As requested by Crescent Peak Renewables, LLC, and in compliance with the National Environmental Policy Act of 1969, as amended (NEPA), the Bureau of Land Management (BLM), Las Vegas Field Office will prepare an Environmental Impact Statement (EIS), which may include a Plan Amendment to the 1998 Las Vegas Resource Management Plan (RMP) or subsequent RMP, for a proposed wind energy project located on public lands 10 miles west of Searchlight in Clark County, Nevada. Publication of this Notice initiates the scoping process and opens a 90-day public comment period. The BLM is considering a Plan Amendment to change the Visual Resource Management classification of the project area. Through a separate ongoing process, the 1998 Las Vegas RMP is being revised. If the BLM issues a Record of Decision (ROD) before the RMP revision is completed, and a change to the plan is determined to be necessary, then the ROD would amend the 1998 RMP. If the ROD comes after RMP revision is completed, and a change to the plan is necessary, then the ROD would amend the revised RMP. Publication of this Notice serves to segregate the public lands from appropriation under the public land laws, including location under the Mining Law, but not the Mineral Leasing Act or the Materials Act, subject to valid existing rights. This Notice initiates the public scoping process and the segregation.

Federal Register, Volume 83 Issue 51 (Thursday, March 15, 2018)
[Federal Register Volume 83, Number 51 (Thursday, March 15, 2018)]
[Notices]
[Pages 11559-11561]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-05273]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Land Management

[LLNVS01000. L51010000.PQ0000. LVRWF09F1840; N-094470; MO#4500108571; 
TAS: 14X5017]


Notice of Intent To Prepare an Environmental Impact Statement and 
a Possible Land Use Plan Amendment for the Proposed Crescent Peak Wind 
Project, West of Searchlight in Clark County, Nevada; and a Notice of 
Public Lands Segregation

AGENCY: Bureau of Land Management, Department of the Interior.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: As requested by Crescent Peak Renewables, LLC, and in 
compliance with the National Environmental Policy Act of 1969, as 
amended (NEPA), the Bureau of Land Management (BLM), Las Vegas Field 
Office will prepare an Environmental Impact Statement (EIS), which may 
include a Plan Amendment to the 1998 Las Vegas Resource Management Plan 
(RMP) or subsequent RMP, for a proposed wind energy project located on 
public lands 10 miles west of Searchlight in Clark County, Nevada. 
Publication of this Notice initiates the scoping process and opens a 
90-day public comment period. The BLM is considering a Plan Amendment 
to change the Visual Resource Management classification of the project 
area. Through a separate ongoing process, the 1998 Las Vegas RMP is 
being revised. If the BLM issues a Record of Decision (ROD) before the 
RMP revision is completed, and a change to the plan is determined to be 
necessary, then the ROD would amend the 1998 RMP. If the ROD comes 
after RMP revision is completed, and a change to the plan is necessary, 
then the ROD would amend the revised RMP. Publication of this Notice 
serves to segregate the public lands from appropriation under the 
public land laws, including location under the Mining Law, but not the 
Mineral Leasing Act or the Materials Act, subject to valid existing 
rights. This Notice initiates the public scoping process and the 
segregation.

DATES: Comments on issues may be submitted in writing until June 13, 
2018. The date(s) and location(s) of the scoping meetings will be 
announced at least 15 days prior in a news release and on the BLM 
website at: http://bit.ly/2tkVGC5.
    Comments must be received prior to the close of the scoping period 
or no later than 15 days after the last public

[[Page 11560]]

meeting, whichever is later, to be included in the Draft EIS. The BLM 
will provide additional opportunities for public participation upon 
publication of the Draft EIS.

ADDRESSES: Submit comments related to the project by any of the 
following methods:
     Email: [email protected].
     Fax: (702) 515-5155, attention Gayle Marrs-Smith.
     Mail: BLM, Las Vegas Field Office, Attn: Gayle Marrs-
Smith, 4701 North Torrey Pines Drive, Las Vegas, NV 89130-2301.

FOR FURTHER INFORMATION CONTACT: For further information and/or to have 
your name added to the mailing list, send requests to: Gayle Marrs-
Smith, Field Manager, at telephone (702) 515-5199; or address 4701 
North Torrey Pines Drive, Las Vegas, NV 89130-2301; or email 
[email protected]. Persons who use a telecommunications 
device for the deaf (TDD) may call the Federal Relay Service (FRS) at 
1-800-877-8339 to contact the above individual during normal business 
hours. The FRS is available 24 hours a day, 7 days a week, to leave a 
message or question with the above individual. You will receive a reply 
during normal business hours.

SUPPLEMENTARY INFORMATION: On November 16, 2015, Crescent Peak 
Renewables, LLC, submitted an application to BLM requesting 
authorization to construct, operate, maintain, and terminate an up-to-
500 megawatt wind energy generation facility--Crescent Peak Renewables 
(N-94470). It would be located on four sites and constructed in two 
phases. The project area is 22 miles long (north and south) and 5 miles 
wide (east and west), covers 32,531 acres of public land and is located 
10 miles west of Searchlight, Nevada.
    Due to the size and potential impacts of the Crescent Peak wind 
project, the BLM is preparing an EIS. The purpose of the public scoping 
process is to identify relevant issues that will influence the scope of 
the environmental analysis, including alternatives, and to guide the 
process for developing the potential Plan Amendment. The BLM has 
identified the following preliminary issues: biological resources, 
visual resources, cultural resources, tribal interests, recreation, and 
cumulative impacts.
    The BLM will use the NEPA public commenting process to satisfy the 
public involvement process for Section 106 of the National Historic 
Preservation Act (NHPA) (54 U.S.C. 306108), as provided for in 36 CFR 
800.2(d)(3). The information about historic and cultural resources 
within the area potentially affected by the project will assist the BLM 
in identifying and evaluating impacts to such resources in the context 
of both NEPA and Section 106 of the NHPA.
    The BLM will consult with Native American tribes on a government-
to-government basis in accordance with applicable laws, regulations, 
Executive Order 13175, and other policies. Tribal concerns will be 
given due consideration, including impacts on Indian Trust assets. The 
Federal, State, and local agencies, along with other stakeholders that 
may be interested or affected by the BLM's decision on this project, 
are invited to participate in the scoping process and, if eligible, may 
request or be requested by the BLM to participate as a cooperating 
agency.
    Before including your address, phone number, email address, or 
other personal identifying information in your comment, you should be 
aware that your entire comment--including your personal identifying 
information--may be made publicly available at any time. While you can 
ask us in your comment to withhold your personal identifying 
information from public review, we cannot guarantee that we will be 
able to do so.

Segregation of the Public Lands

    In 2013, the BLM published a Final Rule, Segregation of Lands--
Renewable Energy (78 FR 25204), that amended the regulations found in 
43 CFR 2090 and 2800. The provisions of the Final Rule allow the BLM to 
temporarily segregate public lands within a solar or wind application 
area from the operation of the public land laws, including the Mining 
Law, by publication of a Federal Register Notice. This temporary 
segregation does not affect valid existing rights of mining claims 
located before this segregation notice. The purpose of this temporary 
segregation is to allow for the orderly administration of the public 
lands associated with the BLM's consideration of this renewable energy 
ROW. Licenses, permits, cooperative agreements, or discretionary land 
use authorizations of a temporary nature will not impact lands 
identified in this Notice and may be allowed with the approval of the 
authorized officer of the BLM. The lands segregated under this Notice 
are legally described as follows:

Mount Diablo Meridian, Clark County, Nevada

Mount Diablo Meridian, Nevada

T. 27 S., R. 61 E.,
    Sec. 27, E\1/2\, E\1/2\NW\1/4\, and E\1/2\SW\1/4\;
    Sec. 33, SE\1/4\NE\1/4\, E\1/2\SE\1/4\, and S\1/2\SW\1/4\;
    Sec. 34.
T. 28 S., R. 60 E.,
    Sec. 1, lot 4, S\1/2\NW\1/4\, SW\1/4\, and S\1/2\SE\1/4\;
    Sec. 12;
    Sec. 13, except Patented Mineral Survey No. 2594.
T. 28 S., R. 61 E.,
    Secs. 3 and 4;
    Sec. 5, lot 1 and SE\1/4\NE\1/4\;
    Sec. 6, S\1/2\SE\1/4\;
    Secs. 7, 8, and 9;
    Sec. 10, N\1/2\NE\1/4\, N\1/2\NW\1/4\, and SE\1/4\SW\1/4\;
    Sec. 13 and 14, except Patented Mineral Survey No. 4490 and 
4579;
    Sec. 15, SE\1/4\NE\1/4\, SE\1/4\SW\1/4\, and SE\1/4\;
    Sec. 16, N\1/2\NE\1/4\ and N\1/2\NW\1/4\;
    Sec. 17;
    Sec. 18, except Patented Mineral Survey No. 2594;
    Sec. 22, except Patented Mineral Survey No. 2945 and 2940;
    Sec. 23, except Patented Mineral Survey No. 2776, 4799, and 
4579;
    Sec. 24, except Patented Mineral Survey No. 4579;
    Sec. 25, except Patented Mineral Survey No. 2632;
    Sec. 26, except Patented Mineral Survey No. 2939, 2687, and 
4799;
    Sec. 27, except Patented Mineral Survey No. 2939, 2687, and 
2945;
    Sec. 33, E\1/2\NE\1/4\ and E\1/2\SE\1/4\;
    Secs. 34 and 35, except Patented Mineral Survey No. 2687;
    Sec. 36.
T. 28 S., R. 62 E.,
    Secs. 18, 19, and 30;
    Sec. 31, lots 5 thru 12, NE\1/4\, and E\1/2\NW\1/4\.
T. 29 S., R. 61 E.,
    Sec. 1, lots 1 thru 4, S\1/2\NE\1/4\, and S\1/2\NW\1/4\, except 
Patented Mineral Survey No. 3580;
    Sec. 2, lots 1 thru 4, S\1/2\NE\1/4\, and S\1/2\NW\1/4\;
    Sec. 3, lots 1 thru 4, S\1/2\NE\1/4\, and S\1/2\NW\1/4\;
    Secs. 10 thru 15 and secs. 22 thru 26.
T. 29 S., R. 62 E.,
    Sec. 6, lots 3 thru 7, SE\1/4\NW\1/4\, and E\1/2\SW\1/4\;
    Sec. 32, SE\1/4\SE\1/4\;
    Sec. 33, NW\1/4\NE\1/4\, NE\1/4\NW\1/4\, S\1/2\NE\1/4\, S\1/
2\NW\1/4\, and S\1/2\.
T. 30 S., R. 62 E.,
    Secs. 3 and 4;
    Sec. 5, except Patented Mineral Survey No. 4803;
    Secs. 6, 8, 9, and 10;
    Sec. 15, except Patented Mineral Survey No. 2652;
    Secs. 16, 22 thru 26, and 36.
T. 30 S., R. 63 E.,
    Secs. 30 and 31.
T. 31 S., R. 63 E.,
    Sec. 6.

    As provided in the Final Rule, the segregation of lands in this 
Notice will not exceed two years from the date of publication of this 
Notice, though it can

[[Page 11561]]

be extended for up to two additional years through publication of a new 
notice in the Federal Register. Termination of the segregation occurs 
on the earliest of the following dates: upon issuance of a decision by 
the authorized officer granting, granting with modifications, or 
denying the application for a right-of-way; automatically at the end of 
the segregation; or upon publication of a Federal Register Notice of 
termination of the segregation.
    Upon termination of segregation of these lands, all lands subject 
to this segregation will automatically reopen to appropriation under 
the public land laws.

(Authority: 43 CFR 2800 and 2090)

Gayle Marrs-Smith,
Las Vegas Field Manager.
[FR Doc. 2018-05273 Filed 3-14-18; 8:45 am]
 BILLING CODE 4310-HC-P



                                                                             Federal Register / Vol. 83, No. 51 / Thursday, March 15, 2018 / Notices                                           11559

                                                settlement of their natural resource                    early restoration plans and in                        DEPARTMENT OF THE INTERIOR
                                                damage claims with BP in an April 4,                    accordance with the Consent Decree.
                                                2016, Consent Decree approved by the                    The Trustees have determined that                     Bureau of Land Management
                                                United States District Court for the                    decisions concerning any unexpended                   [LLNVS01000. L51010000.PQ0000.
                                                Eastern District of Louisiana. Pursuant                 early restoration funds are to be made                LVRWF09F1840; N–094470;
                                                to that Consent Decree, restoration                     by the appropriate TIG, in this case the              MO#4500108571; TAS: 14X5017]
                                                projects in the Florida Restoration Area                Florida TIG.
                                                are now chosen and managed by the                                                                             Notice of Intent To Prepare an
                                                Florida TIG. The Florida TIG is                         Overview of the Final Phase V.2 RP/                   Environmental Impact Statement and a
                                                composed of the following six Trustees:                 SEA                                                   Possible Land Use Plan Amendment
                                                State of Florida Department of                                                                                for the Proposed Crescent Peak Wind
                                                                                                           The Final Phase V.2 RP/SEA/FONSI
                                                Environmental Protection and Fish and                                                                         Project, West of Searchlight in Clark
                                                                                                        is being released in accordance with
                                                Wildlife Conservation Commission;                                                                             County, Nevada; and a Notice of Public
                                                                                                        OPA, NRDA regulations found in the
                                                DOI; NOAA; EPA; and USDA.                                                                                     Lands Segregation
                                                   A notice of availability of the Draft                Code of Federal Regulations (CFR) at 15
                                                Phase V.2 Restoration Plan and                          CFR part 990, NEPA, the Consent                       AGENCY: Bureau of Land Management,
                                                Supplemental Environmental                              Decree, the Final PDARP/PEIS, the                     Department of the Interior.
                                                Assessment was published in the                         Phase III ERP/PEIS and the Phase V                    ACTION: Notice of intent.
                                                Federal Register on November 8, 2017                    ERP/EA. The purpose of this notice is to
                                                                                                        inform the public of the availability of              SUMMARY:    As requested by Crescent
                                                (82 FR 51858). The public was provided                                                                        Peak Renewables, LLC, and in
                                                with a period to review and comment                     the Final Phase V.2 RP/SEA and FONSI.
                                                                                                                                                              compliance with the National
                                                on the Draft Restoration Plan, from                        The Florida TIG has selected to fund               Environmental Policy Act of 1969, as
                                                November 8, 2017, through December 8,                   the second phase of the Florida Coastal               amended (NEPA), the Bureau of Land
                                                2017, and a public meeting was held on                  Access Project in the Final Phase V.2                 Management (BLM), Las Vegas Field
                                                November 16, 2017, in Port St. Joe,                     RP/SEA to address lost recreational                   Office will prepare an Environmental
                                                Florida. The Florida TIG considered the                 opportunities in Florida caused by the                Impact Statement (EIS), which may
                                                public comments received, which                         Deepwater Horizon oil spill. In the Final             include a Plan Amendment to the 1998
                                                informed the TIG’s analyses and                         Phase V.2 RP/SEA, the Florida TIG                     Las Vegas Resource Management Plan
                                                selection of the preferred restoration                  selected to fund one alternative, the                 (RMP) or subsequent RMP, for a
                                                alternative, the Salinas Park Addition                  Salinas Park Addition, which involves                 proposed wind energy project located
                                                project, in the Final Phase V.2 RP/SEA.                 the acquisition and enhancement of a                  on public lands 10 miles west of
                                                A summary of the public comments                        6.6-acre coastal parcel. The Florida                  Searchlight in Clark County, Nevada.
                                                received, and the Florida TIG’s                         Coastal Access Project was allocated
                                                responses to those comments, are                                                                              Publication of this Notice initiates the
                                                                                                        approximately $45.4 million in early                  scoping process and opens a 90-day
                                                addressed in Chapter 6 of the Final                     restoration funds, and the Salinas Park
                                                Phase V.2 RP/SEA. The FONSI is                                                                                public comment period. The BLM is
                                                                                                        Addition will cost approximately $3.2                 considering a Plan Amendment to
                                                included as Appendix C of the Final                     million of the $6.4 million remaining
                                                Phase V.2 RP/SEA.                                                                                             change the Visual Resource
                                                                                                        funds not utilized in the first phase of              Management classification of the project
                                                Background                                              the Florida Coastal Access Project.                   area. Through a separate ongoing
                                                                                                        Details on the second phase of the                    process, the 1998 Las Vegas RMP is
                                                  In the 2011 Framework Agreement for                   Florida Coastal Access Project are
                                                Early Restoration Addressing Injuries                                                                         being revised. If the BLM issues a
                                                                                                        provided in the Final Phase V.2 RP/                   Record of Decision (ROD) before the
                                                Resulting from the Deepwater Horizon                    SEA. Additional restoration planning
                                                Oil Spill (Framework Agreement), BP                                                                           RMP revision is completed, and a
                                                                                                        for the Florida Restoration Area will                 change to the plan is determined to be
                                                agreed to provide to the Trustees up to                 continue.
                                                $1 billion toward early restoration                                                                           necessary, then the ROD would amend
                                                projects in the Gulf of Mexico to address               Administrative Record                                 the 1998 RMP. If the ROD comes after
                                                injuries to natural resources caused by                                                                       RMP revision is completed, and a
                                                the Deepwater Horizon oil spill. The                      The documents comprising the                        change to the plan is necessary, then the
                                                Framework Agreement represented a                       Administrative Record for the Final                   ROD would amend the revised RMP.
                                                preliminary step toward the restoration                 Phase V.2 RP/SEA can be viewed at                     Publication of this Notice serves to
                                                of injured natural resources and was                    http://www.doi.gov/deepwaterhorizon/                  segregate the public lands from
                                                intended to expedite the start of                       administrativerecord.                                 appropriation under the public land
                                                restoration in the Gulf in advance of the                                                                     laws, including location under the
                                                                                                        Authority
                                                completion of the injury assessment                                                                           Mining Law, but not the Mineral
                                                process. In the five phases of the early                  The authority of this action is the Oil             Leasing Act or the Materials Act, subject
                                                restoration process, the Trustees                       Pollution Act of 1990 (33 U.S.C. 2701 et              to valid existing rights. This Notice
                                                selected, and BP agreed to fund, a total                seq.) and its implementing Natural                    initiates the public scoping process and
                                                of 65 early restoration projects expected               Resource Damage Assessment                            the segregation.
                                                to cost a total of approximately $877                   regulations found at 15 CFR part 990                  DATES: Comments on issues may be
                                                million. The Trustees selected these                    and the National Environmental Policy                 submitted in writing until June 13,
sradovich on DSK3GMQ082PROD with NOTICES




                                                projects after public notice, public                    Act of 1969 (42 U.S.C. 4321 et seq.).                 2018. The date(s) and location(s) of the
                                                meetings, and consideration of public                                                                         scoping meetings will be announced at
                                                comments.                                               Kevin D. Reynolds,                                    least 15 days prior in a news release and
                                                  The April 4, 2016, Consent Decree                     Designated Department of the Interior Natural         on the BLM website at: http://bit.ly/
                                                terminated and replaced the Framework                   Resource Trustee Official for the Florida             2tkVGC5.
                                                Agreement and provided that the                         Implementation Group.                                    Comments must be received prior to
                                                Trustees shall use remaining early                      [FR Doc. 2018–05137 Filed 3–14–18; 8:45 am]           the close of the scoping period or no
                                                restoration funds as specified in the                   BILLING CODE 4333–15–P                                later than 15 days after the last public


                                           VerDate Sep<11>2014   17:34 Mar 14, 2018   Jkt 244001   PO 00000   Frm 00072   Fmt 4703   Sfmt 4703   E:\FR\FM\15MRN1.SGM   15MRN1


                                                11560                        Federal Register / Vol. 83, No. 51 / Thursday, March 15, 2018 / Notices

                                                meeting, whichever is later, to be                      306108), as provided for in 36 CFR                      Sec. 27, E1⁄2, E1⁄2NW1⁄4, and E1⁄2SW1⁄4;
                                                included in the Draft EIS. The BLM will                 800.2(d)(3). The information about                      Sec. 33, SE1⁄4NE1⁄4, E1⁄2SE1⁄4, and
                                                provide additional opportunities for                    historic and cultural resources within                    S1⁄2SW1⁄4;
                                                                                                                                                                Sec. 34.
                                                public participation upon publication of                the area potentially affected by the
                                                                                                                                                              T. 28 S., R. 60 E.,
                                                the Draft EIS.                                          project will assist the BLM in                          Sec. 1, lot 4, S1⁄2NW1⁄4, SW1⁄4, and
                                                ADDRESSES: Submit comments related to                   identifying and evaluating impacts to                     S1⁄2SE1⁄4;
                                                the project by any of the following                     such resources in the context of both                   Sec. 12;
                                                methods:                                                NEPA and Section 106 of the NHPA.                       Sec. 13, except Patented Mineral Survey
                                                   • Email: blm_nv_sndo_crescentpeak@                      The BLM will consult with Native                       No. 2594.
                                                blm.gov.                                                American tribes on a government-to-                   T. 28 S., R. 61 E.,
                                                   • Fax: (702) 515–5155, attention                     government basis in accordance with                     Secs. 3 and 4;
                                                Gayle Marrs-Smith.                                      applicable laws, regulations, Executive                 Sec. 5, lot 1 and SE1⁄4NE1⁄4;
                                                                                                                                                                Sec. 6, S1⁄2SE1⁄4;
                                                   • Mail: BLM, Las Vegas Field Office,                 Order 13175, and other policies. Tribal
                                                                                                                                                                Secs. 7, 8, and 9;
                                                Attn: Gayle Marrs-Smith, 4701 North                     concerns will be given due                              Sec. 10, N1⁄2NE1⁄4, N1⁄2NW1⁄4, and
                                                Torrey Pines Drive, Las Vegas, NV                       consideration, including impacts on                       SE1⁄4SW1⁄4;
                                                89130–2301.                                             Indian Trust assets. The Federal, State,                Sec. 13 and 14, except Patented Mineral
                                                FOR FURTHER INFORMATION CONTACT: For                    and local agencies, along with other                      Survey No. 4490 and 4579;
                                                further information and/or to have your                 stakeholders that may be interested or                  Sec. 15, SE1⁄4NE1⁄4, SE1⁄4SW1⁄4, and SE1⁄4;
                                                name added to the mailing list, send                    affected by the BLM’s decision on this                  Sec. 16, N1⁄2NE1⁄4 and N1⁄2NW1⁄4;
                                                requests to: Gayle Marrs-Smith, Field                   project, are invited to participate in the              Sec. 17;
                                                                                                        scoping process and, if eligible, may                   Sec. 18, except Patented Mineral Survey
                                                Manager, at telephone (702) 515–5199;                                                                             No. 2594;
                                                or address 4701 North Torrey Pines                      request or be requested by the BLM to
                                                                                                                                                                Sec. 22, except Patented Mineral Survey
                                                Drive, Las Vegas, NV 89130–2301; or                     participate as a cooperating agency.                      No. 2945 and 2940;
                                                email blm_nv_sndo_crescentpeak@                            Before including your address, phone                 Sec. 23, except Patented Mineral Survey
                                                blm.gov. Persons who use a                              number, email address, or other                           No. 2776, 4799, and 4579;
                                                telecommunications device for the deaf                  personal identifying information in your                Sec. 24, except Patented Mineral Survey
                                                (TDD) may call the Federal Relay                        comment, you should be aware that                         No. 4579;
                                                Service (FRS) at 1–800–877–8339 to                      your entire comment—including your                      Sec. 25, except Patented Mineral Survey
                                                contact the above individual during                     personal identifying information—may                      No. 2632;
                                                                                                        be made publicly available at any time.                 Sec. 26, except Patented Mineral Survey
                                                normal business hours. The FRS is                                                                                 No. 2939, 2687, and 4799;
                                                available 24 hours a day, 7 days a week,                While you can ask us in your comment
                                                                                                                                                                Sec. 27, except Patented Mineral Survey
                                                to leave a message or question with the                 to withhold your personal identifying                     No. 2939, 2687, and 2945;
                                                above individual. You will receive a                    information from public review, we                      Sec. 33, E1⁄2NE1⁄4 and E1⁄2SE1⁄4;
                                                reply during normal business hours.                     cannot guarantee that we will be able to                Secs. 34 and 35, except Patented Mineral
                                                SUPPLEMENTARY INFORMATION: On                           do so.                                                    Survey No. 2687;
                                                November 16, 2015, Crescent Peak                                                                                Sec. 36.
                                                                                                        Segregation of the Public Lands                       T. 28 S., R. 62 E.,
                                                Renewables, LLC, submitted an
                                                                                                           In 2013, the BLM published a Final                   Secs. 18, 19, and 30;
                                                application to BLM requesting                                                                                   Sec. 31, lots 5 thru 12, NE1⁄4, and
                                                authorization to construct, operate,                    Rule, Segregation of Lands—Renewable
                                                                                                        Energy (78 FR 25204), that amended the                    E1⁄2NW1⁄4.
                                                maintain, and terminate an up-to-500                                                                          T. 29 S., R. 61 E.,
                                                megawatt wind energy generation                         regulations found in 43 CFR 2090 and
                                                                                                                                                                Sec. 1, lots 1 thru 4, S1⁄2NE1⁄4, and
                                                facility—Crescent Peak Renewables (N–                   2800. The provisions of the Final Rule                    S1⁄2NW1⁄4, except Patented Mineral
                                                94470). It would be located on four sites               allow the BLM to temporarily segregate                    Survey No. 3580;
                                                and constructed in two phases. The                      public lands within a solar or wind                     Sec. 2, lots 1 thru 4, S1⁄2NE1⁄4, and
                                                project area is 22 miles long (north and                application area from the operation of                    S1⁄2NW1⁄4;
                                                south) and 5 miles wide (east and west),                the public land laws, including the                     Sec. 3, lots 1 thru 4, S1⁄2NE1⁄4, and
                                                                                                        Mining Law, by publication of a Federal                   S1⁄2NW1⁄4;
                                                covers 32,531 acres of public land and                                                                          Secs. 10 thru 15 and secs. 22 thru 26.
                                                is located 10 miles west of Searchlight,                Register Notice. This temporary
                                                                                                        segregation does not affect valid existing            T. 29 S., R. 62 E.,
                                                Nevada.                                                                                                         Sec. 6, lots 3 thru 7, SE1⁄4NW1⁄4, and
                                                   Due to the size and potential impacts                rights of mining claims located before
                                                                                                                                                                  E1⁄2SW1⁄4;
                                                of the Crescent Peak wind project, the                  this segregation notice. The purpose of                 Sec. 32, SE1⁄4SE1⁄4;
                                                BLM is preparing an EIS. The purpose                    this temporary segregation is to allow                  Sec. 33, NW1⁄4NE1⁄4, NE1⁄4NW1⁄4, S1⁄2NE1⁄4,
                                                of the public scoping process is to                     for the orderly administration of the                     S1⁄2NW1⁄4, and S1⁄2.
                                                identify relevant issues that will                      public lands associated with the BLM’s                T. 30 S., R. 62 E.,
                                                influence the scope of the                              consideration of this renewable energy                  Secs. 3 and 4;
                                                                                                        ROW. Licenses, permits, cooperative                     Sec. 5, except Patented Mineral Survey No.
                                                environmental analysis, including                                                                                 4803;
                                                alternatives, and to guide the process for              agreements, or discretionary land use
                                                                                                        authorizations of a temporary nature                    Secs. 6, 8, 9, and 10;
                                                developing the potential Plan                                                                                   Sec. 15, except Patented Mineral Survey
                                                Amendment. The BLM has identified                       will not impact lands identified in this
                                                                                                                                                                  No. 2652;
                                                the following preliminary issues:                       Notice and may be allowed with the                      Secs. 16, 22 thru 26, and 36.
                                                                                                        approval of the authorized officer of the
sradovich on DSK3GMQ082PROD with NOTICES




                                                biological resources, visual resources,                                                                       T. 30 S., R. 63 E.,
                                                cultural resources, tribal interests,                   BLM. The lands segregated under this                    Secs. 30 and 31.
                                                recreation, and cumulative impacts.                     Notice are legally described as follows:              T. 31 S., R. 63 E.,
                                                   The BLM will use the NEPA public                                                                             Sec. 6.
                                                                                                        Mount Diablo Meridian, Clark County,
                                                commenting process to satisfy the                       Nevada                                                  As provided in the Final Rule, the
                                                public involvement process for Section                                                                        segregation of lands in this Notice will
                                                106 of the National Historic                            Mount Diablo Meridian, Nevada                         not exceed two years from the date of
                                                Preservation Act (NHPA) (54 U.S.C.                      T. 27 S., R. 61 E.,                                   publication of this Notice, though it can


                                           VerDate Sep<11>2014   17:34 Mar 14, 2018   Jkt 244001   PO 00000   Frm 00073   Fmt 4703   Sfmt 4703   E:\FR\FM\15MRN1.SGM   15MRN1


                                                                             Federal Register / Vol. 83, No. 51 / Thursday, March 15, 2018 / Notices                                                  11561

                                                be extended for up to two additional                    Control Number 1029–0112 in the                       protection and reclamation
                                                years through publication of a new                      subject line of your comments.                        requirements of 30 CFR parts 772 and
                                                notice in the Federal Register.                         FOR FURTHER INFORMATION CONTACT:      To              815, and section 512 of SMCRA (30
                                                Termination of the segregation occurs                   request additional information about                  U.S.C. 1262).
                                                on the earliest of the following dates:                 this ICR, contact John Trelease by email                Form Number: None.
                                                upon issuance of a decision by the                      at jtrelease@osmre.gov, or by telephone                 Type of Review: Extension of a
                                                authorized officer granting, granting                   at (202) 208–2783. You may also view                  currently approved collection.
                                                with modifications, or denying the                      the ICR at http://www.reginfo.gov/                      Respondents/Affected Public: Persons
                                                application for a right-of-way;                         public/do/PRAMain.                                    planning to conduct coal exploration
                                                automatically at the end of the                                                                               and State regulatory authorities.
                                                                                                        SUPPLEMENTARY INFORMATION: In
                                                segregation; or upon publication of a                                                                           Total Estimated Number of Annual
                                                                                                        accordance with the Paperwork
                                                Federal Register Notice of termination                                                                        Respondents: 320 coal operators and 24
                                                                                                        Reduction Act of 1995, we provide the
                                                of the segregation.                                                                                           State regulatory authorities.
                                                                                                        general public and other Federal
                                                  Upon termination of segregation of                                                                            Total Estimated Number of Annual
                                                                                                        agencies with an opportunity to
                                                these lands, all lands subject to this                                                                        Responses: 613.
                                                                                                        comment on new, proposed, revised,                      Estimated Completion Time per
                                                segregation will automatically reopen to                and continuing collections of
                                                appropriation under the public land                                                                           Response: Varies from .5 hours to 70
                                                                                                        information. This helps us assess the                 hours, depending on type of respondent
                                                laws.                                                   impact of our information collection                  and activity.
                                                (Authority: 43 CFR 2800 and 2090)                       requirements and minimize the public’s                  Total Estimated Number of Annual
                                                Gayle Marrs-Smith,                                      reporting burden. It also helps the                   Burden Hours: 1,864 hours.
                                                                                                        public understand our information                       Respondent’s Obligation: Required to
                                                Las Vegas Field Manager.
                                                                                                        collection requirements and provides                  Obtain or Retain a Benefit.
                                                [FR Doc. 2018–05273 Filed 3–14–18; 8:45 am]
                                                                                                        the requested data in the desired format.               Frequency of Collection: One time.
                                                BILLING CODE 4310–HC–P                                     A Federal Register notice with a 60-                 Total Estimated Annual Nonhour
                                                                                                        day public comment period soliciting                  Burden Cost: $288.
                                                                                                        comments on this collection of                          An agency may not conduct or
                                                DEPARTMENT OF THE INTERIOR                              information was published on                          sponsor and a person is not required to
                                                Office of Surface Mining Reclamation                    November 20, 2017 (82 FR 55114). No                   respond to a collection of information
                                                and Enforcement                                         comments were received.                               unless it displays a currently valid OMB
                                                                                                           We are again soliciting comments on                control number.
                                                [S1D1S SS08011000 SX066A0067F                           the proposed ICR that is described                      The authority for this action is the
                                                178S180110; S2D2D SS08011000 SX066A00                   below. We are especially interested in
                                                33F 17XS501520; OMB Control Number                                                                            Paperwork Reduction Act of 1995 (44
                                                                                                        public comment addressing the                         U.S.C. 3501 et seq.).
                                                1029–0112]
                                                                                                        following issues: (1) Is the collection
                                                                                                                                                                Dated: March 12, 2018.
                                                Agency Information Collection                           necessary to the proper functions of
                                                                                                        OSMRE; (2) is the estimate of burden                  John A. Trelease,
                                                Activities: Submission to the Office of                                                                       Acting Chief, Division of Regulatory Support.
                                                Management and Budget for Review                        accurate; (3) how might OSMRE
                                                                                                        enhance the quality, utility, and clarity             [FR Doc. 2018–05236 Filed 3–14–18; 8:45 am]
                                                and Approval; Requirements for Coal
                                                Exploration                                             of the information to be collected; and               BILLING CODE 4310–05–P
                                                                                                        (4) how might OSMRE minimize the
                                                AGENCY:  Office of Surface Mining                       burden of this collection on the
                                                Reclamation and Enforcement, Interior.                  respondents, including through the use                DEPARTMENT OF THE INTERIOR
                                                ACTION: Notice of information collection;               of information technology.
                                                request for comment.                                       Comments that you submit in                        Office of Surface Mining Reclamation
                                                                                                        response to this notice are a matter of               and Enforcement
                                                SUMMARY:   In accordance with the                       public record. Before including your                  [S1D1S SS08011000 SX066A0067F
                                                Paperwork Reduction Act of 1995, we,                    address, phone number, email address,                 178S180110; S2D2D SS08011000 SX066A00
                                                the Office of Surface Mining                            or other personal identifying                         33F 17XS501520; OMB Control Number
                                                Reclamation and Enforcement (OSMRE)                     information in your comment, you                      1029–0040]
                                                are proposing to renew an information                   should be aware that your entire
                                                collection related to requirements for                                                                        Agency Information Collection
                                                                                                        comment—including your personal
                                                coal exploration.                                                                                             Activities: Submission to the Office of
                                                                                                        identifying information—may be made
                                                DATES: Interested persons are invited to                                                                      Management and Budget for Review
                                                                                                        publicly available at any time. While
                                                submit comments on or before April 16,                                                                        and Approval; Requirements for
                                                                                                        you can ask us in your comment to
                                                2018                                                                                                          Permits for Special Categories of
                                                                                                        withhold your personal identifying
                                                ADDRESSES: Send written comments on
                                                                                                                                                              Mining
                                                                                                        information from public review, we
                                                this information collection request (ICR)               cannot guarantee that we will be able to              AGENCY:  Office of Surface Mining
                                                to the Office of Management and                         do so.                                                Reclamation and Enforcement, Interior.
                                                Budget’s Desk Officer for the                              Title: 30 CFR part 772—Requirements                ACTION: Notice of information collection;
                                                Department of the Interior by email at                  for coal exploration.                                 request for comment.
                                                OIRA_Submission@omb.eop.gov; or via                        OMB Control Number: 1029–0112.
sradovich on DSK3GMQ082PROD with NOTICES




                                                facsimile to (202) 395–5806. Please                        Abstract: OSMRE and State regulatory               SUMMARY:   In accordance with the
                                                provide a copy of your comments to                      authorities use the information collected             Paperwork Reduction Act of 1995, we,
                                                John Trelease, Office of Surface Mining                 under 30 CFR part 772 to keep track of                the Office of Surface Mining
                                                Reclamation and Enforcement, 1849 C                     coal exploration activities, evaluate the             Reclamation and Enforcement (OSMRE)
                                                Street NW, Mail Stop 4559, Washington,                  need for an exploration permit, and                   are proposing to renew an information
                                                DC 20240; or by email to jtrelease@                     ensure that exploration activities                    collection relating to requirements for
                                                osmre.gov. Please reference OMB                         comply with the environmental                         permits for special categories of mining.


                                           VerDate Sep<11>2014   17:34 Mar 14, 2018   Jkt 244001   PO 00000   Frm 00074   Fmt 4703   Sfmt 4703   E:\FR\FM\15MRN1.SGM   15MRN1



Document Created: 2018-03-15 02:37:31
Document Modified: 2018-03-15 02:37:31
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of intent.
DatesComments on issues may be submitted in writing until June 13, 2018. The date(s) and location(s) of the scoping meetings will be announced at least 15 days prior in a news release and on the BLM website at: http://bit.ly/2tkVGC5.
ContactFor further information and/or to have your name added to the mailing list, send requests to: Gayle Marrs-
FR Citation83 FR 11559 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR