                                                                                                                             mainline block valve at the existing
                                               to the proceedings for this project                     the eFiling link at http://www.ferc.gov.
                                                                                                                                                             Roseland M&R facility located in Essex
                                               should, on or before the comment date                   Persons unable to file electronically
                                                                                                                                                             County, New Jersey; and (4) installing
                                               stated below, file with the Federal                     should submit an original and five
                                                                                                                                                             one electric transformer at the existing
                                               Energy Regulatory Commission, 888                       copies of the protest or intervention to
                                                                                                                                                             Roseland Electric Substation located in
                                               First Street NE., Washington, DC 20426,                 the Federal Energy regulatory
                                                                                                                                                             Essex County, New Jersey.
                                               a motion to intervene in accordance                     Commission, 888 First Street NE.,                        Pursuant to Section 157.9 of the
                                               with the requirements of the                            Washington, DC 20426.                                 Commission’s rules, 18 CFR 157.9,
daltland on DSKBBV9HB2PROD with NOTICES




                                               Commission’s Rules of Practice and                         Comment date: December 21, 2017.                   within 90 days of this Notice the
                                               Procedure (18 CFR 385.214 or 385.211)                     Dated: November 30, 2017.                           Commission staff will either: complete
                                               and the Regulations under the NGA (18                                                                         its environmental assessment (EA) and
                                                                                                       Nathaniel J. Davis, Sr.,
                                               CFR 157.10). A person obtaining party                                                                         place it into the Commission’s public
                                               status will be placed on the service list               Deputy Secretary.                                     record (eLibrary) for this proceeding, or
                                               maintained by the Secretary of the                      [FR Doc. 2017–26248 Filed 12–5–17; 8:45 am]           issue a Notice of Schedule for
                                               Commission and will receive copies of                   BILLING CODE 6717–01–P                                Environmental Review. If a Notice of


                                          VerDate Sep<11>2014   18:07 Dec 05, 2017   Jkt 244001   PO 00000   Frm 00026   Fmt 4703   Sfmt 4703   E:\FR\FM\06DEN1.SGM   06DEN1



Document Created: 2017-12-06 00:21:49
Document Modified: 2017-12-06 00:21:49
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
DatesDecember 21, 2017.
FR Citation82 FR 57593 

2025 Federal Register | Disclaimer | Privacy Policy