The U.S. Nuclear Regulatory Commission (NRC) is issuing for public comment a draft project plan, ``Draft Project Plan to Prepare the U.S. Nuclear Regulatory Commission to License and Regulate Accident Tolerant Fuel.'' The NRC has established a steering committee of senior managers to oversee and set direction for a staff working group to prepare the agency for the anticipated licensing and use of accident tolerant fuel (ATF) in U.S. commercial power reactors. This draft project plan lays out the tasks that must be completed by the agency ahead of licensing submittals in order to conduct meaningful and timely reviews of ATF designs. The plan is expected to be a living document that may evolve as ATF concepts are more clearly defined and schedules for lead test assemblies (LTAs) and batch loading are refined.

Federal Register, Volume 82 Issue 244 (Thursday, December 21, 2017)
[Federal Register Volume 82, Number 244 (Thursday, December 21, 2017)]
[Notices]
[Pages 60633-60634]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-27516]



[[Page 60633]]

-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2017-0236]


Preparing To License Accident Tolerant Fuel

AGENCY: Nuclear Regulatory Commission.

ACTION: Draft project plan; request for comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing for 
public comment a draft project plan, ``Draft Project Plan to Prepare 
the U.S. Nuclear Regulatory Commission to License and Regulate Accident 
Tolerant Fuel.'' The NRC has established a steering committee of senior 
managers to oversee and set direction for a staff working group to 
prepare the agency for the anticipated licensing and use of accident 
tolerant fuel (ATF) in U.S. commercial power reactors. This draft 
project plan lays out the tasks that must be completed by the agency 
ahead of licensing submittals in order to conduct meaningful and timely 
reviews of ATF designs. The plan is expected to be a living document 
that may evolve as ATF concepts are more clearly defined and schedules 
for lead test assemblies (LTAs) and batch loading are refined.

DATES: Submit comments by February 5, 2018. Comments received after 
this date will be considered if it is practical to do so, but the 
Commission is able to ensure consideration only for comments received 
before this date.

ADDRESSES: You may submit comments by any of the following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2017-0236. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     Mail comments to: May Ma, Office of Administration, Mail 
Stop: OWFN-2-A13, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Andrew Proffitt, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 
20555-0001; telephone: 301-415-1418, email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2017-0236 when contacting the NRC 
about the availability of information for this action. You may obtain 
publicly-available information related to this action by any of the 
following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2017-0236.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
``Draft Project Plan to Prepare the U.S. Nuclear Regulatory Commission 
to License and Regulate Accident Tolerant Fuel,'' is available in ADAMS 
under Package Accession No. ML17325B771.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2017-0236 in your comment submission.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC posts all comment submissions at http://www.regulations.gov as well as entering the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment submissions into ADAMS.

II. Discussion

    The Offices of Nuclear Reactor Regulation, New Reactors, Nuclear 
Material Safety and Safeguards, and Nuclear Regulatory Research are 
preparing for anticipated licensing and use of ATF in the United States 
commercial power reactors.
    Several fuel vendors, in coordination with Department of Energy 
(DOE), have announced plans to develop and seek approval for various 
fuel designs with enhanced accident tolerance (i.e., fuels with longer 
coping times during loss of cooling conditions). The designs being 
considered in the development of this plan include Cr coated claddings, 
Cr-doped UO2 pellets, FeCrAl cladding, SiC cladding, U3Si2 pellets, and 
metallic fuels. For these ATF designs, the time frames for initial 
irradiation of LTA programs and topical report/license amendment 
request review were used as a basis for the timelines discussed in this 
plan.
    The NRC has entered into a Memorandum of Understanding with DOE to 
collaborate on the nuclear safety research of enhanced ATFs that will 
reduce duplication of efforts and make the appropriate data available 
for regulatory decision processes. In preparing the agency to conduct 
meaningful and timely reviews of these advanced fuel designs, the NRC 
is conducting advanced planning, reviewing the existing regulatory 
infrastructure, and identifying needs for additional analysis 
capabilities and the development of unique critical skillsets within 
the staff.
    This project plan outlines the preliminary strategy for preparing 
the NRC to license ATF designs. It also identifies the lead 
organization for each planned activity. The project plan does not cover 
existing licensing activities, as they follow existing processes for 
which schedules and regulatory approaches are well-established. Current 
preparation for ATF licensing is focused on light water reactor (LWR) 
fuel for the operating fleet. There may be synergies between the 
revolutionary LWR ATF fuel development and fuel safety qualification of 
some types of non-LWR fuels for advanced reactor designs. As 
appropriate, the NRC will leverage any synergies to optimize licensing 
efficiency and effectiveness.
    The NRC is issuing the plan for public comment to solicit feedback 
and insight from stakeholders to ensure that the plan will 
appropriately prepare the NRC to license and regulate the ATF designs 
the industry is currently pursuing on a schedule consistent with 
industry timelines.


[[Page 60634]]


    Dated at Rockville, Maryland, this 18th day of December 2017.

    For the Nuclear Regulatory Commission.
Mirela Gavrilas,
Director, Division of Safety Systems, Office of Nuclear Reactor 
Regulation.
[FR Doc. 2017-27516 Filed 12-20-17; 8:45 am]
 BILLING CODE 7590-01-P



                                                                         Federal Register / Vol. 82, No. 244 / Thursday, December 21, 2017 / Notices                                            60633

                                               NUCLEAR REGULATORY                                      SUPPLEMENTARY INFORMATION:                            II. Discussion
                                               COMMISSION                                              I. Obtaining Information and                             The Offices of Nuclear Reactor
                                               [NRC–2017–0236]                                         Submitting Comments                                   Regulation, New Reactors, Nuclear
                                                                                                                                                             Material Safety and Safeguards, and
                                               Preparing To License Accident                           A. Obtaining Information                              Nuclear Regulatory Research are
                                               Tolerant Fuel                                              Please refer to Docket ID NRC–2017–                preparing for anticipated licensing and
                                                                                                       0236 when contacting the NRC about                    use of ATF in the United States
                                               AGENCY: Nuclear Regulatory
                                                                                                       the availability of information for this              commercial power reactors.
                                               Commission.
                                                                                                       action. You may obtain publicly-                         Several fuel vendors, in coordination
                                               ACTION: Draft project plan; request for
                                                                                                       available information related to this                 with Department of Energy (DOE), have
                                               comment.                                                                                                      announced plans to develop and seek
                                                                                                       action by any of the following methods:
                                               SUMMARY:   The U.S. Nuclear Regulatory                     • Federal Rulemaking website: Go to                approval for various fuel designs with
                                               Commission (NRC) is issuing for public                  http://www.regulations.gov and search                 enhanced accident tolerance (i.e., fuels
                                               comment a draft project plan, ‘‘Draft                   for Docket ID NRC–2017–0236.                          with longer coping times during loss of
                                               Project Plan to Prepare the U.S. Nuclear                                                                      cooling conditions). The designs being
                                                                                                          • NRC’s Agencywide Documents
                                               Regulatory Commission to License and                                                                          considered in the development of this
                                                                                                       Access and Management System
                                               Regulate Accident Tolerant Fuel.’’ The                                                                        plan include Cr coated claddings, Cr-
                                                                                                       (ADAMS): You may obtain publicly-
                                               NRC has established a steering                                                                                doped UO2 pellets, FeCrAl cladding,
                                                                                                       available documents online in the
                                               committee of senior managers to oversee                                                                       SiC cladding, U3Si2 pellets, and
                                                                                                       ADAMS Public Documents collection at
                                               and set direction for a staff working                                                                         metallic fuels. For these ATF designs,
                                                                                                       http://www.nrc.gov/reading-rm/
                                               group to prepare the agency for the                                                                           the time frames for initial irradiation of
                                                                                                       adams.html. To begin the search, select
                                               anticipated licensing and use of                                                                              LTA programs and topical report/
                                                                                                       ‘‘ADAMS Public Documents’’ and then
                                               accident tolerant fuel (ATF) in U.S.                                                                          license amendment request review were
                                                                                                       select ‘‘Begin Web-based ADAMS
                                               commercial power reactors. This draft                                                                         used as a basis for the timelines
                                                                                                       Search.’’ For problems with ADAMS,
                                               project plan lays out the tasks that must                                                                     discussed in this plan.
                                                                                                       please contact the NRC’s Public
                                               be completed by the agency ahead of                                                                              The NRC has entered into a
                                                                                                       Document Room (PDR) reference staff at
                                               licensing submittals in order to conduct                                                                      Memorandum of Understanding with
                                                                                                       1–800–397–4209, 301–415–4737, or by
                                               meaningful and timely reviews of ATF                                                                          DOE to collaborate on the nuclear safety
                                                                                                       email to pdr.resource@nrc.gov. The
                                               designs. The plan is expected to be a                                                                         research of enhanced ATFs that will
                                                                                                       ‘‘Draft Project Plan to Prepare the U.S.
                                               living document that may evolve as ATF                                                                        reduce duplication of efforts and make
                                                                                                       Nuclear Regulatory Commission to
                                               concepts are more clearly defined and                                                                         the appropriate data available for
                                                                                                       License and Regulate Accident Tolerant
                                               schedules for lead test assemblies                                                                            regulatory decision processes. In
                                                                                                       Fuel,’’ is available in ADAMS under
                                               (LTAs) and batch loading are refined.                                                                         preparing the agency to conduct
                                                                                                       Package Accession No. ML17325B771.
                                               DATES: Submit comments by February 5,                                                                         meaningful and timely reviews of these
                                                                                                          • NRC’s PDR: You may examine and                   advanced fuel designs, the NRC is
                                               2018. Comments received after this date
                                                                                                       purchase copies of public documents at                conducting advanced planning,
                                               will be considered if it is practical to do
                                                                                                       the NRC’s PDR, Room O1–F21, One                       reviewing the existing regulatory
                                               so, but the Commission is able to ensure
                                                                                                       White Flint North, 11555 Rockville                    infrastructure, and identifying needs for
                                               consideration only for comments
                                                                                                       Pike, Rockville, Maryland 20852.                      additional analysis capabilities and the
                                               received before this date.
                                               ADDRESSES: You may submit comments                      B. Submitting Comments                                development of unique critical skillsets
                                               by any of the following methods:                                                                              within the staff.
                                                                                                         Please include Docket ID NRC–2017–
                                                  • Federal Rulemaking website: Go to                                                                           This project plan outlines the
                                                                                                       0236 in your comment submission.                      preliminary strategy for preparing the
                                               http://www.regulations.gov and search
                                               for Docket ID NRC–2017–0236. Address                      The NRC cautions you not to include                 NRC to license ATF designs. It also
                                               questions about NRC dockets to Carol                    identifying or contact information that               identifies the lead organization for each
                                               Gallagher; telephone: 301–415–3463;                     you do not want to be publicly                        planned activity. The project plan does
                                               email: Carol.Gallagher@nrc.gov. For                     disclosed in your comment submission.                 not cover existing licensing activities, as
                                               technical questions, contact the                        The NRC posts all comment                             they follow existing processes for which
                                               individual listed in the FOR FURTHER                    submissions at http://                                schedules and regulatory approaches are
                                               INFORMATION CONTACT section of this                     www.regulations.gov as well as entering               well-established. Current preparation
                                               document.                                               the comment submissions into ADAMS.                   for ATF licensing is focused on light
                                                  • Mail comments to: May Ma, Office                   The NRC does not routinely edit                       water reactor (LWR) fuel for the
                                               of Administration, Mail Stop: OWFN–2–                   comment submissions to remove                         operating fleet. There may be synergies
                                               A13, U.S. Nuclear Regulatory                            identifying or contact information.                   between the revolutionary LWR ATF
                                               Commission, Washington, DC 20555–                         If you are requesting or aggregating                fuel development and fuel safety
                                               0001.                                                   comments from other persons for                       qualification of some types of non-LWR
                                                  For additional direction on obtaining                submission to the NRC, then you should                fuels for advanced reactor designs. As
                                               information and submitting comments,                    inform those persons not to include                   appropriate, the NRC will leverage any
                                               see ‘‘Obtaining Information and                         identifying or contact information that               synergies to optimize licensing
                                               Submitting Comments’’ in the                            they do not want to be publicly                       efficiency and effectiveness.
                                               SUPPLEMENTARY INFORMATION section of                    disclosed in their comment submission.                   The NRC is issuing the plan for public
daltland on DSKBBV9HB2PROD with NOTICES




                                               this document.                                          Your request should state that the NRC                comment to solicit feedback and insight
                                               FOR FURTHER INFORMATION CONTACT:                        does not routinely edit comment                       from stakeholders to ensure that the
                                               Andrew Proffitt, Office of Nuclear                      submissions to remove such information                plan will appropriately prepare the NRC
                                               Reactor Regulation, U.S. Nuclear                        before making the comment                             to license and regulate the ATF designs
                                               Regulatory Commission, Washington DC                    submissions available to the public or                the industry is currently pursuing on a
                                               20555–0001; telephone: 301–415–1418,                    entering the comment submissions into                 schedule consistent with industry
                                               email: Andrew.Proffitt@nrc.gov.                         ADAMS.                                                timelines.


                                          VerDate Sep<11>2014   20:57 Dec 20, 2017   Jkt 244001   PO 00000   Frm 00056   Fmt 4703   Sfmt 4703   E:\FR\FM\21DEN1.SGM   21DEN1


                                               60634                              Federal Register / Vol. 82, No. 244 / Thursday, December 21, 2017 / Notices

                                                  Dated at Rockville, Maryland, this 18th day                           Requirements Memorandum associated                                        Tuesday, January 30, 2018, and 10:00
                                               of December 2017.                                                        with COMSECY–17–0019 that a next                                          a.m. to 5:00 p.m. EST on Wednesday,
                                                  For the Nuclear Regulatory Commission.                                step in the Yucca Mountain licensing                                      January 31, 2018. If attending the
                                               Mirela Gavrilas,                                                         process is for the NRC to initiate                                        meeting in person, please plan your
                                               Director, Division of Safety Systems, Office                             information-gathering activities                                          arrival to allow additional time (e.g., 15
                                               of Nuclear Reactor Regulation.                                           regarding reinstituting or replacing the                                  to 30 minutes) for security screening.
                                               [FR Doc. 2017–27516 Filed 12–20–17; 8:45 am]                             Licensing Support Network (LSN). The                                      The preliminary agenda is listed below.
                                               BILLING CODE 7590–01–P                                                   LSN, which was used to make                                               Additional details regarding timing of
                                                                                                                        documentary material associated with                                      presentations and changes to the agenda
                                                                                                                        the Yucca Mountain adjudicatory                                           may be obtained through the contacts
                                               NUCLEAR REGULATORY                                                       proceeding available to hearing                                           listed below and will be announced
                                               COMMISSION                                                               participants and the public, was                                          prior to the meeting.
                                                                                                                        decommissioned when the adjudication                                         The primary focus of the meeting will
                                               [NRC–2017–0235]                                                          was suspended in 2011. The                                                be on the options available for
                                                                                                                        information being collected will assist                                   reconstituting the LSN’s functionality.
                                               Licensing Support Network Advisory
                                                                                                                        the Commission in making efficient,                                       The NRC has prepared a paper
                                               Review Panel: Meeting Notice
                                                                                                                        informed decisions concerning                                             describing the options (Agencywide
                                               AGENCY: U.S. Nuclear Regulatory                                          appropriate means for reconstituting the                                  Documents Access and Management
                                               Commission.                                                              LSN’s functionality if the currently-                                     System (ADAMS) Accession No.
                                               ACTION: Notice of meeting.                                               suspended Yucca Mountain                                                  ML17347B671) to be examined and
                                                                                                                        adjudication were to re-commence in                                       discussed at the meeting with the
                                               SUMMARY:   The U.S. Nuclear Regulatory                                   the future.                                                               objective of soliciting the views of the
                                               Commission (NRC) will convene a                                             The meeting will be open to the                                        LSNARP member organizations on the
                                               meeting of the Licensing Support                                         public pursuant to the Federal Advisory                                   best path forward for reconstituting the
                                               Network Advisory Review Panel                                            Committee Act (FACA) (Pub. L. 94–463,                                     LSN or developing a suitable
                                               (LSNARP) on January 30–31, 2018, at                                      86 Stat. 770–776) and will be conducted                                   replacement system if the Yucca
                                               the NRC’s Headquarters Offices in Room                                   as a virtual meeting with representatives                                 Mountain licensing adjudication is
                                               01C3, Three White Flint North Building,                                  of LSNARP member organizations                                            resumed in the future. Additionally, at
                                               11601 Landsdown Street, Rockville,                                       utilizing the capabilities of                                             the conclusion of the January 30
                                               Maryland 20852.                                                          GoToMeeting® and the general public                                       meeting session, the NRC will provide
                                                 The meeting is being held to carry out                                 having access via GoToWebinar®.                                           an orientation session regarding the
                                               the NRC’s responsibilities under the                                     Representatives of LSNARP member                                          ADAMS LSN Library, which currently
                                               U.S. Court of Appeals for the District of                                organizations and the public may also                                     houses the documentary material
                                               Columbia Circuit’s decision in the case                                  attend in person at the location                                          previously accessible via the LSN and
                                               In re Aiken County, 645 F.3d 428 (D.C.                                   indicated above.                                                          provides the technical basis for one of
                                               Cir. 2011), and the Commission’s July                                       Agenda: The meeting will be held                                       the options to be discussed at the
                                               31, 2017, direction in the Staff                                         from 10:00 a.m. to 6:30 p.m. EST on                                       meeting.

                                                                                                                                                                                                                                             EST/PST

                                               January 30, 2018:
                                                   Security Check-in for Onsite Attendees ...........................................................................................................................                  9:30 a.m./6:30 a.m.
                                                   Introduction and Overview ................................................................................................................................................          10:00 a.m./7:00 a.m.
                                                   Meeting Process/Ground Rules
                                                   Status of Adjudicatory Proceeding
                                                   Status of E-Filing/Electronic Hearing Docket and New Exhibit Submission Process
                                                   Break
                                                   History of the LSN
                                                   Introduction of LSN Reconstitution/Replacement Options and New Functional Requirements
                                                   Lunch
                                                   Option 1, Traditional Discovery
                                                   Member Comment and Discussion
                                                   Public Comments
                                                   Break
                                                   Option 2, NRC ADAMS LSN Library
                                                   Member Comment and Discussion
                                                   Public Comments
                                                   Wrap-up/Adjourn
                                                   Break
                                                   ADAMS LSN Library Orientation ......................................................................................................................................                (Approx. 1 Hour.)
                                                   End of Day 1 ....................................................................................................................................................................   6:30 p.m./3:30 p.m.
                                               January 31, 2018:
daltland on DSKBBV9HB2PROD with NOTICES




                                                   Security Check-in for Onsite Attendees ...........................................................................................................................                  9:30 a.m./6:30 a.m.
                                                   Introduction and Overview ................................................................................................................................................          10:00 a.m./7:00 a.m.




                                          VerDate Sep<11>2014        20:57 Dec 20, 2017         Jkt 244001      PO 00000        Frm 00057       Fmt 4703      Sfmt 4703      E:\FR\FM\21DEN1.SGM              21DEN1



Document Created: 2018-10-25 11:01:30
Document Modified: 2018-10-25 11:01:30
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionDraft project plan; request for comment.
DatesSubmit comments by February 5, 2018. Comments received after this date will be considered if it is practical to do so, but the Commission is able to ensure consideration only for comments received before this date.
ContactAndrew Proffitt, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001; telephone: 301-415-1418, email: [email protected]