[Federal Register Volume 82, Number 26 (Thursday, February 9, 2017)]
[Notices]
[Pages 9998-9999]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-02653]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-9-000]


ANR Pipeline Company; Notice of Schedule for Environmental Review 
of the Wisconsin South Expansion Project

    On November 3, 2016, ANR Pipeline Company (ANR), filed an 
application in Docket No. CP17-9-000 requesting a Certificate of Public 
Convenience and Necessity pursuant to Section 7(c) and 7(b) of the 
Natural Gas Act to modify five existing facilities on ANR's Pipeline 
System. The proposed project is known as the Wisconsin South Expansion 
Project (Project), and consists of modifying and abandoning facilities 
in Illinois and Wisconsin to enable ANR to expand delivery by 230,950 
dekatherms per day (Dth/d) into the Northern Illinois and Wisconsin 
market areas.
    On November 16, 2016, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

Issuance of EA: April 27, 2017
90-day Federal Authorization Decision Deadline: July 26, 2017

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The Project would add an additional capacity of 230,950 Dth/d on 
ANR's system and consist of the modification of the following 
facilities: Install one new 6,130-horsepower (HP) Solar Centaur 50 
compressor unit at the existing Sandwich Compressor Station in Kendall 
County, Illinois; increase capacity of the existing Hampshire Meter 
Station in Kane County, Illinois from the current 304,475 Dth/d to 
approximately 507,458 Dth/d; replace the existing 0.54-mile-long Line 
332 Lateral located in Kane County, Illinois; increase capacity of the 
existing Tiffany East Meter Station in Rock County, Wisconsin from the 
current 119,760 Dth/d to approximately 240,535 Dth/d; and re-stage an 
existing Saturn 10 turbine compressor unit at the Kewaskum Compressor 
Station in Sheboygan County, Wisconsin.

Background

    On November 29, 2016, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Wisconsin South 
Expansion Project and Request for Comments on Environmental Issues 
(NOI). The NOI was sent to affected landowners; federal, state, and 
local government agencies; elected officials; environmental and public 
interest groups; Native American tribes; other interested parties; and 
local libraries and newspapers. In response to the NOI, the Commission 
received three comments from citizens supporting the Project. We also 
received comments from the Miami Tribe of Oklahoma and the Illinois 
Historic Preservation Agency, indicating that they do not object to the 
Project. Finally, we received a comment letter from the U.S.

[[Page 9999]]

Fish and Wildlife Service stating that the EA should fully disclose the 
impacts on federally listed species, migratory birds, and wildlife 
habitat.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC Web site (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP17-9-000), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
Web site also provides access to the texts of formal documents issued 
by the Commission, such as orders, notices, and rule makings.

    Dated: February 2, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-02653 Filed 2-8-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                9998                        Federal Register / Vol. 82, No. 26 / Thursday, February 9, 2017 / Notices

                                                  (vii) Sensitivity of Technology                       with a lock on before launch day or                   of Application for the Project. Among
                                                Contained in the Defense Article or                     night capability. The G model has an                  other things, that notice alerted agencies
                                                Defense Services Proposed to be Sold:                   imaging infrared (IIR) guidance system.               issuing federal authorizations of the
                                                See Annex attached.                                     The infrared Maverick G can track heat                requirement to complete all necessary
                                                  (viii) Date Report Delivered to                       generated by a target and provides the                reviews and to reach a final decision on
                                                Congress: January 31, 2017                              pilot a pictorial display of the target               a request for a federal authorization
                                                  *as defined in Section 47(6) of the                   during darkness and hazy or inclement                 within 90 days of the date of issuance
                                                Arms Export Control Act.                                weather. The warhead on the Maverick                  of the Commission staff’s Environmental
                                                POLICY JUSTIFICATION                                    G is a heavyweight penetrator warhead.                Assessment (EA) for the Project. This
                                                                                                        Maverick hardware is UNCLASSIFIED.                    instant notice identifies the FERC staff’s
                                                Republic of Korea—AGM–65G–2                             Performance and operating logic of the                planned schedule for the completion of
                                                Maverick Missiles                                       countermeasures circuits are SECRET.                  the EA for the Project.
                                                  The Government of the Republic of                     Overall system classification is SECRET.              Schedule for Environmental Review
                                                Korea (ROK) has requested the potential                    2. If a technologically advanced
                                                sale of eighty-nine (89) AGM–65G–2                      adversary were to obtain knowledge of                 Issuance of EA: April 27, 2017
                                                Maverick missiles, missile containers                   the specific hardware and software                    90-day Federal Authorization Decision
                                                and other related elements of support.                  elements, the information could be used                  Deadline: July 26, 2017
                                                The total estimated program cost is $70                 to develop countermeasures or                            If a schedule change becomes
                                                million.                                                equivalent systems which might reduce                 necessary, additional notice will be
                                                  This proposed sale contributes to the                 weapon effectiveness or be used in the                provided so that the relevant agencies
                                                foreign policy and national security of                 development of a system with similar or               are kept informed of the Project’s
                                                the United States. The ROK is one of the                advanced capabilities.                                progress.
                                                major political and economic powers in                     3. This sale is necessary to further the           Project Description
                                                East Asia and the Western Pacific and                   U.S. foreign policy and national security
                                                a key partner of the United States in                                                                            The Project would add an additional
                                                                                                        objectives outlined in the Policy
                                                ensuring peace and stability in the                                                                           capacity of 230,950 Dth/d on ANR’s
                                                                                                        Justification. Moreover, the benefits
                                                region. It is vital to U.S. national                                                                          system and consist of the modification
                                                                                                        derived from this sale, as outlined in the
                                                interests to assist our Korean ally in                                                                        of the following facilities: Install one
                                                                                                        Policy Justification, outweigh the                    new 6,130-horsepower (HP) Solar
                                                developing and maintaining a strong                     potential damage that could result if the
                                                and ready self-defense capability. This                                                                       Centaur 50 compressor unit at the
                                                                                                        sensitive technology were revealed to                 existing Sandwich Compressor Station
                                                sale increases the ROK’s capability to                  unauthorized persons.
                                                participate in Pacific regional security                                                                      in Kendall County, Illinois; increase
                                                                                                           4. All defense articles and services               capacity of the existing Hampshire
                                                operations and improves its national                    listed in this transmittal have been
                                                security posture as a key U.S. ally.                                                                          Meter Station in Kane County, Illinois
                                                                                                        authorized for release and export to the              from the current 304,475 Dth/d to
                                                  The proposed sale will improve the                    Republic of Korea.
                                                ROK’s capability to meet current and                                                                          approximately 507,458 Dth/d; replace
                                                                                                        [FR Doc. 2017–02704 Filed 2–8–17; 8:45 am]            the existing 0.54-mile-long Line 332
                                                future threats. The ROK will use the
                                                enhanced capability as a deterrent to                   BILLING CODE 5001–06–P                                Lateral located in Kane County, Illinois;
                                                regional threats and to strengthen its                                                                        increase capacity of the existing Tiffany
                                                homeland defense. The ROK, which                                                                              East Meter Station in Rock County,
                                                already has AGM–65G missiles in its                     DEPARTMENT OF ENERGY                                  Wisconsin from the current 119,760
                                                inventory, will have no difficulty                                                                            Dth/d to approximately 240,535 Dth/d;
                                                absorbing these additional missiles.                    Federal Energy Regulatory                             and re-stage an existing Saturn 10
                                                  The proposed sale of this equipment                   Commission                                            turbine compressor unit at the
                                                and support does not affect the basic                   [Docket No. CP17–9–000]
                                                                                                                                                              Kewaskum Compressor Station in
                                                military balance in the region.                                                                               Sheboygan County, Wisconsin.
                                                  The principal contractor is Raytheon,                 ANR Pipeline Company; Notice of                       Background
                                                Tucson, AZ. At this time, there are no                  Schedule for Environmental Review of
                                                known offset agreements proposed in                     the Wisconsin South Expansion                            On November 29, 2016, the
                                                connection with this potential sale.                    Project                                               Commission issued a Notice of Intent to
                                                  Implementation of this proposed sale                                                                        Prepare an Environmental Assessment
                                                will not require the assignment of any                     On November 3, 2016, ANR Pipeline                  for the Proposed Wisconsin South
                                                additional U.S. Government or                           Company (ANR), filed an application in                Expansion Project and Request for
                                                contractor representatives to the                       Docket No. CP17–9–000 requesting a                    Comments on Environmental Issues
                                                Republic of Korea.                                      Certificate of Public Convenience and                 (NOI). The NOI was sent to affected
                                                  There is no adverse impact on U.S.                    Necessity pursuant to Section 7(c) and                landowners; federal, state, and local
                                                defense readiness as a result of this                   7(b) of the Natural Gas Act to modify                 government agencies; elected officials;
                                                proposed sale.                                          five existing facilities on ANR’s Pipeline            environmental and public interest
                                                                                                        System. The proposed project is known                 groups; Native American tribes; other
                                                Transmittal No. 16–83                                   as the Wisconsin South Expansion                      interested parties; and local libraries
                                                Notice of Proposed Issuance of Letter of                Project (Project), and consists of                    and newspapers. In response to the NOI,
                                                Offer Pursuant to Section 36(b)(1) of the               modifying and abandoning facilities in                the Commission received three
sradovich on DSK3GMQ082PROD with NOTICES




                                                Arms Export Control Act                                 Illinois and Wisconsin to enable ANR to               comments from citizens supporting the
                                                Annex                                                   expand delivery by 230,950 dekatherms                 Project. We also received comments
                                                                                                        per day (Dth/d) into the Northern                     from the Miami Tribe of Oklahoma and
                                                Item No. vii                                            Illinois and Wisconsin market areas.                  the Illinois Historic Preservation
                                                   (vii) Sensitivity of Technology:                        On November 16, 2016, the Federal                  Agency, indicating that they do not
                                                   1. The AGM–65G–2 Maverick is an                      Energy Regulatory Commission                          object to the Project. Finally, we
                                                air-to-ground close air support missile                 (Commission or FERC) issued its Notice                received a comment letter from the U.S.


                                           VerDate Sep<11>2014   18:11 Feb 08, 2017   Jkt 241001   PO 00000   Frm 00016   Fmt 4703   Sfmt 4703   E:\FR\FM\09FEN1.SGM   09FEN1


                                                                            Federal Register / Vol. 82, No. 26 / Thursday, February 9, 2017 / Notices                                            9999

                                                Fish and Wildlife Service stating that                  proceeding. Due to a scheduling conflict                 Any person may, within 60 days after
                                                the EA should fully disclose the impacts                with the contracted venue in Nelson                   the issuance of the instant notice by the
                                                on federally listed species, migratory                  County, the start time for the public                 Commission, file pursuant to Rule 214
                                                birds, and wildlife habitat.                            comment session scheduled on                          of the Commission’s Procedural Rules
                                                                                                        February 22 at Nelson County High                     (18 CFR 385.214) a motion to intervene
                                                Additional Information                                                                                        or notice of intervention. Any person
                                                                                                        School has changed. This errata notice
                                                   In order to receive notification of the              announces the Wednesday, February 22,                 filing to intervene or the Commission’s
                                                issuance of the EA and to keep track of                 2017 public comment session will begin                staff may, pursuant to section 157.205 of
                                                all formal issuances and submittals in                  at 6:30 p.m. The session ending time                  the Commission’s Regulations under the
                                                specific dockets, the Commission offers                 remains 9:00 p.m. Additional court                    NGA (18 CFR 157.205) file a protest to
                                                a free service called eSubscription. This               reporters will be available at the Nelson             the request. If no protest is filed within
                                                can reduce the amount of time you                       County High School public comment                     the time allowed therefore, the proposed
                                                spend researching proceedings by                        session to account for the reduced                    activity shall be deemed to be
                                                automatically providing you with                        session length.                                       authorized effective the day after the
                                                notification of these filings, document                   Dated: February 2, 2017.
                                                                                                                                                              time allowed for protest. If a protest is
                                                summaries, and direct links to the                                                                            filed and not withdrawn within 30 days
                                                                                                        Kimberly D. Bose,
                                                documents. Go to www.ferc.gov/docs-                                                                           after the time allowed for filing a
                                                                                                        Secretary.                                            protest, the instant request shall be
                                                filing/esubscription.asp.
                                                   Additional information about the                     [FR Doc. 2017–02652 Filed 2–8–17; 8:45 am]            treated as an application for
                                                Project is available from the                           BILLING CODE 6717–01–P                                authorization pursuant to section 7 of
                                                Commission’s Office of External Affairs                                                                       the NGA.
                                                at (866) 208–FERC or on the FERC Web                                                                             Pursuant to section 157.9 of the
                                                site (www.ferc.gov). Using the                          DEPARTMENT OF ENERGY                                  Commission’s rules, 18 CFR 157.9,
                                                ‘‘eLibrary’’ link, select ‘‘General Search’’                                                                  within 90 days of this Notice the
                                                                                                        Federal Energy Regulatory                             Commission staff will either: Complete
                                                from the eLibrary menu, enter the                       Commission
                                                selected date range and ‘‘Docket                                                                              its environmental assessment (EA) and
                                                Number’’ excluding the last three digits                [Docket No. CP17–39–000]                              place it into the Commission’s public
                                                (i.e., CP17–9–000), and follow the                                                                            record (eLibrary) for this proceeding; or
                                                instructions. For assistance with access                Natural Gas Pipeline Company of                       issue a Notice of Schedule for
                                                to eLibrary, the helpline can be reached                America LLC; Notice of Request Under                  Environmental Review. If a Notice of
                                                at (866) 208–3676, TTY (202) 502–8659,                  Blanket Authorization                                 Schedule for Environmental Review is
                                                or at FERCOnlineSupport@ferc.gov. The                                                                         issued, it will indicate, among other
                                                                                                           Take notice that on January 23, 2017,              milestones, the anticipated date for the
                                                eLibrary link on the FERC Web site also                 Natural Gas Pipeline Company of
                                                provides access to the texts of formal                                                                        Commission staff’s issuance of the final
                                                                                                        America LLC (Natural), located at 3250                environmental impact statement (FEIS)
                                                documents issued by the Commission,                     Lacey Road, Suite 700, Downers Grove,
                                                such as orders, notices, and rule                                                                             or EA for this proposal. The filing of the
                                                                                                        Illinois 60515, filed in Docket No.                   EA in the Commission’s public record
                                                makings.                                                CP17–39–000, a prior notice request                   for this proceeding or the issuance of a
                                                  Dated: February 2, 2017.                              pursuant to sections 157.205, 157.208                 Notice of Schedule for Environmental
                                                Kimberly D. Bose,                                       and 157.216 of the Federal Energy                     Review will serve to notify federal and
                                                Secretary.                                              Regulatory Commission’s regulations                   state agencies of the timing for the
                                                [FR Doc. 2017–02653 Filed 2–8–17; 8:45 am]              under the Natural Gas Act (NGA),                      completion of all necessary reviews, and
                                                BILLING CODE 6717–01–P
                                                                                                        seeking authorization to abandon an                   the subsequent need to complete all
                                                                                                        injection and withdrawal well, the                    federal authorizations within 90 days of
                                                                                                        related pipeline lateral, and the related             the date of issuance of the Commission
                                                DEPARTMENT OF ENERGY                                    meter, tap and auxiliary facilities at                staff’s FEIS or EA.
                                                                                                        Natural’s North Lansing Storage Field                    Persons who wish to comment only
                                                Federal Energy Regulatory                               located in Harrison County, Texas, all as             on the environmental review of this
                                                Commission                                              more fully set forth in the application,              project should submit an original and
                                                                                                        which is on file with the Commission                  two copies of their comments to the
                                                Notice of Public Comment Session                        and open to public inspection. The                    Secretary of the Commission.
                                                Schedule Change for the Draft                           filing may also be viewed on the web at               Environmental commenter’s will be
                                                Environmental Impact Statement for                      http://www.ferc.gov using the                         placed on the Commission’s
                                                the Proposed Atlantic Coast Pipeline,                   ‘‘eLibrary’’ link. Enter the docket                   environmental mailing list, will receive
                                                Supply Header Project, and Capacity                     number excluding the last three digits in             copies of the environmental documents,
                                                Lease Proposal                                          the docket number field to access the                 and will be notified of meetings
                                                                                                        document. For assistance, contact FERC                associated with the Commission’s
                                                                                      Docket Nos.       at FERCOnlineSupport@ferc.gov or call                 environmental review process.
                                                                                                        toll-free, (866) 208–3676 or TTY, (202)               Environmental commenter’s will not be
                                                Atlantic Coast Pipeline,         CP15–554–000,
                                                  LLC.                           CP15–554–001           502–8659.                                             required to serve copies of filed
                                                Dominion Transmission,           CP15–555–000              Any questions regarding the Request                documents on all other parties.
                                                                                                        should be directed to Bruce H.
sradovich on DSK3GMQ082PROD with NOTICES




                                                  Inc.                                                                                                        However, the non-party commentary,
                                                Piedmont Natural Gas             CP15–556–000           Newsome, Vice President, Regulatory                   will not receive copies of all documents
                                                  Company, Inc.                                         Products and Services, Natural Gas                    filed by other parties or issued by the
                                                                                                        Pipeline Company of America LLC,                      Commission (except for the mailing of
                                                  On December 30, 2016, the                             3250 Lacey Road, Suite 700, Downers                   environmental documents issued by the
                                                Commission issued a Notice of                           Grove, Illinois 60515–7918, by                        Commission) and will not have the right
                                                Availability of the draft environmental                 telephone at: 630–725–3070, or by email               to seek court review of the
                                                impact statement in the above-captioned                 at bruce_newsome@kindermorgan.com.                    Commission’s final order.


                                           VerDate Sep<11>2014   18:11 Feb 08, 2017   Jkt 241001   PO 00000   Frm 00017   Fmt 4703   Sfmt 4703   E:\FR\FM\09FEN1.SGM   09FEN1



Document Created: 2017-02-09 01:03:05
Document Modified: 2017-02-09 01:03:05
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 9998 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR