83_FR_12055 83 FR 12002 - Notice of Schedule for Environmental Review of the Alaska Gasline Development Corporation Alaska LNG Project

83 FR 12002 - Notice of Schedule for Environmental Review of the Alaska Gasline Development Corporation Alaska LNG Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 53 (March 19, 2018)

Page Range12002-12002
FR Document2018-05427

Federal Register, Volume 83 Issue 53 (Monday, March 19, 2018)
[Federal Register Volume 83, Number 53 (Monday, March 19, 2018)]
[Notices]
[Page 12002]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-05427]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-178-000]


Notice of Schedule for Environmental Review of the Alaska Gasline 
Development Corporation Alaska LNG Project

    On April 17, 2017, the Alaska Gasline Development Corporation 
(AGDC) filed an application in Docket No. CP17-178-000 requesting 
authorization pursuant to section 3(a) of the Natural Gas Act (NGA) to 
construct and operate liquefied natural gas (LNG) export facilities. 
The proposed project is known as the Alaska LNG Project (Project) and 
would commercialize natural gas resources on the North Slope during the 
economic life of the Prudhoe Bay Unit field and provide at least five 
interconnection points along the pipeline to allow for in-state gas 
deliveries.
    On May 1, 2017, the Federal Energy Regulatory Commission (FERC or 
Commission) issued its Notice of Application for the Project. Among 
other things, that notice alerted other agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on the request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's final 
Environmental Impact Statement (EIS) for the Alaska LNG Project. This 
instant notice identifies the FERC staff's planned schedule for 
completion of the final EIS for the Project, which is based on an 
issuance of the draft EIS in March 2019.

Schedule for Environmental Review

Issuance of Notice of Availability of the final EIS--December 9, 2019
90-Day Federal Authorization Decision Deadline--March 8, 2020

    If a schedule change becomes necessary for the final EIS, an 
additional notice will be provided so that the relevant agencies are 
kept informed of the Project's progress.

Project Description

    AGDC is seeking authorization to construct, own, and operate a new 
gas treatment plant near Prudhoe Bay; a 1.0-mile-long, 60-inch-diameter 
Prudhoe Bay Unit Gas Transmission Line; a 62.5-mile-long, 32-inch-
diameter Point Thomson Unit Gas Transmission Line; a 806.6-mile-long, 
42-inch-diameter natural gas pipeline from the gas treatment plant to 
the LNG terminal in Nikiski; an LNG terminal with a 20 million ton per 
annum liquefaction capacity; associated aboveground facilities; and 
non-jurisdictional facilities in Alaska. The Project would have an 
annual average inlet design capacity of up to 3.7 billion standard 
cubic feet per day and a 3.9 billion standard cubic feet per day peak 
capacity of natural gas.

Background

    On September 12, 2014, the Commission staff granted AGDC's request 
to use the FERC's Pre-filing environmental review process and assigned 
the Alaska LNG Project Docket No. PF14-21-000. On March 4, 2015, the 
Commission issued a Notice of Intent to Prepare an Environmental Impact 
Statement for the Planned Alaska LNG Project and Request for Comments 
on Environmental Issues (NOI) during the pre-filing review. In October 
2015, FERC issued two supplemental Notices regarding public scoping 
meetings for the Alaska LNG Project. On July 27, 2016, FERC also issued 
a Supplemental Notice Requesting Comments on the Denali National Park 
and Preserve Alternative for the Planned Alaska LNG Project.
    The NOI and supplemental notices were sent to federal, state, and 
local government agencies; elected officials; affected landowners; 
environmental and public interest groups; Native American tribes and 
regional organizations; commentors and other interested parties; and 
local libraries and newspapers. Major issues raised during scoping 
include impacts on traditional Alaska Native culture, particularly 
subsistence; health impacts on local communities; impacts on wetlands, 
including through placement of permanent gravel fill; visual impacts 
from key observation points, including within the Denali National Park 
and Preserve; impacts of dredging and identification of disposal 
methods; wildlife impacts, specifically on the caribou population and 
its migration routes, the endangered Cook Inlet beluga whale 
population, and Cook Inlet fish habitat; and transportation impacts.
    The U.S. Department of Transportation, Pipeline and Hazardous 
Material Safety Administration; U.S. Environmental Protection Agency; 
U.S. Army Corps of Engineers; U.S. Coast Guard; Bureau of Land 
Management; U.S. Fish and Wildlife Service; National Marine Fisheries 
Service; National Park Service; and U.S. Department of Energy are 
cooperating agencies in the preparation of the EIS.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP17-178), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

    Dated: March 12, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-05427 Filed 3-16-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                12002                         Federal Register / Vol. 83, No. 53 / Monday, March 19, 2018 / Notices

                                                of settlement. Likewise, as non-                        Schedule for Environmental Review                     permanent gravel fill; visual impacts
                                                decisional staff, pursuant to 18 CFR                    Issuance of Notice of Availability of the             from key observation points, including
                                                385.2201 (2017), they are prohibited                       final EIS—December 9, 2019                         within the Denali National Park and
                                                from communicating with advisory staff                  90-Day Federal Authorization Decision                 Preserve; impacts of dredging and
                                                concerning any deliberations in this                       Deadline—March 8, 2020                             identification of disposal methods;
                                                docket.                                                                                                       wildlife impacts, specifically on the
                                                                                                           If a schedule change becomes
                                                   Exceptions to this designation as non-                                                                     caribou population and its migration
                                                                                                        necessary for the final EIS, an additional
                                                decisional are:                                                                                               routes, the endangered Cook Inlet
                                                                                                        notice will be provided so that the
                                                Timothy Helwick                                         relevant agencies are kept informed of                beluga whale population, and Cook Inlet
                                                Eric Ciccoretti                                         the Project’s progress.                               fish habitat; and transportation impacts.
                                                Shawn Bennett                                                                                                    The U.S. Department of
                                                Sebastian Krynski                                       Project Description
                                                                                                                                                              Transportation, Pipeline and Hazardous
                                                Jeffrey Phillips                                           AGDC is seeking authorization to                   Material Safety Administration; U.S.
                                                Grace Kwon                                              construct, own, and operate a new gas
                                                Mark Nagel                                                                                                    Environmental Protection Agency; U.S.
                                                                                                        treatment plant near Prudhoe Bay; a 1.0-
                                                                                                                                                              Army Corps of Engineers; U.S. Coast
                                                  Dated: March 13, 2018.                                mile-long, 60-inch-diameter Prudhoe
                                                                                                                                                              Guard; Bureau of Land Management;
                                                Kimberly D. Bose,                                       Bay Unit Gas Transmission Line; a 62.5-
                                                                                                        mile-long, 32-inch-diameter Point                     U.S. Fish and Wildlife Service; National
                                                Secretary.                                                                                                    Marine Fisheries Service; National Park
                                                                                                        Thomson Unit Gas Transmission Line; a
                                                [FR Doc. 2018–05496 Filed 3–16–18; 8:45 am]                                                                   Service; and U.S. Department of Energy
                                                                                                        806.6-mile-long, 42-inch-diameter
                                                BILLING CODE 6717–01–P
                                                                                                        natural gas pipeline from the gas                     are cooperating agencies in the
                                                                                                        treatment plant to the LNG terminal in                preparation of the EIS.
                                                DEPARTMENT OF ENERGY                                    Nikiski; an LNG terminal with a 20                    Additional Information
                                                                                                        million ton per annum liquefaction
                                                Federal Energy Regulatory                               capacity; associated aboveground                         In order to receive notification of the
                                                Commission                                              facilities; and non-jurisdictional                    issuance of the EIS and to keep track of
                                                                                                        facilities in Alaska. The Project would               all formal issuances and submittals in
                                                [Docket No. CP17–178–000]
                                                                                                        have an annual average inlet design                   specific dockets, the Commission offers
                                                                                                        capacity of up to 3.7 billion standard                a free service called eSubscription. This
                                                Notice of Schedule for Environmental                    cubic feet per day and a 3.9 billion                  can reduce the amount of time you
                                                Review of the Alaska Gasline                            standard cubic feet per day peak                      spend researching proceedings by
                                                Development Corporation Alaska LNG                      capacity of natural gas.                              automatically providing you with
                                                Project                                                 Background                                            notification of these filings, document
                                                                                                                                                              summaries, and direct links to the
                                                   On April 17, 2017, the Alaska Gasline                   On September 12, 2014, the
                                                Development Corporation (AGDC) filed                    Commission staff granted AGDC’s                       documents. Go to www.ferc.gov/docs-
                                                an application in Docket No. CP17–178–                  request to use the FERC’s Pre-filing                  filing/esubscription.asp.
                                                000 requesting authorization pursuant                   environmental review process and                         Additional information about the
                                                to section 3(a) of the Natural Gas Act                  assigned the Alaska LNG Project Docket                Project is available from the
                                                (NGA) to construct and operate                          No. PF14–21–000. On March 4, 2015,                    Commission’s Office of External Affairs
                                                liquefied natural gas (LNG) export                      the Commission issued a Notice of                     at (866) 208–FERC or on the FERC
                                                facilities. The proposed project is                     Intent to Prepare an Environmental                    website (www.ferc.gov). Using the
                                                known as the Alaska LNG Project                         Impact Statement for the Planned                      ‘‘eLibrary’’ link, select ‘‘General Search’’
                                                (Project) and would commercialize                       Alaska LNG Project and Request for                    from the eLibrary menu, enter the
                                                natural gas resources on the North Slope                Comments on Environmental Issues                      selected date range and ‘‘Docket
                                                during the economic life of the Prudhoe                 (NOI) during the pre-filing review. In                Number’’ excluding the last three digits
                                                Bay Unit field and provide at least five                October 2015, FERC issued two                         (i.e., CP17–178), and follow the
                                                interconnection points along the                        supplemental Notices regarding public                 instructions. For assistance with access
                                                pipeline to allow for in-state gas                      scoping meetings for the Alaska LNG                   to eLibrary, the helpline can be reached
                                                deliveries.                                             Project. On July 27, 2016, FERC also                  at (866) 208–3676, TTY (202) 502–8659,
                                                   On May 1, 2017, the Federal Energy                   issued a Supplemental Notice                          or at FERCOnlineSupport@ferc.gov. The
                                                Regulatory Commission (FERC or                          Requesting Comments on the Denali
                                                                                                                                                              eLibrary link on the FERC website also
                                                Commission) issued its Notice of                        National Park and Preserve Alternative
                                                                                                                                                              provides access to the texts of formal
                                                Application for the Project. Among                      for the Planned Alaska LNG Project.
                                                other things, that notice alerted other                    The NOI and supplemental notices                   documents issued by the Commission,
                                                agencies issuing federal authorizations                 were sent to federal, state, and local                such as orders, notices, and rule
                                                of the requirement to complete all                      government agencies; elected officials;               makings.
                                                necessary reviews and to reach a final                  affected landowners; environmental and                  Dated: March 12, 2018.
                                                decision on the request for a federal                   public interest groups; Native American               Kimberly D. Bose,
                                                authorization within 90 days of the date                tribes and regional organizations;                    Secretary.
                                                of issuance of the Commission staff’s                   commentors and other interested
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                                                                              [FR Doc. 2018–05427 Filed 3–16–18; 8:45 am]
                                                final Environmental Impact Statement                    parties; and local libraries and
                                                                                                                                                              BILLING CODE 6717–01–P
                                                (EIS) for the Alaska LNG Project. This                  newspapers. Major issues raised during
                                                instant notice identifies the FERC staff’s              scoping include impacts on traditional
                                                planned schedule for completion of the                  Alaska Native culture, particularly
                                                final EIS for the Project, which is based               subsistence; health impacts on local
                                                on an issuance of the draft EIS in March                communities; impacts on wetlands,
                                                2019.                                                   including through placement of


                                           VerDate Sep<11>2014   16:43 Mar 16, 2018   Jkt 244001   PO 00000   Frm 00049   Fmt 4703   Sfmt 9990   E:\FR\FM\19MRN1.SGM   19MRN1



Document Created: 2018-03-17 04:25:03
Document Modified: 2018-03-17 04:25:03
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 12002 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR