The Bureau of Land Management (BLM) announces the availability of the Decision Record (DR) for the Gateway West Transmission Line Project (Project) and Approved Land Use Plan Amendments for Segments 8 and 9. The Assistant Secretary--Land and Minerals Management (ASLM) signed the DR on March 30, 2018, which constitutes the final decision of the Department of the Interior and is not subject to appeal under Departmental regulations. Any challenge to this decision, including the BLM Authorized Officer's issuance of the right- of-way (ROW) as directed by this decision, must be brought in Federal district court within the timeframe allowed under Title 41 of the FAST Act (FAST-41).

Federal Register, Volume 83 Issue 81 (Thursday, April 26, 2018)
[Federal Register Volume 83, Number 81 (Thursday, April 26, 2018)]
[Notices]
[Pages 18342-18343]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-08808]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Land Management

[18XL5017AP.LLWY920000.L51010000.ER0000.LVRWK09K0990; 4500119076]


Notice of Availability of Decision Record for the Gateway West 
Transmission Line Project and Approved Land Use Plan Amendments, 
Segments 8 and 9, Idaho; IDI-35849-01

AGENCY: Bureau of Land Management, Interior.

ACTION: Notice of availability.

-----------------------------------------------------------------------

SUMMARY: The Bureau of Land Management (BLM) announces the availability 
of the Decision Record (DR) for the Gateway West Transmission Line 
Project (Project) and Approved Land Use Plan Amendments for Segments 8 
and 9. The Assistant Secretary--Land and Minerals Management (ASLM) 
signed the DR on March 30, 2018, which constitutes the final decision 
of the Department of the Interior and is not

[[Page 18343]]

subject to appeal under Departmental regulations. Any challenge to this 
decision, including the BLM Authorized Officer's issuance of the right-
of-way (ROW) as directed by this decision, must be brought in Federal 
district court within the timeframe allowed under Title 41 of the FAST 
Act (FAST-41).

DATES: The ASLM signed the DR on March 30, 2018.

ADDRESSES: Copies of the DR are available online at https://www.blm.gov/gatewaywest and at the BLM Idaho State Office, 1387 S 
Vinnell Way, Boise, ID 83709.

FOR FURTHER INFORMATION CONTACT: Jim Stobaugh, BLM Gateway West 
National Project Manager, telephone 775-861-6478; email 
jstobaug@blm.gov. Persons who use a telecommunications device for the 
deaf (TDD) may call the Federal Relay Service (FRS) at 1-800-877-8339 
to leave a message or question for Mr. Stobaugh. The FRS is available 
24 hours a day, 7 days a week. You will receive a reply during normal 
business hours.

SUPPLEMENTARY INFORMATION: 
    On May 7, 2007, PacificCorp (doing business as Rocky Mountain 
Power) and Idaho Power Company (Proponents) applied to the BLM for a 
ROW grant to build and operate portions of the Project on public lands 
in Wyoming and Idaho. The original project comprised 10 transmission 
line segments originating at the Windstar Substation near Glenrock, 
Wyoming, and terminating at the Hemingway Substation near Melba, Idaho, 
with a total length of approximately 1,000 miles. The BLM published a 
Final Environmental Impact Statement (EIS) for this project on April 
26, 2013 and a Record of Decision (ROD) on November 14, 2013. In the 
ROD, the BLM deferred a decision on Segments 8 and 9 to allow 
additional time for Federal, state, and local permitting agencies to 
examine additional routing options, as well as potential mitigation and 
enhancement measures for these segments, in part, because Segments 8 
and 9 involved resources in and near the Morley Nelson Snake River 
Birds of Prey National Conservation Area (NCA).
    In August 2014, the Proponents submitted a revised ROW application 
for Segments 8 and 9 and a revised Plan of Development for the Project, 
which the BLM determined required additional environmental analysis 
through a Supplemental EIS (SEIS). On October 7, 2016, the BLM 
published a Final SEIS that analyzed 7 alternative ROW routes for 
Segments 8 and 9 and the Land Use Plan Amendments needed to accommodate 
each alternative route pair. The BLM issued a ROD on January 19, 2017, 
selecting the route described as Alternative 5 in the Final SEIS. The 
State of Idaho, Owyhee County, Idaho, and three environmental 
organizations appealed the BLM's ROW decision to the Interior Board of 
Land Appeals (IBLA). In a letter to the Secretary of the Interior, the 
Governor of Idaho requested that the BLM reconsider the January 19, 
2017 decision and select an alternative with fewer impacts to State and 
county resources and communities. The Proponents also requested that 
the BLM reconsider the January 2017 decision and select the alternative 
proposed in their revised application, as more cost-effective and 
providing greater system reliability. On April 18, 2017, the IBLA 
granted the BLM's motion to remand the January 19, 2017, ROW decision 
for reconsideration.
    On May 5, 2017, the Morley Nelson Snake River Birds of Prey 
National Conservation Area Boundary Modification Act (Modification Act) 
was enacted, which directed the BLM to issue a ROW grant to use public 
lands within the NCA as described in Sec. (b)(2) representing portions 
of the Project ``in alignment with the revised proposed routes for 
Segments 8 and 9 identified as Alternative 1 in the Supplementary Final 
Environmental Impact Analysis released October 5, 2016.'' The 
Modification Act also removed the lands affected by this ROW from NCA 
status and stipulated that the mitigation framework presented in the 
Final SEIS would apply to the authorized segments. The BLM offered this 
statutory ROW grant to the Proponents on July 26, 2017.
    The BLM has prepared an Environmental Assessment (EA) (DOI-BLM-ID-
0000-0002-EA) to analyze and document the environmental effects of an 
application from the Proponents for a ROW grant to use public lands for 
Segments 8 and 9 of the Project. The EA also analyzed the effects of 
amending three current BLM land use plans needed to ensure the ROW 
grant conformed to the plans:

Kuna Management Framework Plan (MFP);
Bennett Hills/Timmerman Hills MFP; and
1987 Jarbidge Resource Management Plan (for areas not covered by the 
2015 Jarbidge RMP).

    The BLM tiered to and incorporated by reference the analyses in the 
2013 Final EIS and 2016 Final SEIS. The BLM prepared the EA in 
consultation with Cooperating Agencies and in accordance with the 
National Environmental Policy Act of 1969, as amended, the Federal Land 
Policy and Management Act of 1976, as amended, implementing 
regulations, the BLM Land Use Planning Handbook (H-1601-1), the BLM 
National Environmental Policy Act Handbook (H-1790-1), and other 
applicable law and policy.
    Following the publication of a Notice of Intent to prepare an EA in 
the Federal Register, an opportunity for the public to comment on a 
Draft EA, and an opportunity for interested parties and the State of 
Idaho to protest a decision to amend land use plans as reflected in the 
EA and Finding of No New Significant Impact, the ASLM issued a Decision 
selecting Alternative 1 from the EA. The selected alternative 
authorizes a ROW grant to the Proponents for the portions of Segments 8 
and 9 of the project that physically connect with the portions of those 
segments authorized by the Boundary Modification Act. It also includes 
the Toana Road Variation 1 as analyzed in the Final SEIS and amends the 
1987 Jarbidge RMP and the Kuna and Bennett Hills/Timmerman Hills MFPs 
for BLM-managed public lands in the Jarbidge, Four Rivers and Shoshone 
Field Offices.
    The ASLM's DR also incorporated, as terms and conditions of the ROW 
grant, environmental protection measures described in the EA, 
monitoring requirements, and measures to mitigate effects. In addition, 
the BLM has worked with the Proponents to develop the Mitigation 
Framework for the NCA (Final SEIS EIS Appendix K), which the Boundary 
Modification Act also stipulates will apply to the authorized segments.
    My approval of this decision as the ASLM is not subject to 
administrative appeal under Departmental regulations at 43 CFR part 4 
pursuant to 43 CFR 4.410(a)(3). Any challenge to this decision must be 
brought in Federal District Court and is subject to 42 U.S.C. 4370m-
6(a)(1).

    Authority: 40 CFR 1506.6; 42 U.S.C. 4370m-6(a)(1)

Joseph R. Balash,
Assistant Secretary--Land and Minerals Management.
[FR Doc. 2018-08808 Filed 4-25-18; 8:45 am]
 BILLING CODE 4310-AK-P



                                             18342                         Federal Register / Vol. 83, No. 81 / Thursday, April 26, 2018 / Notices

                                             including your personal identifying                     collection requirements and provide the                 Title of Collection: Claim for
                                             information, may be made publicly                       requested data in the desired format.                 Relocation Payments—Residential, DI–
                                             available at any time. While you can ask                   We are soliciting comments on the                  381 and Claim for Relocation
                                             us in your comments to withhold from                    proposed ICR that is described below.                 Payments—Nonresidential, DI–382.
                                             public review your personal identifying                 We are especially interested in public                  OMB Control Number: 1084–0010.
                                             information, we cannot guarantee that                   comment addressing the following                        Form Number: DI–381 and DI–382.
                                             we will be able to do so.                               issues: (1) Is the collection necessary to              Type of Review: Extension of a
                                                                                                     the proper functions of the Office of                 currently approved collection.
                                               Dated: March 27, 2018.
                                                                                                     Acquisition and Property Management;                    Respondents/Affected Public:
                                             Karen P. Clark                                                                                                Individuals and businesses who are
                                                                                                     (2) will this information be processed
                                             Acting Regional Director, Alaska Region.                and used in a timely manner; (3) is the               displaced because of Federal
                                             [FR Doc. 2018–08760 Filed 4–25–18; 8:45 am]             estimate of burden accurate; (4) how                  acquisitions of their real property.
                                             BILLING CODE 4333–15–P                                  might the Office of Acquisition and                     Total Estimated Number of Annual
                                                                                                     Property Management enhance the                       Respondents: 24.
                                                                                                     quality, utility, and clarity of the                    Total Estimated Number of Annual
                                             DEPARTMENT OF THE INTERIOR                              information to be collected; and (5) how              Responses: 24.
                                                                                                     might the Office of Acquisition and                     Estimated Completion Time per
                                             Office of the Secretary                                 Property Management minimize the                      Response: 50 minutes.
                                             [189D0102DM, DLSN00000.000000,                          burden of this collection on the                        Total Estimated Number of Annual
                                             DS62400000, DX62401; OMB Control                        respondents, including through the use                Burden Hours: 20 Hours.
                                             Number 1084–0010]                                       of information technology.                              Respondent’s Obligation: Required to
                                                                                                        Comments that you submit in                        Obtain or Retain a Benefit.
                                             Agency Information Collection                           response to this notice are a matter of                 Frequency of Collection: As needed.
                                             Activities; Claim for Relocation                        public record. We will include or                       Total Estimated Annual Nonhour
                                             Payments—Residential, DI–381 and                        summarize each comment in our request                 Burden Cost: This collection does not
                                             Claim for Relocation Payments—                          to OMB to approve this ICR. Before                    have a nonhour cost burden.
                                             Nonresidential, DI–382                                  including your address, phone number,                   An agency may not conduct or
                                                                                                     email address, or other personal                      sponsor and a person is not required to
                                             AGENCY:  Office of the Secretary, Office
                                                                                                     identifying information in your                       respond to a collection of information
                                             of Acquisition and Property
                                                                                                     comment, you should be aware that                     unless it displays a currently valid OMB
                                             Management, Interior.
                                                                                                     your entire comment—including your                    control number.
                                             ACTION: Notice of Information                                                                                   The authority for this action is the
                                                                                                     personal identifying information—may
                                             Collection; request for comment.                                                                              Paperwork Reduction Act of 1995 (44
                                                                                                     be made publicly available at any time.
                                             SUMMARY:   In accordance with the                       While you can ask us in your comment                  U.S.C. 3501 et seq).
                                             Paperwork Reduction Act of 1995, we,                    to withhold your personal identifying                 Tammy L. Bagley,
                                             the Office of Acquisition and Property                  information from public review, we                    Acting Director, Office of Acquisition and
                                             Management are proposing to renew an                    cannot guarantee that we will be able to              Property Management.
                                             information collection.                                 do so.
                                                                                                                                                           [FR Doc. 2018–08798 Filed 4–25–18; 8:45 am]
                                             DATES: Interested persons are invited to
                                                                                                        Abstract: Public Law 91–646, Uniform
                                                                                                                                                           BILLING CODE 4334–63–P
                                             submit comments on or before June 25,                   Relocation Assistance and Real Property
                                             2018.                                                   Acquisition Policies Act of 1970, as
                                                                                                     amended, requires each Federal agency
                                             ADDRESSES: Send written comments on                                                                           DEPARTMENT OF THE INTERIOR
                                                                                                     acquiring real estate interests to provide
                                             this information collection request (ICR)               relocation benefits to individuals and
                                             by mail to Mary Heying, Department of                                                                         Bureau of Land Management
                                                                                                     businesses displaced as a result of the
                                             the Interior, Office of Acquisition and                 acquisition. Form DI–381, Claim For                   [18XL5017AP.LLWY920000.L51010000.
                                             Property Management, 1849 C St. NW,                     Relocation Payments—Residential, and                  ER0000.LVRWK09K0990; 4500119076]
                                             MS 4262 MIB, Washington, DC 20240,                      DI–382, Claim For Relocation
                                             fax (202) 513–7645 or by email to mary_                                                                       Notice of Availability of Decision
                                                                                                     Payments—Nonresidential, permit the
                                             heying@ios.doi.gov. Please reference                                                                          Record for the Gateway West
                                                                                                     applicant to present allowable moving
                                             OMB Control Number 1084–0010 in the                                                                           Transmission Line Project and
                                                                                                     expenses and certify occupancy status,
                                             subject line of your comments.                                                                                Approved Land Use Plan
                                                                                                     after having been displaced because of
                                             FOR FURTHER INFORMATION CONTACT: To                                                                           Amendments, Segments 8 and 9,
                                                                                                     Federal acquisition of their real
                                             request additional information about                                                                          Idaho; IDI–35849–01
                                                                                                     property.
                                             this ICR, contact Mary Heying by email                     The information required is obtained               AGENCY:   Bureau of Land Management,
                                             at mary_heying@ios.doi.gov, or by                       through application made by the                       Interior.
                                             telephone at 202–513–0722.                              displaced person or business to the                   ACTION: Notice of availability.
                                             SUPPLEMENTARY INFORMATION: In                           funding agency for determination as to
                                             accordance with the Paperwork                           the specific amount of monies due                     SUMMARY:   The Bureau of Land
                                             Reduction Act of 1995, we provide the                   under the law. The forms, through                     Management (BLM) announces the
                                             general public and other Federal                        which application is made, require                    availability of the Decision Record (DR)
                                             agencies with an opportunity to                         specific information since the Uniform                for the Gateway West Transmission Line
amozie on DSK30RV082PROD with NOTICES




                                             comment on new, proposed, revised,                      Relocation Assistance and Real Property               Project (Project) and Approved Land
                                             and continuing collections of                           Acquisition Act allows for various                    Use Plan Amendments for Segments 8
                                             information. This helps us assess the                   amounts based upon each actual                        and 9. The Assistant Secretary—Land
                                             impact of our information collection                    circumstance. Failure to make                         and Minerals Management (ASLM)
                                             requirements and minimize the public’s                  application to the agency would                       signed the DR on March 30, 2018, which
                                             reporting burden. It also helps the                     eliminate any basis for payment of                    constitutes the final decision of the
                                             public understand our information                       claims.                                               Department of the Interior and is not


                                        VerDate Sep<11>2014   16:58 Apr 25, 2018   Jkt 244001   PO 00000   Frm 00081   Fmt 4703   Sfmt 4703   E:\FR\FM\26APN1.SGM   26APN1


                                                                           Federal Register / Vol. 83, No. 81 / Thursday, April 26, 2018 / Notices                                                 18343

                                             subject to appeal under Departmental                    19, 2017, selecting the route described               Handbook (H–1601–1), the BLM
                                             regulations. Any challenge to this                      as Alternative 5 in the Final SEIS. The               National Environmental Policy Act
                                             decision, including the BLM Authorized                  State of Idaho, Owyhee County, Idaho,                 Handbook (H–1790–1), and other
                                             Officer’s issuance of the right-of-way                  and three environmental organizations                 applicable law and policy.
                                             (ROW) as directed by this decision,                     appealed the BLM’s ROW decision to                       Following the publication of a Notice
                                             must be brought in Federal district court               the Interior Board of Land Appeals                    of Intent to prepare an EA in the Federal
                                             within the timeframe allowed under                      (IBLA). In a letter to the Secretary of the           Register, an opportunity for the public
                                             Title 41 of the FAST Act (FAST–41).                     Interior, the Governor of Idaho                       to comment on a Draft EA, and an
                                             DATES: The ASLM signed the DR on                        requested that the BLM reconsider the                 opportunity for interested parties and
                                             March 30, 2018.                                         January 19, 2017 decision and select an               the State of Idaho to protest a decision
                                             ADDRESSES: Copies of the DR are                         alternative with fewer impacts to State               to amend land use plans as reflected in
                                             available online at https://www.blm.gov/                and county resources and communities.                 the EA and Finding of No New
                                             gatewaywest and at the BLM Idaho State                  The Proponents also requested that the                Significant Impact, the ASLM issued a
                                             Office, 1387 S Vinnell Way, Boise, ID                   BLM reconsider the January 2017                       Decision selecting Alternative 1 from
                                             83709.                                                  decision and select the alternative                   the EA. The selected alternative
                                                                                                     proposed in their revised application, as             authorizes a ROW grant to the
                                             FOR FURTHER INFORMATION CONTACT: Jim
                                                                                                     more cost-effective and providing                     Proponents for the portions of Segments
                                             Stobaugh, BLM Gateway West National
                                                                                                     greater system reliability. On April 18,              8 and 9 of the project that physically
                                             Project Manager, telephone 775–861–
                                                                                                     2017, the IBLA granted the BLM’s                      connect with the portions of those
                                             6478; email jstobaug@blm.gov. Persons
                                                                                                     motion to remand the January 19, 2017,                segments authorized by the Boundary
                                             who use a telecommunications device
                                             for the deaf (TDD) may call the Federal                 ROW decision for reconsideration.                     Modification Act. It also includes the
                                             Relay Service (FRS) at 1–800–877–8339                      On May 5, 2017, the Morley Nelson                  Toana Road Variation 1 as analyzed in
                                             to leave a message or question for Mr.                  Snake River Birds of Prey National                    the Final SEIS and amends the 1987
                                             Stobaugh. The FRS is available 24 hours                 Conservation Area Boundary                            Jarbidge RMP and the Kuna and Bennett
                                             a day, 7 days a week. You will receive                  Modification Act (Modification Act) was               Hills/Timmerman Hills MFPs for BLM-
                                             a reply during normal business hours.                   enacted, which directed the BLM to                    managed public lands in the Jarbidge,
                                                                                                     issue a ROW grant to use public lands                 Four Rivers and Shoshone Field Offices.
                                             SUPPLEMENTARY INFORMATION:
                                                                                                     within the NCA as described in Sec.                      The ASLM’s DR also incorporated, as
                                                On May 7, 2007, PacificCorp (doing
                                                                                                     (b)(2) representing portions of the                   terms and conditions of the ROW grant,
                                             business as Rocky Mountain Power) and
                                                                                                     Project ‘‘in alignment with the revised               environmental protection measures
                                             Idaho Power Company (Proponents)
                                             applied to the BLM for a ROW grant to                   proposed routes for Segments 8 and 9                  described in the EA, monitoring
                                             build and operate portions of the Project               identified as Alternative 1 in the                    requirements, and measures to mitigate
                                             on public lands in Wyoming and Idaho.                   Supplementary Final Environmental                     effects. In addition, the BLM has worked
                                             The original project comprised 10                       Impact Analysis released October 5,                   with the Proponents to develop the
                                             transmission line segments originating                  2016.’’ The Modification Act also                     Mitigation Framework for the NCA
                                             at the Windstar Substation near                         removed the lands affected by this ROW                (Final SEIS EIS Appendix K), which the
                                             Glenrock, Wyoming, and terminating at                   from NCA status and stipulated that the               Boundary Modification Act also
                                             the Hemingway Substation near Melba,                    mitigation framework presented in the                 stipulates will apply to the authorized
                                             Idaho, with a total length of                           Final SEIS would apply to the                         segments.
                                             approximately 1,000 miles. The BLM                      authorized segments. The BLM offered                     My approval of this decision as the
                                             published a Final Environmental Impact                  this statutory ROW grant to the                       ASLM is not subject to administrative
                                             Statement (EIS) for this project on April               Proponents on July 26, 2017.                          appeal under Departmental regulations
                                             26, 2013 and a Record of Decision                          The BLM has prepared an                            at 43 CFR part 4 pursuant to 43 CFR
                                             (ROD) on November 14, 2013. In the                      Environmental Assessment (EA) (DOI–                   4.410(a)(3). Any challenge to this
                                             ROD, the BLM deferred a decision on                     BLM–ID–0000–0002–EA) to analyze and                   decision must be brought in Federal
                                             Segments 8 and 9 to allow additional                    document the environmental effects of                 District Court and is subject to 42 U.S.C.
                                             time for Federal, state, and local                      an application from the Proponents for                4370m–6(a)(1).
                                             permitting agencies to examine                          a ROW grant to use public lands for                     Authority: 40 CFR 1506.6; 42 U.S.C.
                                             additional routing options, as well as                  Segments 8 and 9 of the Project. The EA               4370m–6(a)(1)
                                             potential mitigation and enhancement                    also analyzed the effects of amending
                                                                                                     three current BLM land use plans                      Joseph R. Balash,
                                             measures for these segments, in part,                                                                         Assistant Secretary—Land and Minerals
                                             because Segments 8 and 9 involved                       needed to ensure the ROW grant
                                                                                                     conformed to the plans:                               Management.
                                             resources in and near the Morley Nelson                                                                       [FR Doc. 2018–08808 Filed 4–25–18; 8:45 am]
                                             Snake River Birds of Prey National                      Kuna Management Framework Plan (MFP);
                                                                                                                                                           BILLING CODE 4310–AK–P
                                             Conservation Area (NCA).                                Bennett Hills/Timmerman Hills MFP; and
                                                In August 2014, the Proponents                       1987 Jarbidge Resource Management Plan
                                             submitted a revised ROW application                       (for areas not covered by the 2015 Jarbidge
                                                                                                       RMP).                                               DEPARTMENT OF THE INTERIOR
                                             for Segments 8 and 9 and a revised Plan
                                             of Development for the Project, which                     The BLM tiered to and incorporated                  Bureau of Land Management
                                             the BLM determined required additional                  by reference the analyses in the 2013
                                             environmental analysis through a                        Final EIS and 2016 Final SEIS. The BLM                [18X.LLAK930100.L16100000.PN0000]
amozie on DSK30RV082PROD with NOTICES




                                             Supplemental EIS (SEIS). On October 7,                  prepared the EA in consultation with                  Notice of Intent To Prepare an
                                             2016, the BLM published a Final SEIS                    Cooperating Agencies and in accordance                Environmental Impact Statement for
                                             that analyzed 7 alternative ROW routes                  with the National Environmental Policy                the Coastal Plain Oil and Gas Leasing
                                             for Segments 8 and 9 and the Land Use                   Act of 1969, as amended, the Federal                  Program, Alaska; Correction
                                             Plan Amendments needed to                               Land Policy and Management Act of
                                             accommodate each alternative route                      1976, as amended, implementing                        AGENCY:     Bureau of Land Management,
                                             pair. The BLM issued a ROD on January                   regulations, the BLM Land Use Planning                Interior.


                                        VerDate Sep<11>2014   16:58 Apr 25, 2018   Jkt 244001   PO 00000   Frm 00082   Fmt 4703   Sfmt 4703   E:\FR\FM\26APN1.SGM   26APN1



Document Created: 2018-11-02 08:19:37
Document Modified: 2018-11-02 08:19:37
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability.
DatesThe ASLM signed the DR on March 30, 2018.
ContactJim Stobaugh, BLM Gateway West National Project Manager, telephone 775-861-6478; email [email protected] Persons who use a telecommunications device for the deaf (TDD) may call the Federal Relay Service (FRS) at 1-800-877-8339 to leave a message or question for Mr. Stobaugh. The FRS is available 24 hours a day, 7 days a week. You will receive a reply during normal business hours.