82_FR_8757 82 FR 8739 - Order on Simultaneous Transmission Import Limit Values for the Southwest Region and Providing Direction on Submitting Studies

82 FR 8739 - Order on Simultaneous Transmission Import Limit Values for the Southwest Region and Providing Direction on Submitting Studies

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 18 (January 30, 2017)

Page Range8739-8741
FR Document2017-01939

Federal Register, Volume 82 Issue 18 (Monday, January 30, 2017)
[Federal Register Volume 82, Number 18 (Monday, January 30, 2017)]
[Notices]
[Pages 8739-8741]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-01939]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Order on Simultaneous Transmission Import Limit Values for the 
Southwest Region and Providing Direction on Submitting Studies

Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, 
and Colette D. Honorable.

------------------------------------------------------------------------
                                                      Docket Nos.
------------------------------------------------------------------------
Public Service Company of New Mexico.........  ER10-2302-006
Tucson Electric Power Company................  ER10-2564-006
UNS Electric, Inc............................  ER10-2600-006
UniSource Energy Development Company.........  ER10-2289-006
El Paso Electric Company.....................  ER10-2721-006
Arizona Public Service Company...............  ER10-2437-003
Public Service Company of Colorado...........  ER10-1818-012
Northern States Power Company, a Minnesota     ER10-1819-014
 corporation.
Northern States Power Company, a Wisconsin     ER10-1820-017
 corporation.
Southwestern Public Service Company..........  ER10-1817-013
------------------------------------------------------------------------

    1. In December 2015 and January 2016, Public Service Company of New 
Mexico; Tucson Electric Power Company (Tucson Electric), UNS Electric, 
Inc., and UniSource Energy Development Company; El Paso Electric

[[Page 8740]]

Company; Arizona Public Service Company (Arizona Public Service); 
Public Service Company of Colorado, Northern States Power Company, a 
Minnesota corporation, Northern States Power Company, a Wisconsin 
corporation and Southwestern Public Service Company (collectively, 
Transmission Owners) submitted updated market power analyses for the 
Southwest region in accordance with the regional reporting schedule.\1\ 
The Transmission Owners included Simultaneous Transmission Import Limit 
(SIL) values for the December 2013-November 2014 study period for 
balancing authority areas in the Southwest region.\2\
---------------------------------------------------------------------------

    \1\ See Refinements to Policies and Procedures for Market-Based 
Rates for Wholesale Sales of Electric Energy, Capacity and Ancillary 
Services by Public Utilities, Order No. 816, FERC Stats. & Regs. ] 
31,374, at P 353 (2015), order on reh'g, Order No. 816-A, FERC 
Stats. & Regs. ] 31,382 (2016). See also Market-Based Rates for 
Wholesale Sales of Electric Energy, Capacity and Ancillary Services 
by Public Utilities, Order No. 697, FERC Stats. & Regs. ] 31,252, at 
PP 882-893, clarified, 121 FERC ] 61,260 (2007), order on reh'g, 
Order No. 697-A, FERC Stats. & Regs. ] 31,268, clarified, 124 FERC ] 
61,055, order on reh'g, Order No. 697-B, FERC Stats. & Regs. ] 
31,285 (2008), order on reh'g, Order No. 697-C, FERC Stats. & Regs. 
] 31,291 (2009), order on reh'g, Order No. 697-D, FERC Stats. & 
Regs. ] 31,305 (2010), aff'd sub nom. Montana Consumer Counsel v. 
FERC, 659 F.3d 910 (9th Cir. 2011), cert. denied, 133 S. Ct. 26 
(2012).
    \2\ We note that Public Service Company of Colorado, Northern 
States Power Company, a Minnesota corporation, Northern States Power 
Company, a Wisconsin corporation, and Southwestern Public Service 
Company are not in the Southwest region and therefore their market 
power analyses were not due in December 2015, when transmission 
owners in the Southwest region must file their analyses. However, 
these utilities submitted an updated market power analysis in 
January 2016 to help coordinate review of the SILs. Additionally, we 
note that subsequent to December 2015 and January 2016, some of the 
Transmission Owners amended their filings to reflect updated and 
corrected information with respect to the SIL studies and values.
---------------------------------------------------------------------------

    2. In this order, the Commission accepts the SIL values identified 
in Appendix A (Commission-accepted SIL values).\3\ SIL studies are used 
as a basis for calculating import capability to serve balancing 
authority area load when performing market power analyses. SIL values 
quantify the simultaneous transmission import capability into a market 
or balancing authority area from its aggregated first-tier area. The 
SIL values accepted herein are based on SIL studies submitted by the 
Transmission Owners with their updated market power analyses. As 
discussed below, the Commission-accepted SIL values identified in 
Appendix A will be used by the Commission to analyze updated market 
power analyses for the Southwest region. The updated market power 
analyses for the Transmission Owners, including any responsive 
pleadings, will be addressed in separate orders in the relevant 
dockets.\4\
---------------------------------------------------------------------------

    \3\ The Commission issued an order accepting SIL values for the 
Tucson Electric Power Company balancing authority area in Tucson 
Electric Power Co., 156 FERC ] 61,228 (2016).
    \4\ We note that other transmission owners in the Southwest 
region also submitted updated market power analyses. The updated 
market power analyses for those transmission owners have been or 
will be addressed in separate orders in the relevant dockets.
---------------------------------------------------------------------------

    3. Additionally in this order, the Commission provides further 
direction and clarification on the performance and reporting of SIL 
studies.

I. Background

    4. In Order No. 697, the Commission adopted a staggered filing 
approach for filing updated market power analyses. The Commission 
recognized that the transmission-owning utilities have the information 
necessary to perform SIL studies and therefore determined that 
transmission-owning utilities would be required to file their updated 
market power analyses in advance of other entities in each region.\5\
---------------------------------------------------------------------------

    \5\ Order No. 697, FERC Stats. & Regs. ] 31,252 at P 889.
---------------------------------------------------------------------------

    5. The Transmission Owners provided SIL studies for their 
respective balancing authority areas and, in most cases, their 
respective first-tier balancing authority areas, including balancing 
authority areas that are not operated by public utilities as defined 
under Part II of the Federal Power Act.\6\ Specifically, SIL studies 
were submitted for the following first-tier balancing authority areas: 
Salt River Project; Los Angeles Department of Water and Power; Western 
Area Power Administration-Lower Colorado (WALC); Western Area Power 
Administration-Colorado Missouri (WACM); and the Imperial Irrigation 
District (IID). The Transmission Owners coordinated on the preparation 
of their SIL studies and shared with each other SIL values for their 
respective balancing authority areas.
---------------------------------------------------------------------------

    \6\ 16 U.S.C. 824 (2012).
---------------------------------------------------------------------------

II. Discussion

    6. We begin by commending the Transmission Owners for coordinating 
on the preparation of their SIL studies and sharing the SIL values for 
their respective home balancing authority areas with each other. Such a 
coordinated approach leads to more accurate and consistent SIL study 
results. We have selected, from among the SIL values submitted, the 
Commission-accepted SIL values that we will use in assessing 
transmission import capability for purposes of measuring market power 
within the Southwest region.
    7. The SIL studies prepared by the Transmission Owners generally 
were done correctly and in a manner consistent with prior Commission 
direction.\7\ However, our review of the SIL studies and acceptance of 
the SIL values was hindered and delayed because of various modeling 
issues and incomplete or ambiguous reporting of results. Therefore, we 
take this opportunity to address some of these issues and offer 
guidance so that future filers have a better understanding of how the 
Commission expects such studies to be performed and reported.
---------------------------------------------------------------------------

    \7\ See, e.g., Puget Sound Energy, Inc., 135 FERC ] 61,254, 
Appendix B (2011).
---------------------------------------------------------------------------

    8. The contingencies used in SIL studies are vital to determining 
the limiting element(s) and, subsequently, the final SIL values. Filers 
should study contingencies that are ``historically used and identified 
in the seller's [available transfer capability (ATC)] methodology and 
[Open Access Same-Time Information System (OASIS)] practices 
documentation.'' \8\ This requirement applies for both the study area 
and the first-tier areas. As balancing authorities are already expected 
to communicate with each other on system conditions, the Commission 
believes that this is a reasonable and comprehensive approach.
---------------------------------------------------------------------------

    \8\ Id., Appendix B.
---------------------------------------------------------------------------

    9. Each filer should provide documentation to support that the 
contingency lists provided are consistent with the balancing authority 
area's OASIS practices. The contingency lists used by each filer must 
be valid, representative of the study area and first-tier OASIS 
practices, and must solve in powerflow simulations. Valid contingencies 
take into account the realistic conditions and operating procedures for 
the filer's system and the first-tier areas. For example, parallel 
lines are typically designed and operated such that the loss of one 
line would not overload the other line(s). If a contingency appears to 
overload other parallel line(s), the filer must explain this in its 
contingency results report. Additionally, methods for modeling the 
transmission system may include breaking elements up into segments. The 
contingency of such an element should be represented by these segments.
    10. Every contingency checked must solve in each powerflow case in 
which it is used. If a contingency does not solve when run in the 
powerflow simulation, confirming that it would not cause an overload 
somewhere within

[[Page 8741]]

the system is difficult. This potential overload could be a limiting 
element that would affect the final SIL values.
    11. The Commission notes that inaccurate normal and emergency line 
ratings in the powerflow models can result in erroneous calculated SIL 
values. As such, filers should review the line ratings of their study 
area and the first-tier areas to ensure that they are accurate. In 
order to aid in verifying line overloads, filers must submit facility 
rating documents for themselves and any study area for which they are 
performing a SIL analysis. Historically accurate line ratings should 
aid in confirming the validity of line overloads identified in the SIL 
study.
    12. Generating units that are fully committed under long-term power 
purchase agreements (PPAs) should not be scaled up or down, regardless 
of where they are operating in the model. Partially committed units 
should only be scaled above the amount of their commitment. Solar and 
wind units should not be scaled either up or down. This generation 
generally is not dispatchable and typically is fully committed under 
long-term PPAs. If the study assumes that certain solar or wind 
generation units are dispatchable, historical evidence must be 
provided. Filers should provide a list of all partially and fully 
committed generation units in the study area and first-tier areas.
    13. As stated in Order No. 697, filers may use historical capacity 
factors for certain energy-limited resources, such as hydroelectric and 
wind capacity.\9\ The historical data used to perform the sensitivities 
and determine the capacity factors should be consistent in both the SIL 
and economic studies submitted by the filer.
---------------------------------------------------------------------------

    \9\ Order No. 697, FERC Stats. & Regs. ] 31,252 at P 344.
---------------------------------------------------------------------------

    14. Changes in SIL values from the previous study period should be 
explained in the filing. Significant changes that affect the study area 
should be identified, for example, major generation capacity additions 
or retirements, the addition of a new high-voltage transmission line or 
other topology changes, modified line ratings, and changes in operating 
procedures or study methodology. Clearly explaining and identifying 
significant changes in the SIL study results that occur between filings 
will prevent delays in the analysis of filings and reduce the need for 
Commission staff to request filers to provide additional information. 
Documentation of any changes should extend back approximately five 
years from the study period utilized in the filing to show how the 
study area's topology has evolved over time.
    15. The Commission will use the Commission-accepted SIL values 
identified in Appendix A when reviewing the currently pending updated 
market power analyses submitted by the Transmission Owners as well as 
the updated market power analyses filed by the non-transmission owning 
filers in the Southwest region for this study period. Future filers 
submitting screens for the areas and study period identified in 
Appendix A are encouraged to use these Commission-accepted SIL values. 
In the alternative, such filers may propose different SIL values 
provided that their SIL studies comply with Commission directives and 
they explain why the Commission should consider a different SIL value 
for a particular balancing authority area rather than the Commission-
accepted SIL values provided in Appendix A. In the event that the 
results \10\ for one or more of a particular seller's screens differ if 
the seller-supplied SIL value is used instead of the Commission-
accepted SIL value, the order on that particular filing will examine 
the seller-supplied SIL study and address whether the seller-supplied 
SIL value is acceptable. However, when the overall results of the 
screens would be unchanged, i.e., the seller would pass using either 
set of SIL values or fail using either set of SIL values, the order 
would be based on the Commission-accepted SIL values found in Appendix 
A and would not address the seller-supplied SIL values.
---------------------------------------------------------------------------

    \10\ Results refer to the results of the market share and/or 
pivotal supplier screens. For example, if a seller fails the market 
share screen for a particular season in a particular market using 
either SIL value, we would consider the result unchanged. Similarly, 
if the seller passes the screen using either value, the result is 
also unchanged.
---------------------------------------------------------------------------

The Commission Orders

    (A) The specific Commission-accepted SIL values identified in 
Appendix A to this order are hereby adopted for purposes of analyzing 
updated market power analyses for the Southwest region, as discussed in 
the body of this order.
    (B) The Secretary is hereby directed to publish a copy of this 
order in the Federal Register.

    By the Commission.

    Issued: January 24, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-01939 Filed 1-27-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                          Federal Register / Vol. 82, No. 18 / Monday, January 30, 2017 / Notices                                                                                8739

                                                     Applicants: Florida Gas Transmission                                      Filed Date: 12/27/16.                                                  February 17, 2017 as the EIS issuance
                                                  Company, LLC.                                                                Accession Number: 20161227–5036.                                       date. Due to additional environmental
                                                     Description: Florida Gas Transmission                                     Comments Due: 5 p.m. ET 1/9/17.                                        information filed by PennEast and
                                                  Company, LLC submits tariff filing per                                       The filings are accessible in the                                      certain state agencies since issuance of
                                                  154.203: Annual Accounting Report                                         Commission’s eLibrary system by                                           the November 8, 2016, Scheduling
                                                  filing on 12/28/16 to be effective N/A.                                   clicking on the links or querying the                                     Notice, the Commission staff requires
                                                     Filed Date: 12/28/16.                                                  docket number.                                                            more time to analyze all the
                                                     Accession Number: 20161228–5005.                                          Any person desiring to intervene or                                    environmental data and prepare the
                                                     Comments Due: 5 p.m. ET 1/9/17.                                        protest in any of the above proceedings                                   final EIS. Commission staff has therefore
                                                     Docket Numbers: RP17–293–000.                                          must file in accordance with Rules 211                                    revised the schedule for issuance of the
                                                     Applicants: Iroquois Gas                                               and 214 of the Commission’s                                               final EIS.
                                                  Transmission System, L.P.                                                 Regulations (18 CFR 385.211 and
                                                     Description: Iroquois Gas                                              385.214) on or before 5:00 p.m. Eastern                                   Schedule for Environmental Review
                                                  Transmission System, L.P. submits tariff                                  time on the specified comment date.                                       Issuance of Notice of Availability of the
                                                  filing per 154.204: 12/28/16 Negotiated                                   Protests may be considered, but                                              final EIS: April 7, 2017
                                                  Rates—Mieco, Inc. (HUB) 7080–89 to be                                     intervention is necessary to become a
                                                  effective 1/1/2017.                                                       party to the proceeding.                                                  90-day Federal Authorization Decision
                                                     Filed Date: 12/28/16.                                                     eFiling is encouraged. More detailed                                      Deadline: July 6, 2017
                                                     Accession Number: 20161228–5030.                                       information relating to filing                                              If a schedule change becomes
                                                     Comments Due: 5 p.m. ET 1/9/17.                                        requirements, interventions, protests,                                    necessary, an additional notice will be
                                                     Docket Numbers: RP17–294–000.                                          service, and qualifying facilities filings                                provided so that the relevant agencies
                                                     Applicants: Iroquois Gas                                               can be found at: http://www.ferc.gov/                                     are kept informed of the project’s
                                                  Transmission System, L.P.                                                 docs-filing/efiling/filing-req.pdf. For                                   progress.
                                                     Description: Iroquois Gas                                              other information, call (866) 208–3676
                                                  Transmission System, L.P. submits tariff                                  (toll free). For TTY, call (202) 502–8659.                                Additional Information
                                                  filing per 154.204: 12/28/16 Negotiated                                     Dated: December 28, 2016.                                                  In order to receive notification of the
                                                  Rates—Twin Eagle Resource                                                 Nathaniel J. Davis, Sr.,                                                  issuance of the EIS and to keep track of
                                                  Management, LLC (RTS) 7300–01 to be                                       Deputy Secretary                                                          all formal issuances and submittals in
                                                  effective 1/1/2017.                                                       [FR Doc. 2017–01921 Filed 1–27–17; 8:45 am]                               specific dockets, the Commission offers
                                                     Filed Date: 12/28/16.                                                                                                                            a free service called eSubscription
                                                                                                                            BILLING CODE 6717–01–P
                                                     Accession Number: 20161228–5046.                                                                                                                 (https://www.ferc.gov/docs-filing/
                                                     Comments Due: 5 p.m. ET 1/9/17.                                                                                                                  esubscription.asp).
                                                     Any person desiring to intervene or                                    DEPARTMENT OF ENERGY                                                        Dated: January 23, 2017.
                                                  protest in any of the above proceedings
                                                  must file in accordance with Rules 211                                    Federal Energy Regulatory                                                 Kimberly D. Bose,
                                                  and 214 of the Commission’s                                               Commission                                                                Secretary.
                                                  Regulations (18 CFR 385.211 and                                                                                                                     [FR Doc. 2017–01910 Filed 1–27–17; 8:45 am]
                                                                                                                            [Docket No. CP15–558–000]
                                                  385.214) on or before 5:00 p.m. Eastern                                                                                                             BILLING CODE 6717–01–P
                                                  time on the specified date(s). Protests                                   PennEast Pipeline Company, LLC;
                                                  may be considered, but intervention is                                    Notice of Revised Schedule for
                                                  necessary to become a party to the                                                                                                                  DEPARTMENT OF ENERGY
                                                                                                                            Environmental Review of the Penneast
                                                  proceeding.                                                               Pipeline Project                                                          Federal Energy Regulatory
                                                  Filings in Existing Proceedings                                              This notice identifies the Federal                                     Commission
                                                    Docket Numbers: RP17–49–001.                                            Energy Regulatory Commission (FERC
                                                    Applicants: Destin Pipeline Company,                                    or Commission) staff’s revised schedule                                   Order on Simultaneous Transmission
                                                  L.L.C.                                                                    for the completion of the final                                           Import Limit Values for the Southwest
                                                    Description: Destin Pipeline                                            environmental impact statement (EIS)                                      Region and Providing Direction on
                                                  Company, L.L.C. submits tariff filing per                                 for PennEast Pipeline Company, LLC’s                                      Submitting Studies
                                                  154.203: Compliance Filing in Response                                    (PennEast) PennEast Pipeline Project.                                     Before Commissioners: Norman C. Bay,
                                                  to Tariff Changes to Audit to be effective                                The previous revised notice of schedule,                                    Chairman; Cheryl A. LaFleur, and Colette
                                                  12/1/2016.                                                                issued on November 8, 2016, identified                                      D. Honorable.

                                                                                                                                                                                                                                   Docket Nos.

                                                  Public Service Company of New Mexico ...............................................................................................................                     ER10–2302–006
                                                  Tucson Electric Power Company ...........................................................................................................................                ER10–2564–006
                                                  UNS Electric, Inc ....................................................................................................................................................   ER10–2600–006
                                                  UniSource Energy Development Company ............................................................................................................                        ER10–2289–006
                                                  El Paso Electric Company ......................................................................................................................................          ER10–2721–006
                                                  Arizona Public Service Company ...........................................................................................................................               ER10–2437–003
                                                  Public Service Company of Colorado ....................................................................................................................                  ER10–1818–012
mstockstill on DSK3G9T082PROD with NOTICES




                                                  Northern States Power Company, a Minnesota corporation .................................................................................                                 ER10–1819–014
                                                  Northern States Power Company, a Wisconsin corporation ..................................................................................                                ER10–1820–017
                                                  Southwestern Public Service Company .................................................................................................................                    ER10–1817–013



                                                    1. In December 2015 and January                                         Mexico; Tucson Electric Power                                             Electric, Inc., and UniSource Energy
                                                  2016, Public Service Company of New                                       Company (Tucson Electric), UNS                                            Development Company; El Paso Electric



                                             VerDate Sep<11>2014         16:27 Jan 27, 2017        Jkt 241001      PO 00000       Frm 00021        Fmt 4703      Sfmt 4703      E:\FR\FM\30JAN1.SGM             30JAN1


                                                  8740                          Federal Register / Vol. 82, No. 18 / Monday, January 30, 2017 / Notices

                                                  Company; Arizona Public Service                         market power analyses for the                          measuring market power within the
                                                  Company (Arizona Public Service);                       Southwest region. The updated market                   Southwest region.
                                                  Public Service Company of Colorado,                     power analyses for the Transmission                       7. The SIL studies prepared by the
                                                  Northern States Power Company, a                        Owners, including any responsive                       Transmission Owners generally were
                                                  Minnesota corporation, Northern States                  pleadings, will be addressed in separate               done correctly and in a manner
                                                  Power Company, a Wisconsin                              orders in the relevant dockets.4                       consistent with prior Commission
                                                  corporation and Southwestern Public                       3. Additionally in this order, the                   direction.7 However, our review of the
                                                  Service Company (collectively,                          Commission provides further direction                  SIL studies and acceptance of the SIL
                                                  Transmission Owners) submitted                          and clarification on the performance                   values was hindered and delayed
                                                  updated market power analyses for the                   and reporting of SIL studies.                          because of various modeling issues and
                                                  Southwest region in accordance with                                                                            incomplete or ambiguous reporting of
                                                  the regional reporting schedule.1 The                   I. Background                                          results. Therefore, we take this
                                                  Transmission Owners included                               4. In Order No. 697, the Commission                 opportunity to address some of these
                                                  Simultaneous Transmission Import                        adopted a staggered filing approach for                issues and offer guidance so that future
                                                  Limit (SIL) values for the December                     filing updated market power analyses.                  filers have a better understanding of
                                                  2013–November 2014 study period for                     The Commission recognized that the                     how the Commission expects such
                                                  balancing authority areas in the                        transmission-owning utilities have the                 studies to be performed and reported.
                                                  Southwest region.2                                      information necessary to perform SIL                      8. The contingencies used in SIL
                                                     2. In this order, the Commission                     studies and therefore determined that                  studies are vital to determining the
                                                  accepts the SIL values identified in                    transmission-owning utilities would be                 limiting element(s) and, subsequently,
                                                  Appendix A (Commission-accepted SIL                     required to file their updated market                  the final SIL values. Filers should study
                                                  values).3 SIL studies are used as a basis               power analyses in advance of other                     contingencies that are ‘‘historically used
                                                  for calculating import capability to serve              entities in each region.5                              and identified in the seller’s [available
                                                  balancing authority area load when                         5. The Transmission Owners provided                 transfer capability (ATC)] methodology
                                                  performing market power analyses. SIL                   SIL studies for their respective                       and [Open Access Same-Time
                                                  values quantify the simultaneous                        balancing authority areas and, in most                 Information System (OASIS)] practices
                                                  transmission import capability into a                   cases, their respective first-tier                     documentation.’’ 8 This requirement
                                                  market or balancing authority area from                 balancing authority areas, including                   applies for both the study area and the
                                                  its aggregated first-tier area. The SIL                 balancing authority areas that are not                 first-tier areas. As balancing authorities
                                                  values accepted herein are based on SIL                 operated by public utilities as defined                are already expected to communicate
                                                  studies submitted by the Transmission                   under Part II of the Federal Power Act.6               with each other on system conditions,
                                                  Owners with their updated market                        Specifically, SIL studies were submitted               the Commission believes that this is a
                                                  power analyses. As discussed below, the                 for the following first-tier balancing                 reasonable and comprehensive
                                                  Commission-accepted SIL values                          authority areas: Salt River Project; Los               approach.
                                                  identified in Appendix A will be used                   Angeles Department of Water and                           9. Each filer should provide
                                                  by the Commission to analyze updated                    Power; Western Area Power                              documentation to support that the
                                                                                                          Administration-Lower Colorado                          contingency lists provided are
                                                    1 See Refinements to Policies and Procedures for
                                                                                                          (WALC); Western Area Power                             consistent with the balancing authority
                                                  Market-Based Rates for Wholesale Sales of Electric                                                             area’s OASIS practices. The contingency
                                                  Energy, Capacity and Ancillary Services by Public
                                                                                                          Administration-Colorado Missouri
                                                  Utilities, Order No. 816, FERC Stats. & Regs.           (WACM); and the Imperial Irrigation                    lists used by each filer must be valid,
                                                  ¶ 31,374, at P 353 (2015), order on reh’g, Order No.    District (IID). The Transmission Owners                representative of the study area and
                                                  816–A, FERC Stats. & Regs. ¶ 31,382 (2016). See         coordinated on the preparation of their                first-tier OASIS practices, and must
                                                  also Market-Based Rates for Wholesale Sales of                                                                 solve in powerflow simulations. Valid
                                                  Electric Energy, Capacity and Ancillary Services by
                                                                                                          SIL studies and shared with each other
                                                  Public Utilities, Order No. 697, FERC Stats. & Regs.    SIL values for their respective balancing              contingencies take into account the
                                                  ¶ 31,252, at PP 882–893, clarified, 121 FERC            authority areas.                                       realistic conditions and operating
                                                  ¶ 61,260 (2007), order on reh’g, Order No. 697–A,                                                              procedures for the filer’s system and the
                                                  FERC Stats. & Regs. ¶ 31,268, clarified, 124 FERC       II. Discussion                                         first-tier areas. For example, parallel
                                                  ¶ 61,055, order on reh’g, Order No. 697–B, FERC
                                                  Stats. & Regs. ¶ 31,285 (2008), order on reh’g, Order     6. We begin by commending the                        lines are typically designed and
                                                  No. 697–C, FERC Stats. & Regs. ¶ 31,291 (2009),         Transmission Owners for coordinating                   operated such that the loss of one line
                                                  order on reh’g, Order No. 697–D, FERC Stats. &          on the preparation of their SIL studies                would not overload the other line(s). If
                                                  Regs. ¶ 31,305 (2010), aff’d sub nom. Montana           and sharing the SIL values for their                   a contingency appears to overload other
                                                  Consumer Counsel v. FERC, 659 F.3d 910 (9th Cir.
                                                  2011), cert. denied, 133 S. Ct. 26 (2012).              respective home balancing authority                    parallel line(s), the filer must explain
                                                    2 We note that Public Service Company of              areas with each other. Such a                          this in its contingency results report.
                                                  Colorado, Northern States Power Company, a              coordinated approach leads to more                     Additionally, methods for modeling the
                                                  Minnesota corporation, Northern States Power            accurate and consistent SIL study                      transmission system may include
                                                  Company, a Wisconsin corporation, and                                                                          breaking elements up into segments.
                                                  Southwestern Public Service Company are not in
                                                                                                          results. We have selected, from among
                                                  the Southwest region and therefore their market         the SIL values submitted, the                          The contingency of such an element
                                                  power analyses were not due in December 2015,           Commission-accepted SIL values that                    should be represented by these
                                                  when transmission owners in the Southwest region        we will use in assessing transmission                  segments.
                                                  must file their analyses. However, these utilities                                                                10. Every contingency checked must
                                                  submitted an updated market power analysis in
                                                                                                          import capability for purposes of
                                                  January 2016 to help coordinate review of the SILs.                                                            solve in each powerflow case in which
mstockstill on DSK3G9T082PROD with NOTICES




                                                  Additionally, we note that subsequent to December         4 We note that other transmission owners in the      it is used. If a contingency does not
                                                  2015 and January 2016, some of the Transmission         Southwest region also submitted updated market         solve when run in the powerflow
                                                  Owners amended their filings to reflect updated         power analyses. The updated market power
                                                                                                          analyses for those transmission owners have been
                                                                                                                                                                 simulation, confirming that it would not
                                                  and corrected information with respect to the SIL
                                                  studies and values.                                     or will be addressed in separate orders in the         cause an overload somewhere within
                                                    3 The Commission issued an order accepting SIL        relevant dockets.
                                                                                                            5 Order No. 697, FERC Stats. & Regs. ¶ 31,252 at       7 See, e.g., Puget Sound Energy, Inc., 135 FERC
                                                  values for the Tucson Electric Power Company
                                                  balancing authority area in Tucson Electric Power       P 889.                                                 ¶ 61,254, Appendix B (2011).
                                                  Co., 156 FERC ¶ 61,228 (2016).                            6 16 U.S.C. 824 (2012).                                8 Id., Appendix B.




                                             VerDate Sep<11>2014   16:27 Jan 27, 2017   Jkt 241001   PO 00000   Frm 00022   Fmt 4703   Sfmt 4703   E:\FR\FM\30JAN1.SGM   30JAN1


                                                                                Federal Register / Vol. 82, No. 18 / Monday, January 30, 2017 / Notices                                                8741

                                                  the system is difficult. This potential                 filing to show how the study area’s                       DEPARTMENT OF ENERGY
                                                  overload could be a limiting element                    topology has evolved over time.
                                                  that would affect the final SIL values.                    15. The Commission will use the                        Federal Energy Regulatory
                                                     11. The Commission notes that                        Commission-accepted SIL values                            Commission
                                                  inaccurate normal and emergency line
                                                                                                          identified in Appendix A when                             Combined Notice of Filings #1
                                                  ratings in the powerflow models can
                                                                                                          reviewing the currently pending
                                                  result in erroneous calculated SIL                                                                                   Take notice that the Commission
                                                                                                          updated market power analyses
                                                  values. As such, filers should review the                                                                         received the following electric corporate
                                                                                                          submitted by the Transmission Owners
                                                  line ratings of their study area and the                                                                          filings:
                                                                                                          as well as the updated market power
                                                  first-tier areas to ensure that they are
                                                  accurate. In order to aid in verifying line             analyses filed by the non-transmission                       Docket Numbers: EC17–64–000.
                                                  overloads, filers must submit facility                  owning filers in the Southwest region                        Applicants: Orange and Rockland
                                                  rating documents for themselves and                     for this study period. Future filers                      Utilities, Inc.
                                                  any study area for which they are                       submitting screens for the areas and                         Description: Application of Orange
                                                  performing a SIL analysis. Historically                 study period identified in Appendix A                     and Rockland Utilities, Inc. for order
                                                  accurate line ratings should aid in                     are encouraged to use these                               pursuant to Section 203 of the Federal
                                                  confirming the validity of line overloads               Commission-accepted SIL values. In the                    Power Act authorizing the purchase or
                                                  identified in the SIL study.                            alternative, such filers may propose                      acquisition by the company of short-
                                                     12. Generating units that are fully                  different SIL values provided that their                  term debt of its affiliate.
                                                  committed under long-term power                         SIL studies comply with Commission                           Filed Date: 1/19/17.
                                                  purchase agreements (PPAs) should not                   directives and they explain why the                          Accession Number: 20170119–5212.
                                                  be scaled up or down, regardless of                     Commission should consider a different                       Comments Due: 5 p.m. ET 2/9/17.
                                                  where they are operating in the model.                  SIL value for a particular balancing                         Take notice that the Commission
                                                  Partially committed units should only                   authority area rather than the                            received the following electric rate
                                                  be scaled above the amount of their                     Commission-accepted SIL values                            filings:
                                                  commitment. Solar and wind units                        provided in Appendix A. In the event                         Docket Numbers: ER10–2835–006.
                                                  should not be scaled either up or down.                 that the results 10 for one or more of a                     Applicants: Google Energy LLC.
                                                  This generation generally is not                        particular seller’s screens differ if the                    Description: Notice of Change in
                                                  dispatchable and typically is fully                     seller-supplied SIL value is used instead                 Status by Google Energy LLC.
                                                  committed under long-term PPAs. If the                  of the Commission-accepted SIL value,                        Filed Date: 1/19/17.
                                                  study assumes that certain solar or wind                the order on that particular filing will                     Accession Number: 20170119–5199.
                                                  generation units are dispatchable,                      examine the seller-supplied SIL study                        Comments Due: 5 p.m. ET 2/9/17.
                                                  historical evidence must be provided.                   and address whether the seller-supplied
                                                                                                                                                                       Docket Numbers: ER10–2961–010;
                                                  Filers should provide a list of all                     SIL value is acceptable. However, when
                                                                                                                                                                    ER10–2950–009; ER10–3193–010; ER11–
                                                  partially and fully committed generation                the overall results of the screens would
                                                                                                                                                                    2042–011; ER11–2041–011; ER10–2924–
                                                  units in the study area and first-tier                  be unchanged, i.e., the seller would pass
                                                                                                                                                                    010; ER10–2480–009; ER10–2718–026;
                                                  areas.                                                  using either set of SIL values or fail
                                                                                                                                                                    ER10–2719–025; ER10–2959–010; ER10–
                                                     13. As stated in Order No. 697, filers               using either set of SIL values, the order
                                                                                                                                                                    2934–009; ER13–821–011; ER14–2500–
                                                  may use historical capacity factors for                 would be based on the Commission-
                                                                                                                                                                    005; ER14–2498–005; ER16–2462–003.
                                                  certain energy-limited resources, such                  accepted SIL values found in Appendix
                                                                                                                                                                       Applicants: Edgecombe Genco, LLC,
                                                  as hydroelectric and wind capacity.9                    A and would not address the seller-
                                                                                                                                                                    Spruance Genco, LLC, Brooklyn Navy
                                                  The historical data used to perform the                 supplied SIL values.
                                                                                                                                                                    Yard Cogeneration Partners, L.P.,
                                                  sensitivities and determine the capacity
                                                                                                          The Commission Orders                                     Seneca Energy II, LLC, Innovative
                                                  factors should be consistent in both the
                                                                                                                                                                    Energy Systems, LLC, Kleen Energy
                                                  SIL and economic studies submitted by                     (A) The specific Commission-                            Systems, LLC, Berkshire Power
                                                  the filer.                                              accepted SIL values identified in                         Company, LLC, Cogen Technologies
                                                     14. Changes in SIL values from the                   Appendix A to this order are hereby                       Linden Venture, L.P., East Coast Power
                                                  previous study period should be                         adopted for purposes of analyzing                         Linden Holding, L.L.C., Chambers
                                                  explained in the filing. Significant                    updated market power analyses for the                     Cogeneration Limited Partnership,
                                                  changes that affect the study area should               Southwest region, as discussed in the                     Logan Generating Company, LP,
                                                  be identified, for example, major                       body of this order.                                       Scrubgrass Generating Company, L.P.,
                                                  generation capacity additions or
                                                                                                            (B) The Secretary is hereby directed to                 Newark Energy Center LLC, EIF Newark,
                                                  retirements, the addition of a new high-
                                                                                                          publish a copy of this order in the                       LLC, Oregon Clean Energy, LLC.
                                                  voltage transmission line or other
                                                                                                          Federal Register.                                            Description: Notice of Non-Material
                                                  topology changes, modified line ratings,
                                                                                                                                                                    Change in Status of Edgecombe Genco,
                                                  and changes in operating procedures or                    By the Commission.
                                                                                                                                                                    LLC., et al.
                                                  study methodology. Clearly explaining                     Issued: January 24, 2017.                                  Filed Date: 1/19/17.
                                                  and identifying significant changes in                  Nathaniel J. Davis, Sr.,                                     Accession Number: 20170119–5208.
                                                  the SIL study results that occur between
                                                                                                          Deputy Secretary.                                            Comments Due: 5 p.m. ET 2/9/17.
                                                  filings will prevent delays in the
                                                  analysis of filings and reduce the need                 [FR Doc. 2017–01939 Filed 1–27–17; 8:45 am]                  Docket Numbers: ER17–820–000.
                                                                                                                                                                       Applicants: Southwest Power Pool,
mstockstill on DSK3G9T082PROD with NOTICES




                                                  for Commission staff to request filers to               BILLING CODE 6717–01–P
                                                  provide additional information.                                                                                   Inc.
                                                  Documentation of any changes should                        10 Results refer to the results of the market share       Description: § 205(d) Rate Filing:
                                                  extend back approximately five years                    and/or pivotal supplier screens. For example, if a        3114R2 Resale Power Group of Iowa to
                                                                                                          seller fails the market share screen for a particular     be effective 1/1/2017.
                                                  from the study period utilized in the                   season in a particular market using either SIL value,
                                                                                                          we would consider the result unchanged. Similarly,
                                                                                                                                                                       Filed Date: 1/19/17.
                                                    9 Order No. 697, FERC Stats. & Regs. ¶ 31,252 at      if the seller passes the screen using either value, the      Accession Number: 20170119–5156.
                                                  P 344.                                                  result is also unchanged.                                    Comments Due: 5 p.m. ET 2/9/17.


                                             VerDate Sep<11>2014   16:27 Jan 27, 2017   Jkt 241001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\30JAN1.SGM    30JAN1



Document Created: 2017-01-28 01:26:22
Document Modified: 2017-01-28 01:26:22
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 8739 

2025 Federal Register | Disclaimer | Privacy Policy