82_FR_57829 82 FR 57596 - Turlock Irrigation District, Modesto Irrigation District; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions

82 FR 57596 - Turlock Irrigation District, Modesto Irrigation District; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 233 (December 6, 2017)

Page Range57596-57597
FR Document2017-26246

Federal Register, Volume 82 Issue 233 (Wednesday, December 6, 2017)
[Federal Register Volume 82, Number 233 (Wednesday, December 6, 2017)]
[Notices]
[Pages 57596-57597]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-26246]



[[Page 57596]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2299-082]


Turlock Irrigation District, Modesto Irrigation District; Notice 
of Application Accepted for Filing, Soliciting Motions To Intervene and 
Protests, Ready for Environmental Analysis, and Soliciting Comments, 
Recommendations, Preliminary Terms and Conditions, and Preliminary 
Fishway Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Major License.
    b. Project No.: 2299-082.
    c. Date filed: October 11, 2017.
    d. Applicant: Turlock Irrigation District and Modesto Irrigation 
District (Districts).
    e. Name of Project: Don Pedro Hydroelectric Project.
    f. Location: The Don Pedro Project is located on the Tuolumne River 
in Tuolumne County, California. Portions of the project occupy public 
lands managed by the Bureau of Land Management.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contacts: Steve Boyd, Turlock Irrigation District, 333 
East Canal Drive, Turlock, California 95381-0949, (209) 883-8300; and 
Anna Brathwaite, Modesto Irrigation District, P.O. Box 4060, Modesto, 
CA 95352, (209) 526-7384.
    i. FERC Contact: Jim Hastreiter at (503) 552-2760 or 
[email protected].
    j. Deadline for filing motions to intervene and protests, comments, 
recommendations, preliminary terms and conditions, and preliminary 
prescriptions: 60 days from the issuance date of this notice; reply 
comments are due 105 days from the issuance date of this notice.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene, protests, comments, recommendations, preliminary 
terms and conditions, and preliminary fishway prescriptions using the 
Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
http://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-2299-082.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted for filing and is now ready 
for environmental analysis.
    l. The Don Pedro Project consists of the following existing 
facilities: (1) A 580-foot-high, 1,900-foot-long earth and rockfill dam 
with a gross storage capacity of 2,030,000 acre-feet, located on the 
Tuolumne River 54.8 miles upstream of its confluence with the San 
Joaquin River; (2) a 30-foot-high, 45-foot-wide, 135-foot-long gated 
spillway including three radial gates each 45-foot-wide by 30-foot-
high; (3) a 995-foot-long ungated ogee spillway with a crest elevation 
of 830 feet; (4) a set of outlet works located at the left abutment of 
the dam consisting of three individual gate housings, each containing 
two 4-foot-by-5-foot slide gates; (5) a 3,500-foot-long-concrete lined 
tunnel with a total hydraulic capacity of 7,500 cubic feet per second; 
(6) a 2,960-foot-long power tunnel located in the left abutment of the 
dam that transitions from an 18-foot concrete-lined section to a 16-
foot steel-lined section; (7) a 21-foot-high, 12-foot-wide emergency 
closure fixed-wheel gate; (8) a powerhouse located immediately 
downstream of the dam containing a 72-inch hollow jet valve and four 
Francis turbine-generator units with a nameplate capacity of 168 
megawatts; (9) a switchyard located on top of the powerhouse; (10) a 
75-foot-high earth and rockfill Gasburg Creek dike with a slide-gate 
controlled 18-inch-diameter conduit located near the downstream end of 
the spillway; (11) three small embankments dikes (dike A is located 
between the main dam and spillway and dikes B and C are located east of 
the main dam); (12) recreation facilities on Don Pedro reservoir, 
including Fleming Meadows, Blue Oaks, and Moccasin Point; and (13) 
appurtenant facilities and features including access roads. The 
project's estimated average annual generation is about 550,000 
megawatt-hours.
    The Districts propose to: (1) Conduct coarse sediment augmentation 
from river mile (RM) 39 to RM 52 over a 10-year period; (2) provide 
gravel mobilization flows of 6,000 to 7,000 cfs during years when 
sufficient spill is projected to occur; (3) conduct a five-year program 
of experimental gravel cleaning; (4) implement a boulder placement 
program to improve aquatic habitat between RM 42 and RM 50; (5) 
contribute $50,000 per year to the California Division of Boating and 
Waterways to assist with the removal of water hyacinth and other non-
native flora; (6) implement a fall-run Chinook spawning improvement 
superimposition reduction program; (7) implement a predator control and 
suppression program that would include construction and operation of a 
fish counting/barrier weir and active predator control and suppression; 
(8) develop a fall-run Chinook salmon restoration hatchery; (9) install 
an improved take-out facility at RM 78 at Ward's Ferry and a new take-
out and put-in facility at RM 25.7; (10) implement flow-related 
measures including the construction of infiltration galleries and the 
provision of base flows and pulse flows designed to benefit specific 
salmonid life stages and provide for recreational boating; (11) monitor 
the effectiveness of gravel, aquatic habitat and predator control 
measures; and (12) implement management plans for fire prevention and 
response, spill prevention and countermeasures, aquatic invasive 
species, woody debris, terrestrial resources, recreation resources, 
historic properties, and transportation.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    Register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Anyone may submit comments, a protest, or a motion to intervene 
in accordance with the requirements of Rules of Practice and Procedure, 
18 CFR 385.210, .211, and .214. In determining

[[Page 57597]]

the appropriate action to take, the Commission will consider all 
protests or other comments filed, but only those who file a motion to 
intervene in accordance with the Commission's Rules may become a party 
to the proceeding. Any comments, protests, or motions to intervene must 
be received on or before the specified comment date for the particular 
application.
    All filings must (1) bear in all capital letters the title PROTEST, 
MOTION TO INTERVENE, COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, 
PRELIMINARY TERMS AND CONDITIONS, or PRELIMINARY FISHWAY PRESCRIPTIONS; 
(2) set forth in the heading the name of the applicant and the project 
number of the application to which the filing responds; (3) furnish the 
name, address, and telephone number of the person protesting or 
intervening; and (4) otherwise comply with the requirements of 18 CFR 
385.2001 through 385.2005. All comments, recommendations, terms and 
conditions or prescriptions must set forth their evidentiary basis and 
otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may 
obtain copies of the application directly from the applicant. A copy of 
any protest or motion to intervene must be served upon each 
representative of the applicant specified in the particular 
application. A copy of all other filings in reference to this 
application must be accompanied by proof of service on all persons 
listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    o. Procedural Schedule:
    The application will be processed according to the following 
revised Hydro Licensing Schedule. Revisions to the schedule may be made 
as appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Filing of recommendations, preliminary      December 2017.
 terms and conditions, and preliminary
 fishway prescriptions.
Commission issues Draft Environmental       July 2018.
 Statement (EIS).
Comments on Draft EIS.....................  September 2018.
Modified Terms and Conditions.............  November 2018.
Commission Issues Final EIS...............  February 2019.
------------------------------------------------------------------------

    p. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of this notice.
    q. A license applicant must file no later than 60 days following 
the date of issuance of the notice of acceptance and ready for 
environmental analysis provided for in 5.22: (1) A copy of the water 
quality certification; (2) a copy of the request for certification, 
including proof of the date on which the certifying agency received the 
request; or (3) evidence of waiver of water quality certification.

    Dated: November 30, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-26246 Filed 12-5-17; 8:45 am]
 BILLING CODE 6717-01-P



                                               57596                    Federal Register / Vol. 82, No. 233 / Wednesday, December 6, 2017 / Notices

                                               DEPARTMENT OF ENERGY                                    FERCOnlineSupport@ferc.gov, (866)                     estimated average annual generation is
                                                                                                       208–3676 (toll free), or (202) 502–8659               about 550,000 megawatt-hours.
                                               Federal Energy Regulatory                               (TTY). In lieu of electronic filing, please              The Districts propose to: (1) Conduct
                                               Commission                                              send a paper copy to: Secretary, Federal              coarse sediment augmentation from
                                                                                                       Energy Regulatory Commission, 888                     river mile (RM) 39 to RM 52 over a 10-
                                               [Project No. 2299–082]
                                                                                                       First Street NE., Washington, DC 20426.               year period; (2) provide gravel
                                               Turlock Irrigation District, Modesto                    The first page of any filing should                   mobilization flows of 6,000 to 7,000 cfs
                                               Irrigation District; Notice of Application              include docket number P–2299–082.                     during years when sufficient spill is
                                               Accepted for Filing, Soliciting Motions                    The Commission’s Rules of Practice                 projected to occur; (3) conduct a five-
                                               To Intervene and Protests, Ready for                    require all intervenors filing documents              year program of experimental gravel
                                               Environmental Analysis, and Soliciting                  with the Commission to serve a copy of                cleaning; (4) implement a boulder
                                               Comments, Recommendations,                              that document on each person on the                   placement program to improve aquatic
                                               Preliminary Terms and Conditions, and                   official service list for the project.                habitat between RM 42 and RM 50; (5)
                                               Preliminary Fishway Prescriptions                       Further, if an intervenor files comments              contribute $50,000 per year to the
                                                                                                       or documents with the Commission                      California Division of Boating and
                                                  Take notice that the following                       relating to the merits of an issue that               Waterways to assist with the removal of
                                               hydroelectric application has been filed                may affect the responsibilities of a                  water hyacinth and other non-native
                                               with the Commission and is available                    particular resource agency, they must                 flora; (6) implement a fall-run Chinook
                                               for public inspection.                                  also serve a copy of the document on                  spawning improvement
                                                  a. Type of Application: Major License.               that resource agency.                                 superimposition reduction program; (7)
                                                  b. Project No.: 2299–082.                                                                                  implement a predator control and
                                                  c. Date filed: October 11, 2017.                        k. This application has been accepted
                                                                                                       for filing and is now ready for                       suppression program that would
                                                  d. Applicant: Turlock Irrigation                                                                           include construction and operation of a
                                               District and Modesto Irrigation District                environmental analysis.
                                                                                                                                                             fish counting/barrier weir and active
                                               (Districts).                                               l. The Don Pedro Project consists of
                                                                                                                                                             predator control and suppression; (8)
                                                  e. Name of Project: Don Pedro                        the following existing facilities: (1) A
                                                                                                                                                             develop a fall-run Chinook salmon
                                               Hydroelectric Project.                                  580-foot-high, 1,900-foot-long earth and
                                                                                                                                                             restoration hatchery; (9) install an
                                                  f. Location: The Don Pedro Project is                rockfill dam with a gross storage
                                                                                                                                                             improved take-out facility at RM 78 at
                                               located on the Tuolumne River in                        capacity of 2,030,000 acre-feet, located              Ward’s Ferry and a new take-out and
                                               Tuolumne County, California. Portions                   on the Tuolumne River 54.8 miles                      put-in facility at RM 25.7; (10)
                                               of the project occupy public lands                      upstream of its confluence with the San               implement flow-related measures
                                               managed by the Bureau of Land                           Joaquin River; (2) a 30-foot-high, 45-                including the construction of infiltration
                                               Management.                                             foot-wide, 135-foot-long gated spillway               galleries and the provision of base flows
                                                  g. Filed Pursuant to: Federal Power                  including three radial gates each 45-                 and pulse flows designed to benefit
                                               Act, 16 U.S.C. 791(a)–825(r).                           foot-wide by 30-foot-high; (3) a 995-foot-            specific salmonid life stages and
                                                  h. Applicant Contacts: Steve Boyd,                   long ungated ogee spillway with a crest               provide for recreational boating; (11)
                                               Turlock Irrigation District, 333 East                   elevation of 830 feet; (4) a set of outlet            monitor the effectiveness of gravel,
                                               Canal Drive, Turlock, California 95381–                 works located at the left abutment of the             aquatic habitat and predator control
                                               0949, (209) 883–8300; and Anna                          dam consisting of three individual gate               measures; and (12) implement
                                               Brathwaite, Modesto Irrigation District,                housings, each containing two 4-foot-by-              management plans for fire prevention
                                               P.O. Box 4060, Modesto, CA 95352,                       5-foot slide gates; (5) a 3,500-foot-long-            and response, spill prevention and
                                               (209) 526–7384.                                         concrete lined tunnel with a total                    countermeasures, aquatic invasive
                                                  i. FERC Contact: Jim Hastreiter at                   hydraulic capacity of 7,500 cubic feet                species, woody debris, terrestrial
                                               (503) 552–2760 or james.hastreiter@                     per second; (6) a 2,960-foot-long power               resources, recreation resources, historic
                                               ferc.gov.                                               tunnel located in the left abutment of                properties, and transportation.
                                                  j. Deadline for filing motions to                    the dam that transitions from an 18-foot                 m. A copy of the application is
                                               intervene and protests, comments,                       concrete-lined section to a 16-foot steel-            available for review at the Commission
                                               recommendations, preliminary terms                      lined section; (7) a 21-foot-high, 12-foot-           in the Public Reference Room or may be
                                               and conditions, and preliminary                         wide emergency closure fixed-wheel                    viewed on the Commission’s Web site at
                                               prescriptions: 60 days from the issuance                gate; (8) a powerhouse located                        http://www.ferc.gov using the
                                               date of this notice; reply comments are                 immediately downstream of the dam                     ‘‘eLibrary’’ link. Enter the docket
                                               due 105 days from the issuance date of                  containing a 72-inch hollow jet valve                 number excluding the last three digits in
                                               this notice.                                            and four Francis turbine-generator units              the docket number field to access the
                                                  The Commission strongly encourages                   with a nameplate capacity of 168                      document. For assistance, contact FERC
                                               electronic filing. Please file motions to               megawatts; (9) a switchyard located on                Online Support. A copy is also available
                                               intervene, protests, comments,                          top of the powerhouse; (10) a 75-foot-                for inspection and reproduction at the
                                               recommendations, preliminary terms                      high earth and rockfill Gasburg Creek                 address in item h above.
                                               and conditions, and preliminary                         dike with a slide-gate controlled 18-                    Register online at http://
                                               fishway prescriptions using the                         inch-diameter conduit located near the                www.ferc.gov/docs-filing/
                                               Commission’s eFiling system at http://                  downstream end of the spillway; (11)                  esubscription.asp to be notified via
                                               www.ferc.gov/docs-filing/efiling.asp.                   three small embankments dikes (dike A                 email of new filings and issuances
                                               Commenters can submit brief comments                    is located between the main dam and                   related to this or other pending projects.
daltland on DSKBBV9HB2PROD with NOTICES




                                               up to 6,000 characters, without prior                   spillway and dikes B and C are located                For assistance, contact FERC Online
                                               registration, using the eComment system                 east of the main dam); (12) recreation                Support.
                                               at http://www.ferc.gov/docs-filing/                     facilities on Don Pedro reservoir,                       n. Anyone may submit comments, a
                                               ecomment.asp. You must include your                     including Fleming Meadows, Blue Oaks,                 protest, or a motion to intervene in
                                               name and contact information at the end                 and Moccasin Point; and (13)                          accordance with the requirements of
                                               of your comments. For assistance,                       appurtenant facilities and features                   Rules of Practice and Procedure, 18 CFR
                                               please contact FERC Online Support at                   including access roads. The project’s                 385.210, .211, and .214. In determining


                                          VerDate Sep<11>2014   18:07 Dec 05, 2017   Jkt 244001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\06DEN1.SGM   06DEN1


                                                                        Federal Register / Vol. 82, No. 233 / Wednesday, December 6, 2017 / Notices                                        57597

                                               the appropriate action to take, the                        q. A license applicant must file no                Docket No. ER17–1376, Midcontinent
                                               Commission will consider all protests or                later than 60 days following the date of                Independent System Operator, Inc.
                                               other comments filed, but only those                    issuance of the notice of acceptance and              Docket No. ER17–1570, Midcontinent
                                               who file a motion to intervene in                       ready for environmental analysis                        Independent System Operator, Inc.
                                               accordance with the Commission’s                        provided for in 5.22: (1) A copy of the               Docket No. ER17–1571, Midcontinent
                                               Rules may become a party to the                         water quality certification; (2) a copy of              Independent System Operator, Inc.
                                               proceeding. Any comments, protests, or                  the request for certification, including              Docket No. ER17–1712, Midcontinent
                                               motions to intervene must be received                   proof of the date on which the certifying               Independent System Operator, Inc.
                                               on or before the specified comment date                 agency received the request; or (3)                   Docket No. ER17–1376, Midcontinent
                                               for the particular application.                         evidence of waiver of water quality                     Independent System Operator, Inc.
                                                  All filings must (1) bear in all capital             certification.                                        Docket No. ER17–2097, Midcontinent
                                               letters the title PROTEST, MOTION TO                      Dated: November 30, 2017.                             Independent System Operator, Inc.
                                               INTERVENE, COMMENTS, REPLY                              Nathaniel J. Davis, Sr.,                              Docket No. ER17–2113, Midcontinent
                                               COMMENTS, RECOMMENDATIONS,                              Deputy Secretary.                                       Independent System Operator, Inc.
                                               PRELIMINARY TERMS AND                                   [FR Doc. 2017–26246 Filed 12–5–17; 8:45 am]
                                                                                                                                                             Docket No. ER17–1712, Midcontinent
                                               CONDITIONS, or PRELIMINARY                                                                                      Independent System Operator, Inc.
                                                                                                       BILLING CODE 6717–01–P
                                               FISHWAY PRESCRIPTIONS; (2) set                                                                                Docket No. ER17–215, Midcontinent
                                               forth in the heading the name of the                                                                            Independent System Operator, Inc.
                                               applicant and the project number of the                 DEPARTMENT OF ENERGY                                  Docket No. ER17–2220, Midcontinent
                                               application to which the filing                                                                                 Independent System Operator, Inc.
                                               responds; (3) furnish the name, address,                Federal Energy Regulatory                             Docket No. ER17–2323, Midcontinent
                                               and telephone number of the person                      Commission                                              Independent System Operator, Inc.
                                               protesting or intervening; and (4)                                                                            Docket No. ER16–2225, Midcontinent
                                               otherwise comply with the requirements                  Notice of Commission and                                Independent System Operator, Inc.
                                               of 18 CFR 385.2001 through 385.2005.                    Commission Staff Attendance at                        Docket No. ER16–2355, Midcontinent
                                               All comments, recommendations, terms                    Midcontinent Independent System                         Independent System Operator, Inc.
                                               and conditions or prescriptions must set                Operator, Inc. Meetings                               Docket No. ER17–2552, Midcontinent
                                               forth their evidentiary basis and                          The Federal Energy Regulatory                        Independent System Operator, Inc.
                                               otherwise comply with the requirements                  Commission hereby gives notice that                   Docket No. ER18–12, Midcontinent
                                               of 18 CFR 4.34(b). Agencies may obtain                  members of the Commission and its staff                 Independent System Operator, Inc.
                                               copies of the application directly from                 may attend the following MISO-related                 Docket No. ER18–23, Midcontinent
                                               the applicant. A copy of any protest or                 meetings: MISO Board of Directors                       Independent System Operator, Inc.
                                               motion to intervene must be served                      Meeting, December 7, 2017, 8:30 a.m.–                 Docket No. ER18–31, Midcontinent
                                               upon each representative of the                         11:00 a.m.                                              Independent System Operator, Inc.
                                               applicant specified in the particular                      Unless otherwise noted, all of the                 Docket No. ER18–39, Midcontinent
                                               application. A copy of all other filings                meetings above will be held at: MISO                    Independent System Operator, Inc.
                                               in reference to this application must be                Headquarters, 720 City Center Drive,                  Docket No. ER18–40, Midcontinent
                                               accompanied by proof of service on all                  Carmel, IN 46032–7574.                                  Independent System Operator, Inc.
                                               persons listed in the service list                         Further information and dial in                    Docket No. ER18–41, Midcontinent
                                               prepared by the Commission in this                      instructions may be found at https://                   Independent System Operator, Inc.
                                               proceeding, in accordance with 18 CFR                   www.misoenergy.org. All meetings are                  Docket No. ER18–42, Midcontinent
                                               4.34(b) and 385.2010.                                   Eastern Time.                                           Independent System Operator, Inc.
                                                  o. Procedural Schedule:                                 The discussions may address matters                Docket No. ER18–44, Midcontinent
                                                                                                       at issue in the following proceedings:                  Independent System Operator, Inc.
                                                  The application will be processed                                                                          Docket No. ER17–2097, Midcontinent
                                                                                                       Docket No. ER16–1766, Midcontinent
                                               according to the following revised                                                                              Independent System Operator, Inc.
                                                                                                          Independent System Operator, Inc.
                                               Hydro Licensing Schedule. Revisions to                  Docket No. EL16–108, Tilton Energy v.                 Docket No. ER18–56, Midcontinent
                                               the schedule may be made as                                Midcontinent Independent System                      Independent System Operator, Inc.
                                               appropriate.                                               Operator, Inc.                                     Docket No. EL18–7, Midcontinent
                                                                                                       Docket No. ER16–2225, Midcontinent                      Independent System Operator, Inc.
                                                          Milestone                   Target date
                                                                                                          Independent System Operator, Inc.                  Docket No. ER18–75, Midcontinent
                                               Filing of recommendations,            December          Docket No. ER16–2355, Midcontinent                      Independent System Operator, Inc.
                                                  preliminary terms and con-           2017.              Independent System Operator, Inc.                  Docket No. ER18–149, Midcontinent
                                                  ditions, and preliminary                             Docket No. ER17–215, Midcontinent                       Independent System Operator, Inc.
                                                  fishway prescriptions.                                  Independent System Operator, Inc.                  Docket No. ER18–146, Midcontinent
                                               Commission issues Draft En-           July 2018.        Docket No. ER12–1266, Midcontinent                      Independent System Operator, Inc.
                                                  vironmental Statement                                   Independent System Operator, Inc.                  Docket No. ER18–136, Midcontinent
                                                  (EIS).                                               Docket No. ER17–67, Midcontinent                        Independent System Operator, Inc.
                                               Comments on Draft EIS ........        September            Independent System Operator, Inc.                  Docket No. ER18–170, Midcontinent
                                                                                       2018.           Docket No. ER17–827, Midcontinent
                                               Modified Terms and Condi-             November                                                                  Independent System Operator, Inc.
                                                                                                          Independent System Operator, Inc.
                                                 tions.                                2018.           Docket No. ER17–305, Midcontinent                     Docket No. ER18–193, Midcontinent
daltland on DSKBBV9HB2PROD with NOTICES




                                               Commission Issues Final EIS           February             Independent System Operator, Inc.                    Independent System Operator, Inc.
                                                                                       2019.           Docket No. ER17–892, Midcontinent                     Docket No. ER18–224, Midcontinent
                                                                                                          Independent System Operator, Inc.                    Independent System Operator, Inc.
                                                 p. Final amendments to the                            Docket No. ER17–156, Midcontinent                     Docket No. ER17–721, Midcontinent
                                               application must be filed with the                         Independent System Operator, Inc.                    Independent System Operator, Inc.
                                               Commission no later than 30 days from                   Docket No. ER16–2534, Midcontinent                      These meetings are open to the
                                               the issuance date of this notice.                          Independent System Operator, Inc.                  public.


                                          VerDate Sep<11>2014   18:07 Dec 05, 2017   Jkt 244001   PO 00000   Frm 00029   Fmt 4703   Sfmt 4703   E:\FR\FM\06DEN1.SGM   06DEN1



Document Created: 2017-12-06 00:22:13
Document Modified: 2017-12-06 00:22:13
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 57596 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR