Matador Power Marketing, Inc. (Matador or Applicant) has applied for authority to transmit electric energy from the United States to Mexico pursuant to the Federal Power Act.

Federal Register, Volume 83 Issue 97 (Friday, May 18, 2018)
[Federal Register Volume 83, Number 97 (Friday, May 18, 2018)]
[Notices]
[Pages 23271-23272]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-10642]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

[OE Docket No. EA-452]


Application To Export Electric Energy; Matador Power Marketing, 
Inc.

AGENCY: Office of Electricity Delivery and Energy Reliability, DOE.

ACTION: Notice of application.

-----------------------------------------------------------------------

SUMMARY: Matador Power Marketing, Inc. (Matador or Applicant) has 
applied for authority to transmit electric energy from the United 
States to Mexico pursuant to the Federal Power Act.

DATES: Comments, protests, or motions to intervene must be submitted on 
or before June 18, 2018.

ADDRESSES: Comments, protests, motions to intervene, or requests for 
more information should be addressed to: Office of Electricity Delivery 
and Energy Reliability, Mail Code: OE-20, U.S. Department of Energy, 
1000 Independence Avenue SW, Washington, DC 20585-0350. Because of 
delays in handling conventional mail, it is recommended that documents 
be transmitted by overnight mail, by electronic mail to 
Electricity.Exports@hq.doe.gov, or by facsimile to 202-586-8008.

SUPPLEMENTARY INFORMATION: Exports of electricity from the United 
States to a foreign country are regulated by the Department of Energy 
(DOE) pursuant to sections 301(b) and 402(f) of the Department of 
Energy Organization Act (42 U.S.C. 7151(b), 7172(f)) and require 
authorization under section 202(e) of the Federal Power Act (16 U.S.C. 
824a(e)).
    On May 1, 2018, DOE received an application from Matador for 
authority to transmit electric energy from the United States to Mexico 
as a power marketer for a five-year term using existing international 
transmission facilities.
    In its application, Matador states that it does not own or control 
any electric generation or transmission facilities, and it does not 
have a franchised service area. The electric energy that the Applicant 
proposes to export to Mexico would be surplus energy purchased from 
third parties such as electric utilities and Federal power marketing 
agencies pursuant to voluntary

[[Page 23272]]

agreements. The existing international transmission facilities to be 
utilized by the Applicant have previously been authorized by 
Presidential Permits issued pursuant to Executive Order 10485, as 
amended, and are appropriate for open access transmission by third 
parties.
    Procedural Matters: Any person desiring to be heard in this 
proceeding should file a comment or protest to the application at the 
address provided above. Protests should be filed in accordance with 
Rule 211 of the Federal Energy Regulatory Commission's (FERC) Rules of 
Practice and Procedures (18 CFR 385.211). Any person desiring to become 
a party to these proceedings should file a motion to intervene at the 
above address in accordance with FERC Rule 214 (18 CFR 385.214). Five 
copies of such comments, protests, or motions to intervene should be 
sent to the address provided above on or before the date listed above.
    Comments and other filings concerning Matador's application to 
export electric energy to Mexico should be clearly marked with OE 
Docket No. EA-452. An additional copy is to be provided to both Ruta 
Kalvaitis Sku[ccaron]as, Pierce Atwood LLC, 1875 K St. NW, Suite 700, 
Washington, DC 20006 and Diana Stoica, Matador Power Marketing, Inc., 
523 Soudan Avenue, Toronto, ON M4S 1X1.
    A final decision will be made on this application after the 
environmental impacts have been evaluated pursuant to DOE's National 
Environmental Policy Act Implementing Procedures (10 CFR part 1021) and 
after a determination is made by DOE that the proposed action will not 
have an adverse impact on the sufficiency of supply or reliability of 
the U.S. electric power supply system.
    Copies of this application will be made available, upon request, 
for public inspection and copying at the address provided above, by 
accessing the program website at http://energy.gov/node/11845, or by 
emailing Angela Troy at Angela.Troy@hq.doe.gov.

    Issued in Washington, DC, on May 10, 2018.
Christopher Lawrence,
Electricity Policy Analyst, Office of Electricity Delivery and Energy 
Reliability.
[FR Doc. 2018-10642 Filed 5-17-18; 8:45 am]
 BILLING CODE 6450-01-P



                                                                                 Federal Register / Vol. 83, No. 97 / Friday, May 18, 2018 / Notices                                                 23271

                                               contained no decisions regarding the                    13,000-square-meters (140,000-square-                   Issued in Washington, DC, on May 14,
                                               interim storage, treatment, or final                    feet) of ground. They also included the               2018.
                                               disposition of the capsules or their                    operational impacts from retrieval of the             Anne Marie White,
                                               contents.2 Accordingly, the capsules                    capsules from WESF and their                          Assistant Secretary for Environmental
                                               continue to be stored in WESF.                          placement into containers; transfer of                Management.
                                                                                                       the containers to the new storage                     [FR Doc. 2018–10643 Filed 5–17–18; 8:45 am]
                                               Events Since Issuance of the First
                                               Record of Decision                                      facility; and maintaining and                         BILLING CODE 6450–01–P
                                                                                                       monitoring of the facility for up to 145
                                                  Since issuance of the ROD,
                                               completion of the Waste Treatment                       years (the maximum storage time under
                                                                                                       all of the Tank Closure Alternatives                  DEPARTMENT OF ENERGY
                                               Project has been delayed and WESF is
                                               experiencing degradation of key                         analyzed in the TC & WM EIS). The                     [OE Docket No. EA–452]
                                               structures and safety systems, including                potential impacts from deactivation of
                                                                                                       the dry storage facility included those               Application To Export Electric Energy;
                                               the concrete walls of the storage pool
                                                                                                       resulting from putting the facility into a            Matador Power Marketing, Inc.
                                               due to gamma radiation emitted by the
                                               capsules. The degradation of WESF has                   stable configuration after removal of the             AGENCY: Office of Electricity Delivery
                                               increased the risk that a beyond design                 capsules for treatment, disposition, or               and Energy Reliability, DOE.
                                               basis natural event (e.g. an earthquake)                both.                                                 ACTION: Notice of application.
                                               could cause the walls to fail, resulting                   The capsules would be transported
                                               in loss of the water that provides                      and stored in casks similar to the casks              SUMMARY:    Matador Power Marketing,
                                               shielding of the capsules. Due to this                  analyzed in the TC&WM EIS; they                       Inc. (Matador or Applicant) has applied
                                               concern and the realization that the                    would be passively ventilated to                      for authority to transmit electric energy
                                               capsules would likely need to stay in                                                                         from the United States to Mexico
                                                                                                       dissipate heat produced by radioactive
                                               WESF for a period longer than its design                                                                      pursuant to the Federal Power Act.
                                                                                                       decay within the capsules. The current
                                               life, DOE has concluded that interim dry                                                                      DATES: Comments, protests, or motions
                                               storage of the capsules in a new facility               design of the dry storage facility, which
                                                                                                       would be located approximately 400                    to intervene must be submitted on or
                                               would significantly reduce the potential                                                                      before June 18, 2018.
                                               risk of onsite radiological exposures and               meters (440 yards) from the existing
                                                                                                       WESF, calls for a storage pad of 753                  ADDRESSES: Comments, protests,
                                               airborne releases from a failure of                                                                           motions to intervene, or requests for
                                               WESF.                                                   square meters (8,100 square feet) within
                                                                                                       the facility on which the casks would be              more information should be addressed
                                               Preferred Alternative for Interim                       placed. The new facility would be a                   to: Office of Electricity Delivery and
                                               Storage of the Capsules                                                                                       Energy Reliability, Mail Code: OE–20,
                                                                                                       ‘‘dangerous waste management unit’’
                                                  Because of the delays in completing                                                                        U.S. Department of Energy, 1000
                                                                                                       under the Hanford Facility Resource
                                               the Waste Treatment Plant and the                                                                             Independence Avenue SW, Washington,
                                                                                                       Conservation and Recovery Act (RCRA)
                                               ongoing degradation of WESF, DOE has                                                                          DC 20585–0350. Because of delays in
                                                                                                       Permit; it would be added to the permit               handling conventional mail, it is
                                               now concluded that its preferred                        through a modification issued by the
                                               alternative for interim storage of the                                                                        recommended that documents be
                                                                                                       state of Washington pursuant to its                   transmitted by overnight mail, by
                                               capsules is in a new dry storage facility.              delegated RCRA authority.
                                               This is also the environmentally                                                                              electronic mail to Electricity.Exports@
                                               preferred alternative for interim storage                  The potential environmental impacts                hq.doe.gov, or by facsimile to 202–586–
                                               of the capsules as it would reduce the                  from interim dry storage of the capsules              8008.
                                               risks posed by a failure of WESF.                       would be less than those identified in                SUPPLEMENTARY INFORMATION: Exports of
                                                                                                       the TC&WM EIS for this alternative,                   electricity from the United States to a
                                               Decision                                                primarily due to the decay of                         foreign country are regulated by the
                                                 DOE evaluated the transfer of the                     radioactivity in the capsules. In June                Department of Energy (DOE) pursuant to
                                               cesium and strontium capsules from                      2017, DOE estimated that the                          sections 301(b) and 402(f) of the
                                               WESF to dry storage in Appendix E of                    radioactivity in the capsules had                     Department of Energy Organization Act
                                               the final TC&WM EIS (Section E                          decayed to 46 million curies; the final               (42 U.S.C. 7151(b), 7172(f)) and require
                                               1.2.3.4.5.) in response to comments from                TC&WM EIS assumed the capsules                        authorization under section 202(e) of
                                               the state of Oregon’s Department of                     contained about 68 million curies.                    the Federal Power Act (16 U.S.C.
                                               Energy and the Yakama Nation (Final                                                                           824a(e)).
                                                                                                          DOE’s decision is to continue interim                 On May 1, 2018, DOE received an
                                               TC&WM EIS at 3–29 to 3–30 and 3–437
                                               to 3–440). This evaluation identified the               storage of the capsules, but in a new dry             application from Matador for authority
                                               potential impacts from construction and                 storage facility rather than in WESF.                 to transmit electric energy from the
                                               operation of a new dry storage facility                 DOE is not making any decisions at this               United States to Mexico as a power
                                               in the 200-East Area of Hanford, which                  time on treatment or final disposition of             marketer for a five-year term using
                                               would be deactivated upon final                         the cesium and strontium capsules.                    existing international transmission
                                               disposition of the capsules. These                      Mitigation Measures                                   facilities.
                                               impacts included those from the                                                                                  In its application, Matador states that
                                               construction of an approximately 6,500-                    Moving the capsules from WESF to a                 it does not own or control any electric
                                               square-meter (70,000-square-feet) dry                   dry storage facility will mitigate                    generation or transmission facilities,
daltland on DSKBBV9HB2PROD with NOTICES




                                               storage facility and disturbance of                     potential impacts resulting from a                    and it does not have a franchised service
                                                                                                       potential failure of WESF. This decision              area. The electric energy that the
                                                  2 The first ROD noted that it ‘‘is the first in a
                                                                                                       will allow DOE to eliminate the                       Applicant proposes to export to Mexico
                                               series of RODs that DOE intends to issue pursuant                                                             would be surplus energy purchased
                                               to the Final TC&WM EIS.’’ (78 FR 75918.) It also        potential for releases to groundwater
                                               stated that DOE was ‘‘not deciding on treatment of      and the atmosphere from a structural                  from third parties such as electric
                                               the cesium and strontium capsules in this ROD.’’        failure of WESF.                                      utilities and Federal power marketing
                                               (Id.)                                                                                                         agencies pursuant to voluntary


                                          VerDate Sep<11>2014   16:38 May 17, 2018   Jkt 244001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\18MYN1.SGM   18MYN1


                                               23272                            Federal Register / Vol. 83, No. 97 / Friday, May 18, 2018 / Notices

                                               agreements. The existing international                  DEPARTMENT OF ENERGY                                     Applicants: Midcontinent
                                               transmission facilities to be utilized by                                                                     Independent System Operator, Inc.
                                               the Applicant have previously been                      Federal Energy Regulatory                                Description: § 205(d) Rate Filing:
                                               authorized by Presidential Permits                      Commission                                            2018–05–14_SA 3114 Walnut Bend
                                               issued pursuant to Executive Order                                                                            Solar-EAI GIA (J552) to be effective 4/
                                                                                                       Combined Notice of Filings #1                         30/2018.
                                               10485, as amended, and are appropriate
                                               for open access transmission by third                      Take notice that the Commission                       Filed Date: 5/14/18.
                                               parties.                                                received the following exempt                            Accession Number: 20180514–6017.
                                                                                                       wholesale generator filings:                             Comments Due: 5 p.m. ET 6/4/18.
                                                  Procedural Matters: Any person
                                                                                                          Docket Numbers: EG18–87–000.                          Docket Numbers: ER18–1587–000.
                                               desiring to be heard in this proceeding
                                                                                                          Applicants: Pratt Wind, LLC.                          Applicants: Tyr Energy, LLC.
                                               should file a comment or protest to the                                                                          Description: § 205(d) Rate Filing:
                                               application at the address provided                        Description: Notice of Self-
                                                                                                       Certification of Exempt Wholesale                     Market-Based Rate Tariff Revisions to be
                                               above. Protests should be filed in                                                                            effective 5/15/2018.
                                               accordance with Rule 211 of the Federal                 Generator Status of Pratt Wind, LLC.
                                                                                                          Filed Date: 5/14/18.                                  Filed Date: 5/14/18.
                                               Energy Regulatory Commission’s (FERC)                                                                            Accession Number: 20180514–6022.
                                                                                                          Accession Number: 20180514–5991.
                                               Rules of Practice and Procedures (18                                                                             Comments Due: 5 p.m. ET 6/4/18.
                                                                                                          Comments Due: 5 p.m. ET 6/4/18.
                                               CFR 385.211). Any person desiring to                                                                             Docket Numbers: ER18–1589–000.
                                               become a party to these proceedings                        Docket Numbers: EG18–88–000.
                                                                                                          Applicants: Stoneray Power Partners,                  Applicants: Monongahela Power
                                               should file a motion to intervene at the                                                                      Company, PJM Interconnection, L.L.C.
                                                                                                       LLC.
                                               above address in accordance with FERC                                                                            Description: § 205(d) Rate Filing:
                                                                                                          Description: Notice of Self-
                                               Rule 214 (18 CFR 385.214). Five copies                  Certification of Exempt Wholesale                     Monongahela Power Company submits
                                               of such comments, protests, or motions                  Generator Status of Stoneray Power                    OIA SA No. 4717 to be effective 7/13/
                                               to intervene should be sent to the                      Partners, LLC.                                        2018.
                                               address provided above on or before the                    Filed Date: 5/14/18.                                  Filed Date: 5/14/18.
                                               date listed above.                                         Accession Number: 20180514–6023.                      Accession Number: 20180514–6041.
                                                  Comments and other filings                              Comments Due: 5 p.m. ET 6/4/18.                       Comments Due: 5 p.m. ET 6/4/18.
                                               concerning Matador’s application to                        Docket Numbers: EG18–89–000.                          Docket Numbers: ER18–1590–000.
                                               export electric energy to Mexico should                    Applicants: Copenhagen Wind Farm,                     Applicants: Southwest Power Pool,
                                               be clearly marked with OE Docket No.                    LLC.                                                  Inc.
                                               EA–452. An additional copy is to be                        Description: Notice of Self-                          Description: § 205(d) Rate Filing:
                                               provided to both Ruta Kalvaitis Skučas,                Certification of Exempt Wholesale                     Revisions to Extend Tariff
                                               Pierce Atwood LLC, 1875 K St. NW,                       Generator Status of Copenhagen Wind                   Administration between SPP and SPA
                                               Suite 700, Washington, DC 20006 and                     Farm, LLC.                                            through 07/31/2018 to be effective 4/1/
                                                                                                          Filed Date: 5/14/18.                               2018.
                                               Diana Stoica, Matador Power Marketing,
                                                                                                          Accession Number: 20180514–6033.                      Filed Date: 5/14/18.
                                               Inc., 523 Soudan Avenue, Toronto, ON
                                                                                                          Comments Due: 5 p.m. ET 6/4/18.                       Accession Number: 20180514–6042.
                                               M4S 1X1.                                                                                                         Comments Due: 5 p.m. ET 6/4/18.
                                                                                                          Take notice that the Commission
                                                  A final decision will be made on this                received the following electric rate                     Docket Numbers: ER18–1592–000.
                                               application after the environmental                     filings:                                                 Applicants: West Penn Power
                                               impacts have been evaluated pursuant                                                                          Company, PJM Interconnection, L.L.C.
                                                                                                          Docket Numbers: ER18–1581–000.
                                               to DOE’s National Environmental Policy                     Applicants: Tucson Electric Power                     Description: § 205(d) Rate Filing: West
                                               Act Implementing Procedures (10 CFR                     Company.                                              Penn Power Company submits OIA SA
                                               part 1021) and after a determination is                    Description: Compliance filing: Order              No. 4976 to be effective 7/13/2018.
                                               made by DOE that the proposed action                    No. 842 Compliance Filing to be                          Filed Date: 5/14/18.
                                               will not have an adverse impact on the                  effective 5/15/2018.                                     Accession Number: 20180514–6046.
                                               sufficiency of supply or reliability of the                Filed Date: 5/14/18.                                  Comments Due: 5 p.m. ET 6/4/18.
                                               U.S. electric power supply system.                         Accession Number: 20180514–5011.                      Docket Numbers: ER18–1593–000.
                                                  Copies of this application will be                      Comments Due: 5 p.m. ET 6/4/18.                       Applicants: Avista Corporation.
                                               made available, upon request, for public                   Docket Numbers: ER18–1582–000.                        Description: Compliance filing: Avista
                                               inspection and copying at the address                      Applicants: UNS Electric, Inc.                     Corp OATT Order 842 Compliance
                                               provided above, by accessing the                           Description: Compliance filing: Order              Filing to be effective 5/15/2018.
                                               program website at http://energy.gov/                   No. 842 Compliance Filing to be                          Filed Date: 5/14/18.
                                               node/11845, or by emailing Angela Troy                  effective 5/15/2018.                                     Accession Number: 20180514–6049.
                                               at Angela.Troy@hq.doe.gov.                                 Filed Date: 5/14/18.                                  Comments Due: 5 p.m. ET 6/4/18.
                                                                                                          Accession Number: 20180514–5012.                      Docket Numbers: ER18–1594–000.
                                                 Issued in Washington, DC, on May 10,                     Comments Due: 5 p.m. ET 6/4/18.                       Applicants: Public Service Company
                                               2018.
                                                                                                          Docket Numbers: ER18–1584–000.                     of Colorado.
                                               Christopher Lawrence,                                      Applicants: Mississippi Power                         Description: Compliance filing:
                                               Electricity Policy Analyst, Office of Electricity       Company.                                              OATT—Order No. 842 Compliance—
daltland on DSKBBV9HB2PROD with NOTICES




                                               Delivery and Energy Reliability.                           Description: Request for Waiver of                 LGIP–SGIP to be effective 5/15/2018.
                                               [FR Doc. 2018–10642 Filed 5–17–18; 8:45 am]             MRA Cost Based Tariff Volume No. 1 for                   Filed Date: 5/14/18.
                                               BILLING CODE 6450–01–P                                  Period I of Mississippi Power Company.                   Accession Number: 20180514–6069.
                                                                                                          Filed Date: 5/14/18.                                  Comments Due: 5 p.m. ET 6/4/18.
                                                                                                          Accession Number: 20180514–5999.                      Docket Numbers: ER18–1597–000.
                                                                                                          Comments Due: 5 p.m. ET 6/4/18.                       Applicants: PJM Interconnection,
                                                                                                          Docket Numbers: ER18–1586–000.                     L.L.C.


                                          VerDate Sep<11>2014   16:38 May 17, 2018   Jkt 244001   PO 00000   Frm 00021   Fmt 4703   Sfmt 4703   E:\FR\FM\18MYN1.SGM   18MYN1



Document Created: 2018-05-18 02:15:48
Document Modified: 2018-05-18 02:15:48
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of application.
DatesComments, protests, or motions to intervene must be submitted on or before June 18, 2018.