82 FR 61284 - Steel Reef Pipelines US LLC; Notice of Application for Section 3 Authorization and Presidential Permit

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 247 (December 27, 2017)

Page Range61284-61285
FR Document2017-27919

Federal Register, Volume 82 Issue 247 (Wednesday, December 27, 2017)
[Federal Register Volume 82, Number 247 (Wednesday, December 27, 2017)]
[Notices]
[Pages 61284-61285]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-27919]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-24-000]


Steel Reef Pipelines US LLC; Notice of Application for Section 3 
Authorization and Presidential Permit

    Take notice that on December 8, 2017, Steel Reef Pipelines US LLC 
(Steel Reef), Suite 500, 407 8th Avenue SW, Calgary, Alberta, T2P 1E5 
Canada, filed in the above referenced docket an application, pursuant 
to section 3 of the Natural Gas Act (NGA) and Subpart B of Section 153 
of the Commission's regulations, seeking authorization to site, 
construct, operate and maintain certain natural gas pipeline border 
crossing facilities to export natural gas from the United States to 
Canada (Border Crossing Facilities). The Border Crossing Facilities 
consist of a segment of 10.75-inch outside diameter pipe that extends 
from an interconnection with upstream gathering facilities for 250 feet 
to the International Boundary. The Border Crossing Facilities are a 
part of the proposed approximately 2.2-mile pipeline that further 
extends to an existing natural gas processing plant in Canada. 
Additionally, Steel Reef requests a Presidential Permit for the Border 
Crossing Facilities, all as more fully set forth in the application 
which is on file with the Commission and open to public inspection. 
This filing may be also viewed on the web at http://www.ferc.gov using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, call (202) 502-8222 or TTY, (202) 208-1659.
    Any questions regarding this application should be directed to 
Chris Anderson, Steel Reef Infrastructure Corp. Suite 500--407, 8th 
Avenue SW, Calgary, Alberta, T2P 1E5 Canada, or call (403) 263-8333 or 
email: [email protected].
    Pursuant to Section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record

[[Page 61285]]

for this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 14 copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    Comments, protests and interventions may be filed electronically 
via the internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and 
the instructions on the Commission's website under the e-Filing link.
    Comment Date: 5:00 p.m. Eastern Time on January 10, 2018.

    Dated: December 20, 2017.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2017-27919 Filed 12-26-17; 8:45 am]
 BILLING CODE 6717-01-P



                                               61284                     Federal Register / Vol. 82, No. 247 / Wednesday, December 27, 2017 / Notices

                                               FERCOnlineSupport@ferc.gov, (866)                       Electric and Gas Corporation; and (7)                 DEPARTMENT OF ENERGY
                                               208–3676 (toll free), or (202) 502–8659                 appurtenant facilities.
                                               (TTY). In lieu of electronic filing, please                                                                   Federal Energy Regulatory
                                                                                                          Goodyear Lake Hydro operates the
                                               send a paper copy to: Secretary, Federal                                                                      Commission
                                                                                                       project in a run-of-river mode. The
                                               Energy Regulatory Commission, 888                                                                             [Docket No. CP18–24–000]
                                                                                                       project experiences substantial seasonal
                                               First Street NE, Washington, DC 20426.
                                                                                                       and annual variations in generation, and
                                               The first page of any filing should                                                                           Steel Reef Pipelines US LLC; Notice of
                                               include docket number P–2788–017.                       generates an annual average of 5,985
                                                                                                                                                             Application for Section 3 Authorization
                                                  The Commission’s Rules of Practice                   megawatt-hours. Goodyear Lake Hydro
                                                                                                                                                             and Presidential Permit
                                               require all intervenors filing documents                proposes to continue to operate the
                                               with the Commission to serve a copy of                  project in run-of-river mode.                            Take notice that on December 8, 2017,
                                               that document on each person on the                        m. A copy of the application is                    Steel Reef Pipelines US LLC (Steel
                                               official service list for the project.                  available for review at the Commission                Reef), Suite 500, 407 8th Avenue SW,
                                               Further, if an intervenor files comments                                                                      Calgary, Alberta, T2P 1E5 Canada, filed
                                                                                                       in the Public Reference Room or may be
                                               or documents with the Commission                                                                              in the above referenced docket an
                                                                                                       viewed on the Commission’s web site at
                                               relating to the merits of an issue that                                                                       application, pursuant to section 3 of the
                                                                                                       http://www.ferc.gov using the eLibrary                Natural Gas Act (NGA) and Subpart B of
                                               may affect the responsibilities of a                    link. Enter the docket number excluding
                                               particular resource agency, they must                                                                         Section 153 of the Commission’s
                                                                                                       the last three digits in the docket                   regulations, seeking authorization to
                                               also serve a copy of the document on
                                                                                                       number field to address the document.                 site, construct, operate and maintain
                                               that resource agency.
                                                  k. This application is not ready for                 For assistance, contact FERC Online                   certain natural gas pipeline border
                                               environmental analysis at this time.                    Support. A copy is available for                      crossing facilities to export natural gas
                                                  l. Project Description.                              inspection and reproduction at the                    from the United States to Canada
                                                  The existing Colliersville                           address in item h above.                              (Border Crossing Facilities). The Border
                                               Hydroelectric Project consists of: (1) A                   n. You may also register online at                 Crossing Facilities consist of a segment
                                               dam that includes: A 200-foot-long, 35-                 http://www.ferc.gov/docs-filing/                      of 10.75-inch outside diameter pipe that
                                               foot-high, reinforced-concrete,                         esubscription.asp to be notified via                  extends from an interconnection with
                                               Ambursen-type dam or spillway                           email of new filings and issuances                    upstream gathering facilities for 250 feet
                                               structure 1 with a crest elevation of                                                                         to the International Boundary. The
                                                                                                       related to this or other pending projects.
                                               1,150.22 feet National Geodetic Vertical                                                                      Border Crossing Facilities are a part of
                                                                                                       For assistance, contact FERC Online
                                               Datum of 1929 (NGVD 29); a 50-foot-                                                                           the proposed approximately 2.2-mile
                                               wide concrete headgate structure                        Support.                                              pipeline that further extends to an
                                               located on the west side of the river and                  o. Scoping Process                                 existing natural gas processing plant in
                                               adjacent to the spillway, forming the                      The Commission staff intends to                    Canada. Additionally, Steel Reef
                                               closure with the west bank; and an                      prepare an Environmental Assessment                   requests a Presidential Permit for the
                                               L-shaped, 66-foot-long, concrete wall                   (EA) for the Colliersville Hydroelectric              Border Crossing Facilities, all as more
                                               with one side along the east side of the                Project in accordance with the National               fully set forth in the application which
                                               spillway and the other side parallel to                 Environmental Policy Act. The EA will                 is on file with the Commission and open
                                               the axis of the dam, extending                                                                                to public inspection. This filing may be
                                                                                                       consider both site-specific and
                                               approximately 6 to 8 feet above the crest                                                                     also viewed on the web at http://
                                                                                                       cumulative environmental impacts and
                                               of the dam; (2) a 364-acre reservoir                                                                          www.ferc.gov using the ‘‘eLibrary’’ link.
                                               (Goodyear Lake) with a gross storage                    reasonable alternatives to the proposed
                                                                                                                                                             Enter the docket number excluding the
                                               capacity of 7,800 acre-feet at a normal                 action.                                               last three digits in the docket number
                                               pool elevation of 1,150.22 feet NGVD29;                    Commission staff does not propose to               field to access the document. For
                                               (3) a 550-foot-long reinforced concrete                 conduct any on-site scoping meetings at               assistance, call (202) 502–8222 or TTY,
                                               power canal, approximately 50 feet                      this time. Instead, we are soliciting                 (202) 208–1659.
                                               wide and 6 feet deep at the head gates,                 comments, recommendations, and                           Any questions regarding this
                                               extending from a head gate structure                    information, on the Scoping Document                  application should be directed to Chris
                                               adjacent to the dam (i.e., the intake) to               1 (SD1) issued December 20, 2017.                     Anderson, Steel Reef Infrastructure
                                               the powerhouse; (4) a 103-foot-long by                                                                        Corp. Suite 500—407, 8th Avenue SW,
                                               33-foot-wide reinforced concrete                           Copies of SD1 outlining the subject
                                                                                                                                                             Calgary, Alberta, T2P 1E5 Canada, or
                                               powerhouse with trash racks with a                      areas to be addressed in the EA were
                                                                                                                                                             call (403) 263–8333 or email:
                                               clear spacing of 1.5 inches, and                        distributed to the parties on the                     chris.anderson@steelreef.ca.
                                               containing two turbines rated at 850                    Commission’s mailing list. Copies of                     Pursuant to Section 157.9 of the
                                               horsepower (HP) and 1,150 HP, and two                   SD1 may be viewed on the web at                       Commission’s rules, 18 CFR 157.9,
                                               generators having a rated capacity of                   http://www.ferc.gov using the eLibrary                within 90 days of this Notice the
                                               650 kilowatts (kW) and 850 kW,                          link. Enter the docket number excluding               Commission staff will either: complete
                                               respectively; (5) a 300-foot-long and                   the last three digits in the docket                   its environmental assessment (EA) and
                                               approximately 50- to 60-foot-wide                       number field to access the document.                  place it into the Commission’s public
                                               tailrace; (6) three, approximately 80-                  For assistance, call 1–866–208–3676 or                record (eLibrary) for this proceeding; or
                                               foot-long, 4.16-kilovolt underground                    for TTY, (202) 502–8659.                              issue a Notice of Schedule for
                                               generator leads or transmission lines                     Dated: December 20, 2017.                           Environmental Review. If a Notice of
daltland on DSKBBV9HB2PROD with NOTICES




                                               from the powerhouse to an adjacent                                                                            Schedule for Environmental Review is
                                               substation owned by the New York State                  Kimberly D. Bose,
                                                                                                                                                             issued, it will indicate, among other
                                                                                                       Secretary.                                            milestones, the anticipated date for the
                                                 1 A type of buttress dam of which the upstream        [FR Doc. 2017–27917 Filed 12–26–17; 8:45 am]          Commission staff’s issuance of the final
                                               part is a relatively thin flat slab usually made of
                                               reinforced concrete. A buttress dam consists of
                                                                                                       BILLING CODE 6717–01–P                                environmental impact statement (FEIS)
                                               watertight parts supported at intervals on the                                                                or EA for this proposal. The filing of the
                                               downstream side by a series of buttresses.                                                                    EA in the Commission’s public record


                                          VerDate Sep<11>2014   21:43 Dec 26, 2017   Jkt 244001   PO 00000   Frm 00034   Fmt 4703   Sfmt 4703   E:\FR\FM\27DEN1.SGM   27DEN1


                                                                        Federal Register / Vol. 82, No. 247 / Wednesday, December 27, 2017 / Notices                                         61285

                                               for this proceeding or the issuance of a                will not receive copies of all documents                 Applicants: Amazon Energy LLC.
                                               Notice of Schedule for Environmental                    filed by other parties or issued by the                  Description: Notice of Change in
                                               Review will serve to notify federal and                 Commission (except for the mailing of                 Status of Amazon Energy LLC.
                                               state agencies of the timing for the                    environmental documents issued by the                    Filed Date: 12/19/17.
                                               completion of all necessary reviews, and                Commission) and will not have the right                  Accession Number: 20171219–5241.
                                               the subsequent need to complete all                     to seek court review of the                              Comments Due: 5 p.m. ET 1/9/18.
                                               federal authorizations within 90 days of                Commission’s final order.                                Docket Numbers: ER17–1562–001.
                                               the date of issuance of the Commission                     Comments, protests and interventions                  Applicants: Energy Unlimited, Inc.
                                               staff’s FEIS or EA.                                     may be filed electronically via the                      Description: Compliance filing:
                                                  There are two ways to become                         internet in lieu of paper. See, 18 CFR                Energy Unlimited Inc MBR Tariff
                                               involved in the Commission’s review of                  385.2001(a)(1)(iii) and the instructions              Update to be effective 2/19/2018.
                                               this project. First, any person wishing to              on the Commission’s website under the                    Filed Date: 12/19/17.
                                               obtain legal status by becoming a party                 e-Filing link.                                           Accession Number: 20171219–5204.
                                               to the proceedings for this project                        Comment Date: 5:00 p.m. Eastern                       Comments Due: 5 p.m. ET 1/9/18.
                                               should, on or before the comment date                   Time on January 10, 2018.
                                               stated below, file with the Federal                                                                              Docket Numbers: ER17–2201–003;
                                                                                                         Dated: December 20, 2017.                           ER13–1536–015; ER10–2192–031;
                                               Energy Regulatory Commission, 888
                                               First Street NE, Washington, DC 20426,                  Kimberly D. Bose,                                     ER10–2178–031; ER10–2181–035;
                                               a motion to intervene in accordance                     Secretary.                                            ER10–2182–034.
                                               with the requirements of the                            [FR Doc. 2017–27919 Filed 12–26–17; 8:45 am]             Applicants: Exelon FitzPatrick, LLC,
                                               Commission’s Rules of Practice and                      BILLING CODE 6717–01–P                                Exelon Generation Company, LLC,
                                               Procedure (18 CFR 385.214 or 385.211)                                                                         Constellation Energy Commodities
                                               and the Regulations under the NGA (18                                                                         Group Maine, LLC, Constellation
                                               CFR 157.10). A person obtaining party                   DEPARTMENT OF ENERGY                                  NewEnergy, Inc., Nine Mile Point
                                               status will be placed on the service list                                                                     Nuclear Station, LLC, R.E. Ginna
                                               maintained by the Secretary of the                      Federal Energy Regulatory                             Nuclear Power Plant, LLC.
                                               Commission and will receive copies of                   Commission                                               Description: Notice of Non-Material
                                               all documents filed by the applicant and                                                                      Change in Status of Exelon FitzPatrick,
                                                                                                       Combined Notice of Filings #1                         LLC, et. al.
                                               by all other parties. A party must submit
                                               14 copies of filings made with the                         Take notice that the Commission                       Filed Date: 12/19/17.
                                               Commission and must mail a copy to                      received the following electric corporate                Accession Number: 20171219–5240.
                                               the applicant and to every other party in               filings:                                                 Comments Due: 5 p.m. ET 1/9/18.
                                               the proceeding. Only parties to the                        Docket Numbers: EC18–37–000.                          Docket Numbers: ER18–210–002.
                                               proceeding can ask for court review of                     Applicants: Shoreham Solar                            Applicants: Emera Maine.
                                               Commission orders in the proceeding.                    Commons LLC.                                             Description: Tariff Amendment:
                                                  However, a person does not have to                      Description: Application for Approval              Request to Lift Stay and Answer Protest
                                               intervene in order to have comments                     of the Disposition of Jurisdictional                  ER18–210–000 to be effective 1/1/2018.
                                               considered. The second way to                           Facilities under Section 203 of the                      Filed Date: 12/19/17.
                                               participate is by filing with the                       Federal Power Act of Shoreham Solar                      Accession Number: 20171219–5195.
                                               Secretary of the Commission, as soon as                 Commons LLC.                                             Comments Due: 5 p.m. ET 1/9/18.
                                               possible, an original and two copies of                    Filed Date: 12/19/17.                                 Docket Numbers: ER18–215–001.
                                               comments in support of or in opposition                    Accession Number: 20171219–5217.                      Applicants: Interstate Power and
                                               to this project. The Commission will                       Comments Due: 5 p.m. ET 1/9/18.                    Light Company.
                                               consider these comments in                                 Take notice that the Commission                       Description: Supplement to December
                                               determining the appropriate action to be                received the following electric rate                  18, 2017 Interstate Power and Light
                                               taken, but the filing of a comment alone                filings:                                              Company tariff filing (Certificate of
                                               will not serve to make the filer a party                                                                      Service).
                                               to the proceeding. The Commission’s                        Docket Numbers: ER10–1350–006.
                                                                                                          Applicants: Entergy Services, Inc.                    Filed Date: 12/19/17.
                                               rules require that persons filing                                                                                Accession Number: 20171219–5230.
                                               comments in opposition to the project                      Description: Entergy Services, Inc., as
                                                                                                       agent for the Entergy Operating                          Comments Due: 5 p.m. ET 12/26/17.
                                               provide copies of their protests only to
                                               the party or parties directly involved in               Companies submits filing per 35.19a(b):                  Docket Numbers: ER18–455–001.
                                               the protest.                                            Refund Report to be effective N/A.                       Applicants: ISO New England Inc.
                                                  Persons who wish to comment only                        Filed Date: 12/18/17.                                 Description: Tariff Amendment: Errata
                                               on the environmental review of this                        Accession Number: 20171218–5269.                   to Filing Re: CSO Transfer
                                               project should submit an original and                      Comments Due: 5 p.m. ET 1/8/18.                    Improvements—ER18–455–000 to be
                                               two copies of their comments to the                        Docket Numbers: ER13–136–004;                      effective 3/1/2018.
                                               Secretary of the Commission.                            ER13–135–004; ER13–137–004; ER13–                        Filed Date: 12/20/17.
                                               Environmental commenters will be                        138–004; ER13–141–004; ER13–142–                         Accession Number: 20171220–5047.
                                               placed on the Commission’s                              004.                                                     Comments Due: 5 p.m. ET 1/10/18.
                                               environmental mailing list, will receive                   Applicants: Georgia-Pacific Brewton                   Docket Numbers: ER18–475–000.
                                               copies of the environmental documents,                  LLC.                                                     Applicants: The Potomac Edison
daltland on DSKBBV9HB2PROD with NOTICES




                                               and will be notified of meetings                           Description: Triennial Market-Power                Company, Monongahela Power
                                               associated with the Commission’s                        Analyses of the Georgia-Pacific Entities              Company, Virginia Electric and Power
                                               environmental review process.                           in the Southeast Region.                              Company, PJM Interconnection, L.L.C.
                                               Environmental commenters will not be                       Filed Date: 12/19/17.                                 Description: § 205(d) Rate Filing:
                                               required to serve copies of filed                          Accession Number: 20171219–5242.                   VEPCO, Potomac and Monongahela
                                               documents on all other parties.                            Comments Due: 5 p.m. ET 2/20/18.                   submit Interconnection Agreement SA
                                               However, the non-party commenters                          Docket Numbers: ER15–1905–007.                     No. 4874 to be effective 2/20/2018.


                                          VerDate Sep<11>2014   21:43 Dec 26, 2017   Jkt 244001   PO 00000   Frm 00035   Fmt 4703   Sfmt 4703   E:\FR\FM\27DEN1.SGM   27DEN1



Document Created: 2017-12-27 02:23:54
Document Modified: 2017-12-27 02:23:54
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on January 10, 2018.
FR Citation82 FR 61284 