82_FR_60841 82 FR 60597 - Blue Mountain Midstream, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Blue Mountain Delivery Line Project and Request for Comments on Environmental Issues

82 FR 60597 - Blue Mountain Midstream, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Blue Mountain Delivery Line Project and Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 244 (December 21, 2017)

Page Range60597-60599
FR Document2017-27494

Federal Register, Volume 82 Issue 244 (Thursday, December 21, 2017)
[Federal Register Volume 82, Number 244 (Thursday, December 21, 2017)]
[Notices]
[Pages 60597-60599]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-27494]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-14-000]


Blue Mountain Midstream, LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed Blue Mountain Delivery Line 
Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Blue Mountain Delivery Line 
Project involving construction and operation of facilities by Blue 
Mountain Midstream, LLC (Blue Mountain) in Grady County, Oklahoma. The 
Commission will use this EA in its decision-making process to determine 
whether the project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before January 16, 2018.
    If you sent comments on this project to the Commission before the 
opening of this docket on November 9, 2017, you will need to file those 
comments in Docket No. CP18-14-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about

[[Page 60598]]

the acquisition of an easement to construct, operate, and maintain the 
proposed facilities. The company would seek to negotiate a mutually 
acceptable agreement. However, if the Commission approves the project, 
that approval conveys with it the right of eminent domain. Therefore, 
if easement negotiations fail to produce an agreement, the pipeline 
company could initiate condemnation proceedings where compensation 
would be determined in accordance with state law.
    Blue Mountain provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC website (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or [email protected]. Please carefully follow 
these instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's website (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's website (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP18-14-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    Blue Mountain proposes to construct and operate two natural gas 
pipelines totaling 9.57 miles and a metering and pigging facility in 
Grady County, Oklahoma.\1\ The Blue Mountain Deliver Line would provide 
about 225 million cubic feet of natural gas per day to markets in 
Oklahoma and neighboring states. According to Blue Mountain, its 
project would accommodate natural gas development in Grady County, 
Oklahoma.
---------------------------------------------------------------------------

    \1\ A ``pig'' is a tool that the pipeline company inserts into 
and pushes through the pipeline for cleaning the pipeline, 
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------

    The Blue Mountain Delivery Line Project would consist of the 
following facilities:
     Two natural gas pipelines, the Enable Discharge Line #127 
(Line 127) (4.4 miles) and Enable Discharge Line #128 (Line 128) (5.2 
miles); and
     a metering and pigging facility.
    The general location of the project facilities is shown in appendix 
1.\2\
---------------------------------------------------------------------------

    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE, Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 80.7 
acres of land for the aboveground facilities and the pipelines. 
Following construction, Blue Mountain would maintain about 37.9 acres 
for permanent operation of the project's facilities; the remaining 
acreage would be restored and revert to former uses.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\3\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     water resources, fisheries, and wetlands;
     vegetation and wildlife;
     endangered and threatened species;
     cultural resources;
     land use;
     air quality and noise;
     public safety; and
     cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\4\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\5\ We will define the

[[Page 60599]]

project-specific Area of Potential Effects (APE) in consultation with 
the SHPO as the project develops. On natural gas facility projects, the 
APE at a minimum encompasses all areas subject to ground disturbance 
(examples include construction right-of-way, contractor/pipe storage 
yards, compressor stations, and access roads). Our EA for this project 
will document our findings on the impacts on historic properties and 
summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; Native 
American Tribes; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's website. Motions to intervene are more fully described 
at http://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP18-
14). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public sessions or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: December 15, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-27494 Filed 12-20-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                         Federal Register / Vol. 82, No. 244 / Thursday, December 21, 2017 / Notices                                                60597

                                                  Filed Date: 12/14/17.                                DEPARTMENT OF ENERGY                                    Dated: December 15, 2017.
                                                  Accession Number: 20171214–5155.                                                                           Nathaniel J. Davis, Sr.,
                                                                                                       Federal Energy Regulatory                             Deputy Secretary.
                                                  Comments Due: 5 p.m. ET 1/4/18.                      Commission                                            [FR Doc. 2017–27493 Filed 12–20–17; 8:45 am]
                                                 Docket Numbers: ER18–455–000.                                                                               BILLING CODE 6717–01–P
                                                                                                       Combined Notice of Filings #2
                                                 Applicants: ISO New England Inc.,
                                               New England Power Pool Participants                        Take notice that the Commission
                                               Committee.                                              received the following electric rate                  DEPARTMENT OF ENERGY
                                                 Description: § 205(d) Rate Filing: ISO–               filings:
                                                                                                                                                             Federal Energy Regulatory
                                               NE and NEPOOL Filing Re: CSO                               Docket Numbers: ER17–1138–002.                     Commission
                                               Transfer Improvements to be effective                      Applicants: PJM Interconnection,
                                                                                                       L.L.C.                                                [Docket No. CP18–14–000]
                                               3/1/2018.
                                                                                                          Description: Compliance filing:
                                                 Filed Date: 12/15/17.                                 Compliance Filing Pursuant to the Nov.                Blue Mountain Midstream, LLC; Notice
                                                 Accession Number: 20171215–5054.                      17, 2017 Order in Docket No. ER17–                    of Intent To Prepare an Environmental
                                                                                                       1138 to be effective 5/9/2017.                        Assessment for the Proposed Blue
                                                 Comments Due: 5 p.m. ET 1/5/18.                                                                             Mountain Delivery Line Project and
                                                                                                          Filed Date: 12/15/17.
                                                 Docket Numbers: ER18–456–000.                            Accession Number: 20171215–5111.                   Request for Comments on
                                                 Applicants: PJM Interconnection,                         Comments Due: 5 p.m. ET 1/5/18.                    Environmental Issues
                                               L.L.C.                                                     Docket Numbers: ER17–1864–001.                        The staff of the Federal Energy
                                                 Description: Tariff Cancellation:                        Applicants: Bayshore Solar A, LLC.                 Regulatory Commission (FERC or
                                               Notice of Cancellation of 1st Rev.                         Description: Compliance filing:                    Commission) will prepare an
                                               Service Agreement No. 2195, Queue No.                   Bayshore Solar A LLC MBR Tariff to be                 environmental assessment (EA) that will
                                               X1–074 to be effective 1/13/2018.                       effective 8/19/2017.                                  discuss the environmental impacts of
                                                                                                          Filed Date: 12/15/17.                              the Blue Mountain Delivery Line Project
                                                 Filed Date: 12/15/17.                                    Accession Number: 20171215–5073.                   involving construction and operation of
                                                 Accession Number: 20171215–5061.                         Comments Due: 5 p.m. ET 1/5/18.                    facilities by Blue Mountain Midstream,
                                                 Comments Due: 5 p.m. ET 1/5/18.                          Docket Numbers: ER17–1909–001.                     LLC (Blue Mountain) in Grady County,
                                                                                                          Applicants: Bayshore Solar C, LLC.                 Oklahoma. The Commission will use
                                                  Docket Numbers: ER18–457–000.                           Description: Compliance filing:                    this EA in its decision-making process
                                                  Applicants: Gainesville Renewable                    Bayshore Solar C LLC MBR Tariff to be                 to determine whether the project is in
                                               Energy Center, LLC.                                     effective 8/26/2017.                                  the public convenience and necessity.
                                                                                                          Filed Date: 12/15/17.                                 This notice announces the opening of
                                                  Description: Tariff Cancellation:
                                                                                                          Accession Number: 20171215–5072.                   the scoping process the Commission
                                               Cancellation of MBR Tariff to be                           Comments Due: 5 p.m. ET 1/5/18.
                                               effective 12/18/2017.                                                                                         will use to gather input from the public
                                                                                                          Docket Numbers: ER18–458–000.                      and interested agencies on the project.
                                                  Filed Date: 12/15/17.                                   Applicants: Midcontinent                           You can make a difference by providing
                                                  Accession Number: 20171215–5069.                     Independent System Operator, Inc.,                    us with your specific comments or
                                                  Comments Due: 5 p.m. ET 1/5/18.                      Ameren Illinois Company.                              concerns about the project. Your
                                                                                                          Description: § 205(d) Rate Filing:                 comments should focus on the potential
                                                  The filings are accessible in the                    2017–12–15_SA 2880 Attachment A                       environmental effects, reasonable
                                               Commission’s eLibrary system by                         Project Specs No. 2 (Ameren-Wabash                    alternatives, and measures to avoid or
                                               clicking on the links or querying the                   Valley UCA) to be effective 11/30/2017.               lessen environmental impacts. Your
                                               docket number.                                             Filed Date: 12/15/17.                              input will help the Commission staff
                                                  Any person desiring to intervene or                     Accession Number: 20171215–5103.                   determine what issues they need to
                                               protest in any of the above proceedings                    Comments Due: 5 p.m. ET 1/5/18.                    evaluate in the EA. To ensure that your
                                               must file in accordance with Rules 211                     The filings are accessible in the                  comments are timely and properly
                                               and 214 of the Commission’s                             Commission’s eLibrary system by                       recorded, please send your comments so
                                               Regulations (18 CFR 385.211 and                         clicking on the links or querying the                 that the Commission receives them in
                                               385.214) on or before 5:00 p.m. Eastern                 docket number.                                        Washington, DC on or before January 16,
                                               time on the specified comment date.                        Any person desiring to intervene or                2018.
                                               Protests may be considered, but                         protest in any of the above proceedings                  If you sent comments on this project
                                               intervention is necessary to become a                   must file in accordance with Rules 211                to the Commission before the opening of
                                               party to the proceeding.                                and 214 of the Commission’s                           this docket on November 9, 2017, you
                                                  eFiling is encouraged. More detailed                 Regulations (18 CFR 385.211 and                       will need to file those comments in
                                               information relating to filing                          385.214) on or before 5:00 p.m. Eastern               Docket No. CP18–14–000 to ensure they
                                               requirements, interventions, protests,                  time on the specified comment date.                   are considered as part of this
                                               service, and qualifying facilities filings              Protests may be considered, but                       proceeding.
                                               can be found at: http://www.ferc.gov/                   intervention is necessary to become a                    This notice is being sent to the
                                               docs-filing/efiling/filing-req.pdf. For                 party to the proceeding.                              Commission’s current environmental
                                               other information, call (866) 208–3676                     eFiling is encouraged. More detailed               mailing list for this project. State and
daltland on DSKBBV9HB2PROD with NOTICES




                                               (toll free). For TTY, call (202) 502–8659.              information relating to filing                        local government representatives should
                                                                                                       requirements, interventions, protests,                notify their constituents of this
                                                 Dated: December 15, 2017.
                                                                                                       service, and qualifying facilities filings            proposed project and encourage them to
                                               Nathaniel J. Davis, Sr.,                                can be found at: http://www.ferc.gov/                 comment on their areas of concern.
                                               Deputy Secretary.                                       docs-filing/efiling/filing-req.pdf. For                  If you are a landowner receiving this
                                               [FR Doc. 2017–27492 Filed 12–20–17; 8:45 am]            other information, call (866) 208–3676                notice, a pipeline company
                                               BILLING CODE 6717–01–P                                  (toll free). For TTY, call (202) 502–8659.            representative may contact you about


                                          VerDate Sep<11>2014   20:57 Dec 20, 2017   Jkt 244001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\21DEN1.SGM   21DEN1


                                               60598                     Federal Register / Vol. 82, No. 244 / Thursday, December 21, 2017 / Notices

                                               the acquisition of an easement to                       totaling 9.57 miles and a metering and                 proposed project under these general
                                               construct, operate, and maintain the                    pigging facility in Grady County,                      headings:
                                               proposed facilities. The company would                  Oklahoma.1 The Blue Mountain Deliver                      • Geology and soils;
                                               seek to negotiate a mutually acceptable                 Line would provide about 225 million                      • water resources, fisheries, and
                                               agreement. However, if the Commission                   cubic feet of natural gas per day to                   wetlands;
                                               approves the project, that approval                     markets in Oklahoma and neighboring                       • vegetation and wildlife;
                                               conveys with it the right of eminent                    states. According to Blue Mountain, its                   • endangered and threatened species;
                                               domain. Therefore, if easement                          project would accommodate natural gas                     • cultural resources;
                                               negotiations fail to produce an                         development in Grady County,                              • land use;
                                               agreement, the pipeline company could                   Oklahoma.                                                 • air quality and noise;
                                               initiate condemnation proceedings                                                                                 • public safety; and
                                                                                                         The Blue Mountain Delivery Line                         • cumulative impacts.
                                               where compensation would be                             Project would consist of the following                    We will also evaluate reasonable
                                               determined in accordance with state                     facilities:                                            alternatives to the proposed project or
                                               law.                                                      • Two natural gas pipelines, the                     portions of the project, and make
                                                 Blue Mountain provided landowners                     Enable Discharge Line #127 (Line 127)
                                               with a fact sheet prepared by the FERC                                                                         recommendations on how to lessen or
                                                                                                       (4.4 miles) and Enable Discharge Line                  avoid impacts on the various resource
                                               entitled ‘‘An Interstate Natural Gas                    #128 (Line 128) (5.2 miles); and                       areas.
                                               Facility On My Land? What Do I Need                       • a metering and pigging facility.                      The EA will present our independent
                                               To Know?’’ This fact sheet addresses a                    The general location of the project                  analysis of the issues. The EA will be
                                               number of typically asked questions,                    facilities is shown in appendix 1.2                    available in the public record through
                                               including the use of eminent domain
                                                                                                       Land Requirements for Construction                     eLibrary. Depending on the comments
                                               and how to participate in the
                                                                                                                                                              received during the scoping process, we
                                               Commission’s proceedings. It is also                      Construction of the proposed facilities              may also publish and distribute the EA
                                               available for viewing on the FERC                       would disturb about 80.7 acres of land                 to the public for an allotted comment
                                               website (www.ferc.gov).                                 for the aboveground facilities and the                 period. We will consider all comments
                                               Public Participation                                    pipelines. Following construction, Blue                on the EA before making our
                                                                                                       Mountain would maintain about 37.9                     recommendations to the Commission.
                                                  For your convenience, there are three                acres for permanent operation of the
                                               methods you can use to submit your                                                                             To ensure we have the opportunity to
                                                                                                       project’s facilities; the remaining                    consider and address your comments,
                                               comments to the Commission. The                         acreage would be restored and revert to
                                               Commission encourages electronic filing                                                                        please carefully follow the instructions
                                                                                                       former uses.                                           in the Public Participation section,
                                               of comments and has expert staff
                                               available to assist you at (202) 502–8258               The EA Process                                         beginning on page 2.
                                               or FercOnlineSupport@ferc.gov. Please                                                                             With this notice, we are asking
                                                                                                          The National Environmental Policy                   agencies with jurisdiction by law and/
                                               carefully follow these instructions so                  Act (NEPA) requires the Commission to
                                               that your comments are properly                                                                                or special expertise with respect to the
                                                                                                       take into account the environmental                    environmental issues of this project to
                                               recorded.                                               impacts that could result from an action
                                                  (1) You can file your comments                                                                              formally cooperate with us in the
                                                                                                       whenever it considers the issuance of a                preparation of the EA.4 Agencies that
                                               electronically using the eComment                       Certificate of Public Convenience and
                                               feature on the Commission’s website                                                                            would like to request cooperating
                                                                                                       Necessity. NEPA also requires us 3 to                  agency status should follow the
                                               (www.ferc.gov) under the link to                        discover and address concerns the
                                               Documents and Filings. This is an easy                                                                         instructions for filing comments
                                                                                                       public may have about proposals. This                  provided under the Public Participation
                                               method for submitting brief, text-only                  process is referred to as ‘‘scoping.’’ The
                                               comments on a project;                                                                                         section of this notice.
                                                                                                       main goal of the scoping process is to
                                                  (2) You can file your comments                       focus the analysis in the EA on the                    Consultations Under Section 106 of the
                                               electronically by using the eFiling                     important environmental issues. By this                National Historic Preservation Act
                                               feature on the Commission’s website                     notice, the Commission requests public
                                               (www.ferc.gov) under the link to                                                                                 In accordance with the Advisory
                                                                                                       comments on the scope of the issues to                 Council on Historic Preservation’s
                                               Documents and Filings. With eFiling,                    address in the EA. We will consider all
                                               you can provide comments in a variety                                                                          implementing regulations for section
                                                                                                       filed comments during the preparation                  106 of the National Historic
                                               of formats by attaching them as a file                  of the EA.
                                               with your submission. New eFiling                                                                              Preservation Act, we are using this
                                                                                                          In the EA we will discuss impacts that              notice to initiate consultation with the
                                               users must first create an account by                   could occur as a result of the
                                               clicking on ‘‘eRegister.’’ If you are filing                                                                   applicable State Historic Preservation
                                                                                                       construction and operation of the                      Office (SHPO), and to solicit their views
                                               a comment on a particular project,
                                               please select ‘‘Comment on a Filing’’ as                                                                       and those of other government agencies,
                                                                                                         1 A ‘‘pig’’ is a tool that the pipeline company
                                               the filing type; or                                                                                            interested Indian tribes, and the public
                                                                                                       inserts into and pushes through the pipeline for
                                                  (3) You can file a paper copy of your                cleaning the pipeline, conducting internal
                                                                                                                                                              on the project’s potential effects on
                                               comments by mailing them to the                         inspections, or other purposes.                        historic properties.5 We will define the
                                               following address. Be sure to reference                   2 The appendices referenced in this notice will

                                               the project docket number (CP18–14–                     not appear in the Federal Register. Copies of            4 The Council on Environmental Quality

                                                                                                       appendices were sent to all those receiving this       regulations addressing cooperating agency
                                               000) with your submission: Kimberly D.
daltland on DSKBBV9HB2PROD with NOTICES




                                                                                                       notice in the mail and are available at www.ferc.gov   responsibilities are at Title 40, Code of Federal
                                               Bose, Secretary, Federal Energy                         using the link called ‘‘eLibrary’’ or from the         Regulations, Part 1501.6.
                                               Regulatory Commission, 888 First Street                 Commission’s Public Reference Room, 888 First            5 The Advisory Council on Historic Preservation’s

                                               NE, Room 1A, Washington, DC 20426.                      Street NE, Washington, DC 20426, or call (202) 502–    regulations are at Title 36, Code of Federal
                                                                                                       8371. For instructions on connecting to eLibrary,      Regulations, Part 800. Those regulations define
                                               Summary of the Proposed Project                         refer to the last page of this notice.                 historic properties as any prehistoric or historic
                                                                                                         3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the           district, site, building, structure, or object included
                                                 Blue Mountain proposes to construct                   environmental staff of the Commission’s Office of      in or eligible for inclusion in the National Register
                                               and operate two natural gas pipelines                   Energy Projects.                                       of Historic Places.



                                          VerDate Sep<11>2014   20:57 Dec 20, 2017   Jkt 244001   PO 00000   Frm 00021   Fmt 4703   Sfmt 4703   E:\FR\FM\21DEN1.SGM    21DEN1


                                                                         Federal Register / Vol. 82, No. 244 / Thursday, December 21, 2017 / Notices                                            60599

                                               project-specific Area of Potential Effects              Commission’s Office of External Affairs,              proposed interim decisions, EPA is
                                               (APE) in consultation with the SHPO as                  at (866) 208–FERC, or on the FERC                     releasing and obtaining public comment
                                               the project develops. On natural gas                    website at www.ferc.gov using the                     on these two benefits assessments at an
                                               facility projects, the APE at a minimum                 ‘‘eLibrary’’ link. Click on the eLibrary              earlier stage of the registration review
                                               encompasses all areas subject to ground                 link, click on ‘‘General Search’’ and                 process. These benefits assessments will
                                               disturbance (examples include                           enter the docket number, excluding the                help EPA evaluate the impacts of
                                               construction right-of-way, contractor/                  last three digits in the Docket Number                potential measures to reduce certain
                                               pipe storage yards, compressor stations,                field (i.e., CP18–14). Be sure you have               risks to pollinators identified in
                                               and access roads). Our EA for this                      selected an appropriate date range. For               previously issued preliminary pollinator
                                               project will document our findings on                   assistance, please contact FERC Online                risk assessments. EPA is not proposing
                                               the impacts on historic properties and                  Support at FercOnlineSupport@ferc.gov                 any mitigation at this stage, and
                                               summarize the status of consultations                   or toll free at (866) 208–3676, or for                anticipates that early input and
                                               under section 106.                                      TTY, contact (202) 502–8659. The                      information from the public on the
                                               Environmental Mailing List                              eLibrary link also provides access to the             benefits of these compounds will be
                                                                                                       texts of formal documents issued by the               helpful as EPA evaluates and considers
                                                  The environmental mailing list                       Commission, such as orders, notices,                  the risks and the benefits of the
                                               includes federal, state, and local                      and rulemakings.                                      neonicotinoid insecticides. Finally, EPA
                                               government representatives and                             In addition, the Commission offers a               is releasing a response to public
                                               agencies; elected officials; Native                     free service called eSubscription which               comments on the Agency’s 2014
                                               American Tribes; and local libraries and                allows you to keep track of all formal                assessment of the benefits of
                                               newspapers. This list also includes all                 issuances and submittals in specific                  neonicotinoid seed treatments to
                                               affected landowners (as defined in the                  dockets. This can reduce the amount of                soybean production. This assessment
                                               Commission’s regulations) who are                       time you spend researching proceedings                and associated comments are available
                                               potential right-of-way grantors, whose                  by automatically providing you with                   in docket EPA–HQ–OPP–2014–0737.
                                               property may be used temporarily for                    notification of these filings, document               Copies of all of the benefits assessments
                                               project purposes, or who own homes                      summaries, and direct links to the                    will be placed in the individual
                                               within certain distances of aboveground                 documents. Go to www.ferc.gov/docs-                   chemical dockets for each of the four
                                               facilities, and anyone who submits                      filing/esubscription.asp.                             neonicotinoid insecticides listed in
                                               comments on the project. We will                           Finally, public sessions or site visits            Table 1 of Unit III.
                                               update the environmental mailing list as                will be posted on the Commission’s                    DATES: Comments must be received on
                                               the analysis proceeds to ensure that we                 calendar located at www.ferc.gov/                     or before February 20, 2018.
                                               send the information related to this                    EventCalendar/EventsList.aspx along
                                                                                                                                                             ADDRESSES: Submit your comments,
                                               environmental review to all individuals,                with other related information.
                                               organizations, and government entities                                                                        identified by the docket identification
                                                                                                         Dated: December 15, 2017.                           (ID) number for the specific pesticide of
                                               interested in and/or potentially affected
                                               by the proposed project.                                Nathaniel J. Davis, Sr.,                              interest provided in Table 1 of Unit III,
                                                  If we publish and distribute the EA,                 Deputy Secretary.                                     by one of the following methods:
                                               copies will be sent to the environmental                [FR Doc. 2017–27494 Filed 12–20–17; 8:45 am]             • Federal eRulemaking Portal: http://
                                               mailing list for public review and                      BILLING CODE 6717–01–P
                                                                                                                                                             www.regulations.gov. Follow the online
                                               comment. If you would prefer to receive                                                                       instructions for submitting comments.
                                               a paper copy of the document instead of                                                                       Do not submit electronically any
                                               the CD version or would like to remove                  ENVIRONMENTAL PROTECTION                              information you consider to be
                                               your name from the mailing list, please                 AGENCY                                                Confidential Business Information (CBI)
                                               return the attached Information Request                                                                       or other information whose disclosure is
                                                                                                       [EPA–HQ–OPP–2017–0011; FRL–9970–95]                   restricted by statute.
                                               (appendix 2).
                                                                                                                                                                • Mail: OPP Docket, Environmental
                                               Becoming an Intervenor                                  Registration Review; Neonicotinoid                    Protection Agency Docket Center (EPA/
                                                                                                       Risk Assessments; Neonicotinoid                       DC), (28221T), 1200 Pennsylvania Ave.
                                                  In addition to involvement in the EA
                                                                                                       Benefits Assessments; Notice of                       NW, Washington, DC 20460–0001.
                                               scoping process, you may want to
                                                                                                       Availability                                             • Hand Delivery: To make special
                                               become an ‘‘intervenor’’ which is an
                                               official party to the Commission’s                      AGENCY: Environmental Protection                      arrangements for hand delivery or
                                               proceeding. Intervenors play a more                     Agency (EPA).                                         delivery of boxed information, please
                                               formal role in the process and are able                 ACTION: Notice.
                                                                                                                                                             follow the instructions at http://
                                               to file briefs, appear at hearings, and be                                                                    www.epa.gov/dockets/contacts.html.
                                               heard by the courts if they choose to                   SUMMARY:   This notice announces the                     Additional instructions on
                                               appeal the Commission’s final ruling.                   availability of EPA’s (or Agency) draft               commenting or visiting the docket,
                                               An intervenor formally participates in                  ecological non-pollinator risk                        along with more information about
                                               the proceeding by filing a request to                   assessment for the registration review of             dockets generally, is available at http://
                                               intervene. Instructions for becoming an                 imidacloprid, along with draft human                  www.epa.gov/dockets.
                                               intervenor are in the ‘‘Document-less                   health and non-pollinator ecological                  FOR FURTHER INFORMATION CONTACT:
                                               Intervention Guide’’ under the ‘‘e-filing’’             risk assessments for the registration                    For pesticide specific information
                                               link on the Commission’s website.                       review of clothianidin, thiamethoxam,                 contact: The Chemical Review Manager
daltland on DSKBBV9HB2PROD with NOTICES




                                               Motions to intervene are more fully                     and dinotefuran, and opens a public                   for the pesticide of interest identified in
                                               described at http://www.ferc.gov/                       comment period on these assessments.                  Table 1 of Unit III.
                                               resources/guides/how-to/intervene.asp.                  This notice also announces the                           For general questions on the
                                                                                                       availability of assessments of benefits of            registration review program, contact:
                                               Additional Information                                  neonicotinoid insecticide use in cotton               Dana Friedman, Pesticide Re-Evaluation
                                                 Additional information about the                      and citrus. While EPA typically releases              Division (7508P), Office of Pesticide
                                               project is available from the                           benefits assessments along with the                   Programs, Environmental Protection


                                          VerDate Sep<11>2014   20:57 Dec 20, 2017   Jkt 244001   PO 00000   Frm 00022   Fmt 4703   Sfmt 4703   E:\FR\FM\21DEN1.SGM   21DEN1



Document Created: 2018-10-25 11:00:10
Document Modified: 2018-10-25 11:00:10
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 60597 