83_FR_20897 83 FR 20808 - Portland Natural Gas Transmission System; Notice of Application

83 FR 20808 - Portland Natural Gas Transmission System; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 89 (May 8, 2018)

Page Range20808-20808
FR Document2018-09713

Federal Register, Volume 83 Issue 89 (Tuesday, May 8, 2018)
[Federal Register Volume 83, Number 89 (Tuesday, May 8, 2018)]
[Notices]
[Page 20808]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-09713]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-251-000]


Portland Natural Gas Transmission System; Notice of Application

    Take notice that on April 20, 2018, Portland Natural Gas 
Transmission System (Portland Natural Gas), 700 Louisiana Street, Suite 
700, Houston, TX 77002-2700, filed an application under section 7(c) of 
the Natural Gas Act (NGA) and Parts 157 and 284 of the Commission's 
rules and regulations for Phase I of the Portland Xpress Project. 
Portland Natural Gas requests authorization to increase the 
certificated capacity on its wholly-owned north system from Pittsburg, 
New Hampshire, to Westbrook, Maine, by 39.841 million cubic feet per 
day (MMcf/d), and to increase the certificated capacity on its system 
facilities jointly-owned with Maritimes & Northeast Pipeline, L.L.C. 
from Westbrook, Maine to Dracut, Massachusetts by 1.641 MMcf/d, 
effective November 1, 2018, all as more fully described in the 
application which is on file with the Commission and open to public 
inspection. The filing may also be viewed on the web at http://www.ferc.gov using the eLibrary link. Enter the docket number excluding 
the last three digits in the docket number field to access the 
document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or 
call toll-free, (866) 208-3676 or TTY, (202) 502-8659.
    Additionally, pursuant to section 3 of the NGA (15 U.S.C. 717b), 
Part 153 of the Commission's regulations, Executive Order 10485, as 
amended by Executive Order 12038, and Secretary of Energy Delegation 
Order No. 0204-112, Portland Natural Gas requests authorization to 
increase its import and export capacity from 210 MMcf/d to 274.216 
MMcf/d. Portland Natural Gas also proposes to amend its Presidential 
Permit issued on September 24, 1997, as amended on November 18, 2003, 
and on November 28, 2017, to reflect the increase mentioned above.\1\
---------------------------------------------------------------------------

    \1\ See Portland Natural Gas Transmission System, 80 FERC 61,346 
(1997); 105 FERC 61,235 (2003); and 161 FERC 61,230 (2017).
---------------------------------------------------------------------------

    Portland Natural Gas states that it's Phase I of the Portland 
XPress Project would expand gas service delivery options for the New 
England market. Portland Natural Gas proposes no construction or 
modifications to its existing system or border crossing facilities in 
connection with this request, and as such, there are no costs 
associated with the project.
    Any questions regarding this application should be directed to 
Robert Jackson, Manager, Certificates & Regulatory Administration, 
Portland Natural Gas Transmission System, 700 Louisiana Street, Suite 
700, Houston, Texas 77002-2700, or call (832) 320-5487, or email: 
robert_jackson@transcanada.com.
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice, the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 7 copies of filings made in the proceeding with the Commission 
and must mail a copy to the applicant and to every other party. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on May 23, 2018

    Dated: May 2, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-09713 Filed 5-7-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                20808                           Federal Register / Vol. 83, No. 89 / Tuesday, May 8, 2018 / Notices

                                                  Dated: May 2, 2018.                                      Portland Natural Gas states that it’s              proceeding can ask for court review of
                                                Kimberly D. Bose,                                       Phase I of the Portland XPress Project                Commission orders in the proceeding.
                                                Secretary.                                              would expand gas service delivery                        However, a person does not have to
                                                [FR Doc. 2018–09714 Filed 5–7–18; 8:45 am]              options for the New England market.                   intervene in order to have comments
                                                BILLING CODE 6717–01–P                                  Portland Natural Gas proposes no                      considered. The second way to
                                                                                                        construction or modifications to its
                                                                                                                                                              participate is by filing with the
                                                                                                        existing system or border crossing
                                                                                                                                                              Secretary of the Commission, as soon as
                                                DEPARTMENT OF ENERGY                                    facilities in connection with this
                                                                                                        request, and as such, there are no costs              possible, an original and two copies of
                                                Federal Energy Regulatory                               associated with the project.                          comments in support of or in opposition
                                                Commission                                                 Any questions regarding this                       to this project. The Commission will
                                                                                                        application should be directed to Robert              consider these comments in
                                                [Docket No. CP18–251–000]                               Jackson, Manager, Certificates &                      determining the appropriate action to be
                                                                                                        Regulatory Administration, Portland                   taken, but the filing of a comment alone
                                                Portland Natural Gas Transmission                       Natural Gas Transmission System, 700                  will not serve to make the filer a party
                                                System; Notice of Application                           Louisiana Street, Suite 700, Houston,                 to the proceeding. The Commission’s
                                                                                                        Texas 77002–2700, or call (832) 320–                  rules require that persons filing
                                                   Take notice that on April 20, 2018,                                                                        comments in opposition to the project
                                                Portland Natural Gas Transmission                       5487, or email: robert_jackson@
                                                                                                        transcanada.com.                                      provide copies of their protests only to
                                                System (Portland Natural Gas), 700
                                                                                                           Pursuant to section 157.9 of the                   the party or parties directly involved in
                                                Louisiana Street, Suite 700, Houston,
                                                                                                        Commission’s rules (18 CFR 157.9),                    the protest.
                                                TX 77002–2700, filed an application
                                                under section 7(c) of the Natural Gas                   within 90 days of this Notice, the                       Persons who wish to comment only
                                                Act (NGA) and Parts 157 and 284 of the                  Commission staff will either: Complete                on the environmental review of this
                                                Commission’s rules and regulations for                  its environmental assessment (EA) and                 project should submit an original and
                                                Phase I of the Portland Xpress Project.                 place it into the Commission’s public                 two copies of their comments to the
                                                Portland Natural Gas requests                           record (eLibrary) for this proceeding; or             Secretary of the Commission.
                                                authorization to increase the certificated              issue a Notice of Schedule for                        Environmental commentors will be
                                                capacity on its wholly-owned north                      Environmental Review. If a Notice of
                                                                                                                                                              placed on the Commission’s
                                                system from Pittsburg, New Hampshire,                   Schedule for Environmental Review is
                                                                                                                                                              environmental mailing list, will receive
                                                to Westbrook, Maine, by 39.841 million                  issued, it will indicate, among other
                                                                                                                                                              copies of the environmental documents,
                                                cubic feet per day (MMcf/d), and to                     milestones, the anticipated date for the
                                                                                                        Commission staff’s issuance of the final              and will be notified of meetings
                                                increase the certificated capacity on its                                                                     associated with the Commission’s
                                                system facilities jointly-owned with                    environmental impact statement (FEIS)
                                                                                                        or EA for this proposal. The filing of the            environmental review process.
                                                Maritimes & Northeast Pipeline, L.L.C.                                                                        Environmental commentors will not be
                                                from Westbrook, Maine to Dracut,                        EA in the Commission’s public record
                                                                                                        for this proceeding or the issuance of a              required to serve copies of filed
                                                Massachusetts by 1.641 MMcf/d,                                                                                documents on all other parties.
                                                effective November 1, 2018, all as more                 Notice of Schedule for Environmental
                                                                                                        Review will serve to notify federal and               However, the non-party commentors
                                                fully described in the application which
                                                                                                        state agencies of the timing for the                  will not receive copies of all documents
                                                is on file with the Commission and open
                                                                                                        completion of all necessary reviews, and              filed by other parties or issued by the
                                                to public inspection. The filing may also
                                                be viewed on the web at http://                         the subsequent need to complete all                   Commission (except for the mailing of
                                                www.ferc.gov using the eLibrary link.                   federal authorizations within 90 days of              environmental documents issued by the
                                                Enter the docket number excluding the                   the date of issuance of the Commission                Commission) and will not have the right
                                                last three digits in the docket number                  staff’s FEIS or EA.                                   to seek court review of the
                                                field to access the document. For                          There are two ways to become                       Commission’s final order.
                                                assistance, contact FERC at                             involved in the Commission’s review of                   The Commission strongly encourages
                                                FERCOnlineSupport@ferc.gov or call                      this project. First, any person wishing to            electronic filings of comments, protests
                                                toll-free, (866) 208–3676 or TTY, (202)                 obtain legal status by becoming a party               and interventions in lieu of paper using
                                                502–8659.                                               to the proceedings for this project
                                                                                                                                                              the eFiling link at http://www.ferc.gov.
                                                   Additionally, pursuant to section 3 of               should, on or before the comment date
                                                                                                                                                              Persons unable to file electronically
                                                the NGA (15 U.S.C. 717b), Part 153 of                   stated below file with the Federal
                                                                                                        Energy Regulatory Commission, 888                     should submit an original and 5 copies
                                                the Commission’s regulations, Executive                                                                       of the protest or intervention to the
                                                Order 10485, as amended by Executive                    First Street NE, Washington, DC 20426,
                                                                                                        a motion to intervene in accordance                   Federal Energy regulatory Commission,
                                                Order 12038, and Secretary of Energy                                                                          888 First Street NE, Washington, DC
                                                Delegation Order No. 0204–112,                          with the requirements of the
                                                                                                        Commission’s Rules of Practice and                    20426.
                                                Portland Natural Gas requests
                                                authorization to increase its import and                Procedure (18 CFR 385.214 or 385.211)                    Comment Date: 5:00 p.m. Eastern
                                                export capacity from 210 MMcf/d to                      and the Regulations under the NGA (18                 Time on May 23, 2018
                                                274.216 MMcf/d. Portland Natural Gas                    CFR 157.10). A person obtaining party
                                                                                                                                                                Dated: May 2, 2018.
                                                also proposes to amend its Presidential                 status will be placed on the service list
                                                                                                        maintained by the Secretary of the                    Kimberly D. Bose,
sradovich on DSK3GMQ082PROD with NOTICES




                                                Permit issued on September 24, 1997, as
                                                                                                        Commission and will receive copies of                 Secretary.
                                                amended on November 18, 2003, and on
                                                November 28, 2017, to reflect the                       all documents filed by the applicant and              [FR Doc. 2018–09713 Filed 5–7–18; 8:45 am]
                                                increase mentioned above.1                              by all other parties. A party must submit             BILLING CODE 6717–01–P
                                                                                                        7 copies of filings made in the
                                                  1 See Portland Natural Gas Transmission System,       proceeding with the Commission and
                                                80 FERC 61,346 (1997); 105 FERC 61,235 (2003);          must mail a copy to the applicant and
                                                and 161 FERC 61,230 (2017).                             to every other party. Only parties to the


                                           VerDate Sep<11>2014   18:41 May 07, 2018   Jkt 244001   PO 00000   Frm 00022   Fmt 4703   Sfmt 9990   E:\FR\FM\08MYN1.SGM   08MYN1



Document Created: 2018-05-08 01:31:27
Document Modified: 2018-05-08 01:31:27
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on May 23, 2018
FR Citation83 FR 20808 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR