83_FR_23825 83 FR 23726 - Florida Power & Light Company: Turkey Point Nuclear Plant Units 3 and 4

83 FR 23726 - Florida Power & Light Company: Turkey Point Nuclear Plant Units 3 and 4

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 83, Issue 99 (May 22, 2018)

Page Range23726-23728
FR Document2018-10806

The U.S. Nuclear Regulatory Commission will conduct a scoping process to gather information necessary to prepare an environmental impact statement (EIS) to evaluate the environmental impacts for the subsequent license renewal of the operating licenses for Turkey Point Nuclear Plant (Turkey Point) Unit Nos. 3 and 4. The NRC is seeking stakeholder input on this action and has scheduled a public meeting.

Federal Register, Volume 83 Issue 99 (Tuesday, May 22, 2018)
[Federal Register Volume 83, Number 99 (Tuesday, May 22, 2018)]
[Notices]
[Pages 23726-23728]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-10806]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-250 and 50-251; NRC-2018-0101]


Florida Power & Light Company: Turkey Point Nuclear Plant Units 3 
and 4

AGENCY: Nuclear Regulatory Commission.

ACTION: Intent to conduct scoping process and prepare environmental 
impact statement; public meeting and request for comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission will conduct a scoping 
process to gather information necessary to prepare an environmental 
impact statement (EIS) to evaluate the environmental impacts for the 
subsequent license renewal of the operating licenses for Turkey Point 
Nuclear Plant (Turkey Point) Unit Nos. 3 and 4. The NRC is seeking 
stakeholder input on this action and has scheduled a public meeting.

DATES: Submit comments by June 21, 2018. Comments received after this 
date will be considered if it is practical to do so, but assurance of 
consideration cannot be given to comments received after this date.

ADDRESSES: You may submit comments by any of the following methods 
(unless this document describes a different method for submitting 
comments on a specific subject):
     Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0101. Address 
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: Jennifer.Borges@nrc.gov. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     Mail comments to: May Ma, Office of Administration, Mail 
Stop: TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

[[Page 23727]]


FOR FURTHER INFORMATION CONTACT: William Burton, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-6332, email: William.Burton@nrc.gov.

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2018-0101 when contacting the NRC 
about the availability of information regarding this document. You may 
obtain publicly-available information related to this document by any 
of the following methods:
     Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0101.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The 
ADAMS accession number for each document referenced in this notice (if 
it is available in ADAMS) is provided the first time that it is 
mentioned in this document. The application for subsequent license 
renewal of the Turkey Point licenses can be found in ADAMS under 
Accession Nos. ML18037A812, ML18044A653, ML18053A123, ML18072A224, 
ML18113A132, and ML18102A521.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2018-0101 in the subject line of your 
comment submission in order to ensure that the NRC is able to make your 
comment submission available to the public in this docket.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC will post all comment submissions at http://www.regulations.gov as well as enter the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comments submissions into ADAMS.

II. Discussion

    By letter dated January 30, 2018, as supplemented by letters dated 
February 9, 2018; February 16, 2018; March 1, 2018; and April 10, 2018; 
Florida Power & Light Company submitted to the NRC an application for 
subsequent license renewal of Facility Operating License Nos. DPR-31 
and DPR-41 for an additional 20 years of operation at Turkey Point 
Units 3 and 4. Turkey Point Units 3 and 4 are located on Biscayne Bay 
in Miami-Dade County, Florida. The current renewed operating license 
for Unit 3 expires at midnight on July 19, 2032, and the current 
renewed operating license for Unit 4 expires at midnight on April 10, 
2033. The application for subsequent license renewal was submitted 
pursuant to part 54 of title 10 of the Code of Federal Regulations (10 
CFR) and included an environmental report (ER), also supplemented. A 
separate notice of receipt and availability of the application was 
published in the Federal Register on April 18, 2018 (83 FR 17196). A 
notice of acceptance for docketing of the supplemented application and 
opportunity for hearing regarding subsequent license renewal of the 
facility operating licenses was published in the Federal Register on 
May 2, 2018 (83 FR 19304).

III. Request for Comments

    This notice informs the public of the NRC's intention to prepare an 
EIS related to the subsequent license renewal application and to 
provide the public an opportunity to participate in the environmental 
scoping process, as defined in 10 CFR 51.29.
    The regulations in 36 CFR 800.8, ``Coordination with the National 
Environmental Policy Act,'' allows agencies to use their National 
Environmental Policy Act of 1969 (NEPA) process to fulfill the 
requirements of Section 106 of the National Historic Preservation Act 
(NHPA). Therefore, pursuant to 36 CFR 800.8(c), the NRC intends to use 
its process and documentation for the preparation of the EIS on the 
proposed action to comply with Section 106 of the NHPA in lieu of the 
procedures set forth at 36 CFR 800.3 through 800.6.
    In accordance with 10 CFR 51.53(c) and 10 CFR 54.23, Florida Power 
& Light Company submitted the ER as part of the subsequent license 
renewal application. To complete the acceptance review, the applicant 
provided supplemental information to support the staff's detailed 
technical review of the proposed action (subsequent license renewal). 
The ER and supplemental information were prepared pursuant to 10 CFR 
51.53(c), and are publicly available in ADAMS under Accession Nos. 
ML18037A836 and ML18102A521, respectively. The ER may also be viewed on 
the internet at https://www.nrc.gov/reactors/operating/licensing/renewal/subsequent-license-renewal.html. In addition, a paper copy of 
the subsequent license renewal application, including the ER, is 
available to the public near the site at the following locations: 
Homestead Branch Library, 700 N. Homestead Blvd., Homestead, FL 33030; 
Naranja Branch Library, 14850 SW 280th St., Homestead, FL 33032; South 
Dade Regional Library, 10750 SW 211th St., Miami, FL 33189; and 
Downtown Miami Branch, 101 West Flagler St., Miami, FL 33130.
    The NRC intends to gather the information necessary to prepare a 
plant-specific supplement to the NRC's ``Generic Environmental Impact 
Statement (GEIS) for License Renewal of Nuclear Plants'' (NUREG-1437), 
related to the application for subsequent license renewal of the Turkey 
Point operating licenses for an additional 20 years beyond the period 
specified in each of the current renewed licenses.
    Possible alternatives to the proposed action include the no action 
alternative and reasonable alternative energy sources. The NRC is 
required by 10 CFR 51.95 to prepare a supplement to the GEIS in 
connection with the renewal of an operating license. This notice is 
being published in accordance with NEPA and the NRC's regulations found 
at 10 CFR part 51.
    The NRC will first conduct scoping for the supplement to the GEIS 
and, as soon as practicable thereafter, will prepare a draft supplement 
to the GEIS for public comment. Participation in the scoping process by 
members of the public and local, State, Tribal, and Federal government 
agencies is encouraged. The scoping process for the supplement to the 
GEIS will be used to accomplish the following:

[[Page 23728]]

    a. Define the proposed action, which is to be the subject of the 
supplement to the GEIS;
    b. Determine the scope of the supplement to the GEIS and identify 
the significant issues to be analyzed in depth;
    c. Identify and eliminate from detailed study those issues that are 
peripheral or are not significant; or were covered by a prior 
environmental review;
    d. Identify any environmental assessments and other EISs that are 
being or will be prepared that are related to, but are not part of, the 
scope of the supplement to the GEIS being considered;
    e. Identify other environmental review and consultation 
requirements related to the proposed action;
    f. Indicate the relationship between the timing of the preparation 
of the environmental analyses and the Commission's tentative planning 
and decisionmaking schedule;
    g. Identify any cooperating agencies and, as appropriate, allocate 
assignments for preparation and schedules for completing the supplement 
to the GEIS to the NRC and any cooperating agencies; and
    h. Describe how the supplement to the GEIS will be prepared, 
including any contractor assistance to be used.
    The NRC invites the following entities to participate in scoping:
    a. The applicant, Florida Power & Light Company;
    b. Any Federal agency that has jurisdiction by law or special 
expertise with respect to any environmental impact involved or that is 
authorized to develop and enforce relevant environmental standards;
    c. Affected State and local government agencies, including those 
authorized to develop and enforce relevant environmental standards;
    d. Any affected Indian Tribe;
    e. Any person who requests or has requested an opportunity to 
participate in the scoping process; and
    f. Any person who has petitioned or intends to petition for leave 
to intervene.

IV. Public Scoping Meeting

    In accordance with 10 CFR 51.26, the scoping process for an EIS may 
include a public scoping meeting to help identify significant issues 
related to a proposed activity and to determine the scope of issues to 
be addressed in an EIS. The NRC will hold two public meetings for the 
Turkey Point license renewal supplement to the GEIS. The scoping 
meetings will be held on May 31, 2018. The meetings will be held from 
1:00 p.m. to 3:00 p.m. and from 5:00 p.m. to 7:00 p.m. at the City of 
Homestead City Hall, 100 Civic Court, Homestead, FL 33030. There will 
be an open house one hour before each session for members of the public 
to meet with NRC staff and sign in to speak.
    The meeting will be transcribed and will include: (1) An overview 
by the NRC staff of the NEPA environmental review process, the proposed 
scope of the supplement to the GEIS, and the proposed review schedule; 
and (2) the opportunity for interested government agencies, 
organizations, and individuals to submit comments or suggestions on the 
environmental issues or the proposed scope of the Turkey Point 
subsequent license renewal supplement to the GEIS. To be considered, 
comments must be provided either at the transcribed public meeting or 
in writing, as discussed in the ADDRESSES section of this notice.
    Persons may register to attend or present oral comments at the 
meetings on the scope of the NEPA review by contacting the NRC Project 
Manager, William Burton, by telephone at 301-415-6332, or by email to 
William.Burton@nrc.gov no later than May 24, 2018. Members of the 
public may also register to speak during the registration period prior 
to the start of the meeting. Individual oral comments may be limited by 
the time available, depending on the number of persons who register. 
Members of the public who have not registered may also have an 
opportunity to speak if time permits. Public comments will be 
considered in the scoping process for the Turkey Point subsequent 
license renewal supplement to the GEIS. Please contact Mr. Burton no 
later than May 24, 2018, if accommodations or special equipment is 
needed to attend or present information at the public meeting, so that 
the NRC staff can determine whether the request can be accommodated.
    Participation in the scoping process for the Turkey Point 
subsequent license renewal supplement to the GEIS does not entitle 
participants to become parties to the proceeding to which the 
supplement to the GEIS relates. Matters related to participation in any 
hearing are outside the scope of matters to be discussed at this public 
meeting.

    Dated at Rockville, Maryland, this 16th day of May, 2018.

    For the Nuclear Regulatory Commission.
Eric R. Oesterle,
Chief, License Renewal Project Branch, Division of Materials and 
License Renewal, Office of Nuclear Reactor Regulation.
[FR Doc. 2018-10806 Filed 5-21-18; 8:45 am]
 BILLING CODE 7590-01-P



                                              23726                          Federal Register / Vol. 83, No. 99 / Tuesday, May 22, 2018 / Notices

                                              similar written information is required                 IV. Public Participation—Submission of                  Signed at Washington, DC, on May 16,
                                              to be kept at the worksite, then the                    Comments on This Notice and Internet                  2018.
                                              employer must make the MSDS or                          Access to Comments and Submissions                    Loren Sweatt,
                                              written information available to the                       You may submit comments in                         Deputy Assistant Secretary of Labor for
                                              medical facility treating the exposed                                                                         Occupational Safety and Health.
                                                                                                      response to this document as follows:
                                              entrant.                                                (1) Electronically at http://                         [FR Doc. 2018–10889 Filed 5–21–18; 8:45 am]
                                                Section 1910.146(l)(1) requires                       www.regulations.gov, which is the                     BILLING CODE 4510–26–P
                                              employers to consult with affected                      Federal eRulemaking Portal; (2) by
                                              employees and their authorized                          facsimile (fax); or (3) by hard copy. All
                                              representatives on the development and                  comments, attachments, and other                      NUCLEAR REGULATORY
                                              implementation of all aspects of the                    material must identify the Agency name                COMMISSION
                                              permit space program required by                        and the OSHA docket number (Docket                    [Docket Nos. 50–250 and 50–251; NRC–
                                              paragraph (c). Section 1910.146(l)(2)                   No. OSHA–2011–0858) for the ICR. You                  2018–0101]
                                              requires employers to make all                          may supplement electronic submissions
                                              information required by this section                    by uploading document files                           Florida Power & Light Company:
                                              available to affected employees and                     electronically. If you wish to mail                   Turkey Point Nuclear Plant Units 3 and
                                              their authorized representatives.                       additional materials in reference to an               4
                                              II. Special Issues for Comment                          electronic or facsimile submission, you               AGENCY:  Nuclear Regulatory
                                                                                                      must submit them to the OSHA Docket                   Commission.
                                                OSHA has a particular interest in                     Office (see the section of this notice
                                              comments on the following issues:                                                                             ACTION: Intent to conduct scoping
                                                                                                      titled ADDRESSES). The additional                     process and prepare environmental
                                                • Whether the proposed information                    materials must clearly identify
                                              collection requirements are necessary                                                                         impact statement; public meeting and
                                                                                                      electronic comments by your name,                     request for comment.
                                              for the proper performance of the                       date, and the docket number so that the
                                              Agency’s functions, including whether                   Agency can attach them to your                        SUMMARY:    The U.S. Nuclear Regulatory
                                              the information is useful;                              comments.                                             Commission will conduct a scoping
                                                • The accuracy of OSHA’s estimate of                     Because of security procedures, the                process to gather information necessary
                                              the burden (time and costs) of the                      use of regular mail may cause a                       to prepare an environmental impact
                                              information collection requirements,                    significant delay in the receipt of                   statement (EIS) to evaluate the
                                              including the validity of the                           comments. For information about                       environmental impacts for the
                                              methodology and assumptions used;                       security procedures concerning the                    subsequent license renewal of the
                                                • The quality, utility, and clarity of                delivery of materials by hand, express                operating licenses for Turkey Point
                                              the information collected; and                          delivery, messenger, or courier service,              Nuclear Plant (Turkey Point) Unit Nos.
                                                • Ways to minimize the burden on                      please contact the OSHA Docket Office                 3 and 4. The NRC is seeking stakeholder
                                              employers who must comply—for                           at (202) 693–2350; TTY (877) 889–5627.                input on this action and has scheduled
                                              example, by using automated or other                       Comments and submissions are                       a public meeting.
                                              technological information collection                    posted without change at http://                      DATES: Submit comments by June 21,
                                              and transmission techniques.                            www.regulations.gov. Therefore, OSHA                  2018. Comments received after this date
                                                                                                      cautions commenters about submitting                  will be considered if it is practical to do
                                              III. Proposed Actions                                   personal information such as Social                   so, but assurance of consideration
                                                 OSHA is requesting an adjustment                     Security numbers and dates of birth.                  cannot be given to comments received
                                              increase for the information collection                 Although all submissions are listed in                after this date.
                                              requirements of 68,406 burden hours                     the http://www.regulations.gov index,                 ADDRESSES: You may submit comments
                                              (from 1,573,813 to 1,642,219). The                      some information (e.g., copyrighted                   by any of the following methods (unless
                                              burden hour increase is related to                      material) is not publicly available to                this document describes a different
                                              updated data estimates showing an                       read or download through this website.                method for submitting comments on a
                                              increase in the number of permit space                  All submissions, including copyrighted                specific subject):
                                              entrants (from 1,463,075 to 1,471,634)                  material, are available for inspection                   • Federal Rulemaking Website: Go to
                                              and establishments with permit spaces                   and copying at the OSHA Docket Office.                http://www.regulations.gov and search
                                              (from 205,548 to 210,281) affected by                   Information on using the http://                      for Docket ID NRC–2018–0101. Address
                                              the Standard.                                           www.regulations.gov website to submit                 questions about NRC dockets to Jennifer
                                                 Type of Review: Extension of a                       comments and access the docket is                     Borges; telephone: 301–287–9127;
                                              currently approved collection.                          available at the website’s ‘‘User Tips’’              email: Jennifer.Borges@nrc.gov. For
                                                 Title: Permit-Required Confined                      link. Contact the OSHA Docket Office                  technical questions, contact the
                                              Spaces (29 CFR 1910.146).                               for information about materials not                   individual listed in the FOR FURTHER
                                                 OMB Control Number: 1218–0203.                       available through the website, and for                INFORMATION CONTACT section of this
                                                 Affected Public: Business or other for-              assistance in using the internet to locate            document.
                                              profits.                                                docket submissions.                                      • Mail comments to: May Ma, Office
                                                                                                                                                            of Administration, Mail Stop: TWFN–7–
                                                 Number of Respondents: 210,281.                      V. Authority and Signature
                                                                                                                                                            A60M, U.S. Nuclear Regulatory
                                                 Frequency: On occasion.                                 Loren Sweatt, Deputy Assistant                     Commission, Washington, DC 20555–
amozie on DSK3GDR082PROD with NOTICES1




                                                 Average Time per Response: Varies.                   Secretary of Labor for Occupational                   0001.
                                                 Estimated Number of Responses:                       Safety and Health, directed the                          For additional direction on obtaining
                                              9,024,483.                                              preparation of this notice. The authority             information and submitting comments,
                                                 Estimated Total Burden Hours:                        for this notice is the Paperwork                      see ‘‘Obtaining Information and
                                              1,642,219.                                              Reduction Act of 1995 (44 U.S.C. 3506                 Submitting Comments’’ in the
                                                 Estimated Cost (Operation and                        et seq.) and Secretary of Labor’s Order               SUPPLEMENTARY INFORMATION section of
                                              Maintenance): $0.                                       No. 1–2012 (77 FR 3912).                              this document.


                                         VerDate Sep<11>2014   16:47 May 21, 2018   Jkt 241001   PO 00000   Frm 00102   Fmt 4703   Sfmt 4703   E:\FR\FM\22MYN1.SGM   22MYN1


                                                                             Federal Register / Vol. 83, No. 99 / Tuesday, May 22, 2018 / Notices                                            23727

                                              FOR FURTHER INFORMATION CONTACT:                        comment submissions to remove                         process and documentation for the
                                              William Burton, Office of Nuclear                       identifying or contact information.                   preparation of the EIS on the proposed
                                              Reactor Regulation, U.S. Nuclear                          If you are requesting or aggregating                action to comply with Section 106 of the
                                              Regulatory Commission, Washington,                      comments from other persons for                       NHPA in lieu of the procedures set forth
                                              DC 20555–0001; telephone: 301–415–                      submission to the NRC, then you should                at 36 CFR 800.3 through 800.6.
                                              6332, email: William.Burton@nrc.gov.                    inform those persons not to include                      In accordance with 10 CFR 51.53(c)
                                              SUPPLEMENTARY INFORMATION:                              identifying or contact information that               and 10 CFR 54.23, Florida Power &
                                                                                                      they do not want publicly disclosed in                Light Company submitted the ER as part
                                              I. Obtaining Information and                            their comment submission. Your request                of the subsequent license renewal
                                              Submitting Comments                                     should state that the NRC does not                    application. To complete the acceptance
                                                                                                      routinely edit comment submissions to                 review, the applicant provided
                                              A. Obtaining Information
                                                                                                      remove such information before making                 supplemental information to support
                                                 Please refer to Docket ID NRC–2018–                  the comment submissions available to                  the staff’s detailed technical review of
                                              0101 when contacting the NRC about                      the public or entering the comments                   the proposed action (subsequent license
                                              the availability of information regarding               submissions into ADAMS.                               renewal). The ER and supplemental
                                              this document. You may obtain                                                                                 information were prepared pursuant to
                                              publicly-available information related to               II. Discussion
                                                                                                                                                            10 CFR 51.53(c), and are publicly
                                              this document by any of the following                      By letter dated January 30, 2018, as
                                                                                                                                                            available in ADAMS under Accession
                                              methods:                                                supplemented by letters dated February
                                                                                                                                                            Nos. ML18037A836 and ML18102A521,
                                                 • Federal Rulemaking Website: Go to                  9, 2018; February 16, 2018; March 1,
                                                                                                                                                            respectively. The ER may also be
                                              http://www.regulations.gov and search                   2018; and April 10, 2018; Florida Power
                                                                                                                                                            viewed on the internet at https://
                                              for Docket ID NRC–2018–0101.                            & Light Company submitted to the NRC
                                                                                                                                                            www.nrc.gov/reactors/operating/
                                                 • NRC’s Agencywide Documents                         an application for subsequent license
                                                                                                                                                            licensing/renewal/subsequent-license-
                                              Access and Management System                            renewal of Facility Operating License
                                                                                                                                                            renewal.html. In addition, a paper copy
                                              (ADAMS): You may obtain publicly-                       Nos. DPR–31 and DPR–41 for an
                                                                                                                                                            of the subsequent license renewal
                                              available documents online in the                       additional 20 years of operation at
                                                                                                                                                            application, including the ER, is
                                              ADAMS Public Documents collection at                    Turkey Point Units 3 and 4. Turkey
                                                                                                      Point Units 3 and 4 are located on                    available to the public near the site at
                                              http://www.nrc.gov/reading-rm/
                                                                                                      Biscayne Bay in Miami-Dade County,                    the following locations: Homestead
                                              adams.html. To begin the search, select
                                                                                                      Florida. The current renewed operating                Branch Library, 700 N. Homestead
                                              ‘‘ADAMS Public Documents’’ and then
                                                                                                      license for Unit 3 expires at midnight on             Blvd., Homestead, FL 33030; Naranja
                                              select ‘‘Begin Web-based ADAMS
                                                                                                      July 19, 2032, and the current renewed                Branch Library, 14850 SW 280th St.,
                                              Search.’’ For problems with ADAMS,
                                                                                                      operating license for Unit 4 expires at               Homestead, FL 33032; South Dade
                                              please contact the NRC’s Public
                                                                                                      midnight on April 10, 2033. The                       Regional Library, 10750 SW 211th St.,
                                              Document Room (PDR) reference staff at
                                                                                                      application for subsequent license                    Miami, FL 33189; and Downtown
                                              1–800–397–4209, 301–415–4737, or by
                                                                                                      renewal was submitted pursuant to part                Miami Branch, 101 West Flagler St.,
                                              email to pdr.resource@nrc.gov. The
                                                                                                      54 of title 10 of the Code of Federal                 Miami, FL 33130.
                                              ADAMS accession number for each
                                              document referenced in this notice (if it               Regulations (10 CFR) and included an                     The NRC intends to gather the
                                              is available in ADAMS) is provided the                  environmental report (ER), also                       information necessary to prepare a
                                              first time that it is mentioned in this                 supplemented. A separate notice of                    plant-specific supplement to the NRC’s
                                              document. The application for                           receipt and availability of the                       ‘‘Generic Environmental Impact
                                              subsequent license renewal of the                       application was published in the                      Statement (GEIS) for License Renewal of
                                              Turkey Point licenses can be found in                   Federal Register on April 18, 2018 (83                Nuclear Plants’’ (NUREG–1437), related
                                              ADAMS under Accession Nos.                              FR 17196). A notice of acceptance for                 to the application for subsequent license
                                              ML18037A812, ML18044A653,                               docketing of the supplemented                         renewal of the Turkey Point operating
                                              ML18053A123, ML18072A224,                               application and opportunity for hearing               licenses for an additional 20 years
                                              ML18113A132, and ML18102A521.                           regarding subsequent license renewal of               beyond the period specified in each of
                                                 • NRC’s PDR: You may examine and                     the facility operating licenses was                   the current renewed licenses.
                                              purchase copies of public documents at                  published in the Federal Register on                     Possible alternatives to the proposed
                                              the NRC’s PDR, Room O1–F21, One                         May 2, 2018 (83 FR 19304).                            action include the no action alternative
                                              White Flint North, 11555 Rockville                                                                            and reasonable alternative energy
                                                                                                      III. Request for Comments                             sources. The NRC is required by 10 CFR
                                              Pike, Rockville, Maryland 20852.
                                                                                                         This notice informs the public of the              51.95 to prepare a supplement to the
                                              B. Submitting Comments                                  NRC’s intention to prepare an EIS                     GEIS in connection with the renewal of
                                                Please include Docket ID NRC–2018–                    related to the subsequent license                     an operating license. This notice is
                                              0101 in the subject line of your                        renewal application and to provide the                being published in accordance with
                                              comment submission in order to ensure                   public an opportunity to participate in               NEPA and the NRC’s regulations found
                                              that the NRC is able to make your                       the environmental scoping process, as                 at 10 CFR part 51.
                                              comment submission available to the                     defined in 10 CFR 51.29.                                 The NRC will first conduct scoping
                                              public in this docket.                                     The regulations in 36 CFR 800.8,                   for the supplement to the GEIS and, as
                                                The NRC cautions you not to include                   ‘‘Coordination with the National                      soon as practicable thereafter, will
                                              identifying or contact information that                 Environmental Policy Act,’’ allows                    prepare a draft supplement to the GEIS
amozie on DSK3GDR082PROD with NOTICES1




                                              you do not want to be publicly                          agencies to use their National                        for public comment. Participation in the
                                              disclosed in your comment submission.                   Environmental Policy Act of 1969                      scoping process by members of the
                                              The NRC will post all comment                           (NEPA) process to fulfill the                         public and local, State, Tribal, and
                                              submissions at http://                                  requirements of Section 106 of the                    Federal government agencies is
                                              www.regulations.gov as well as enter the                National Historic Preservation Act                    encouraged. The scoping process for the
                                              comment submissions into ADAMS.                         (NHPA). Therefore, pursuant to 36 CFR                 supplement to the GEIS will be used to
                                              The NRC does not routinely edit                         800.8(c), the NRC intends to use its                  accomplish the following:


                                         VerDate Sep<11>2014   16:47 May 21, 2018   Jkt 241001   PO 00000   Frm 00103   Fmt 4703   Sfmt 4703   E:\FR\FM\22MYN1.SGM   22MYN1


                                              23728                          Federal Register / Vol. 83, No. 99 / Tuesday, May 22, 2018 / Notices

                                                 a. Define the proposed action, which                 from 1:00 p.m. to 3:00 p.m. and from                    For the Nuclear Regulatory Commission.
                                              is to be the subject of the supplement to               5:00 p.m. to 7:00 p.m. at the City of                 Eric R. Oesterle,
                                              the GEIS;                                               Homestead City Hall, 100 Civic Court,                 Chief, License Renewal Project Branch,
                                                 b. Determine the scope of the                        Homestead, FL 33030. There will be an                 Division of Materials and License Renewal,
                                              supplement to the GEIS and identify the                 open house one hour before each                       Office of Nuclear Reactor Regulation.
                                              significant issues to be analyzed in                    session for members of the public to                  [FR Doc. 2018–10806 Filed 5–21–18; 8:45 am]
                                              depth;                                                  meet with NRC staff and sign in to                    BILLING CODE 7590–01–P
                                                 c. Identify and eliminate from                       speak.
                                              detailed study those issues that are
                                              peripheral or are not significant; or were                 The meeting will be transcribed and                NUCLEAR REGULATORY
                                              covered by a prior environmental                        will include: (1) An overview by the                  COMMISSION
                                              review;                                                 NRC staff of the NEPA environmental
                                                 d. Identify any environmental                        review process, the proposed scope of                 [NRC–2018–0096]
                                              assessments and other EISs that are                     the supplement to the GEIS, and the
                                                                                                                                                            Biweekly Notice; Applications and
                                              being or will be prepared that are                      proposed review schedule; and (2) the
                                                                                                                                                            Amendments to Facility Operating
                                              related to, but are not part of, the scope              opportunity for interested government                 Licenses and Combined Licenses
                                              of the supplement to the GEIS being                     agencies, organizations, and individuals              Involving No Significant Hazards
                                              considered;                                             to submit comments or suggestions on                  Considerations
                                                 e. Identify other environmental                      the environmental issues or the
                                              review and consultation requirements                    proposed scope of the Turkey Point                    AGENCY:  Nuclear Regulatory
                                              related to the proposed action;                         subsequent license renewal supplement                 Commission.
                                                 f. Indicate the relationship between                 to the GEIS. To be considered,                        ACTION: Biweekly notice.
                                              the timing of the preparation of the                    comments must be provided either at
                                              environmental analyses and the                          the transcribed public meeting or in                  SUMMARY:   Pursuant to Section 189a.(2)
                                              Commission’s tentative planning and                                                                           of the Atomic Energy Act of 1954, as
                                                                                                      writing, as discussed in the ADDRESSES
                                              decisionmaking schedule;                                                                                      amended (the Act), the U.S. Nuclear
                                                                                                      section of this notice.
                                                 g. Identify any cooperating agencies                                                                       Regulatory Commission (NRC) is
                                              and, as appropriate, allocate                              Persons may register to attend or                  publishing this regular biweekly notice.
                                              assignments for preparation and                         present oral comments at the meetings                 The Act requires the Commission to
                                              schedules for completing the                            on the scope of the NEPA review by                    publish notice of any amendments
                                              supplement to the GEIS to the NRC and                   contacting the NRC Project Manager,                   issued, or proposed to be issued, and
                                              any cooperating agencies; and                           William Burton, by telephone at 301–                  grants the Commission the authority to
                                                 h. Describe how the supplement to                    415–6332, or by email to                              issue and make immediately effective
                                              the GEIS will be prepared, including                    William.Burton@nrc.gov no later than                  any amendment to an operating license
                                              any contractor assistance to be used.                   May 24, 2018. Members of the public                   or combined license, as applicable,
                                                 The NRC invites the following entities               may also register to speak during the                 upon a determination by the
                                              to participate in scoping:                              registration period prior to the start of             Commission that such amendment
                                                 a. The applicant, Florida Power &                    the meeting. Individual oral comments                 involves no significant hazards
                                              Light Company;                                                                                                consideration, notwithstanding the
                                                                                                      may be limited by the time available,
                                                 b. Any Federal agency that has                                                                             pendency before the Commission of a
                                                                                                      depending on the number of persons
                                              jurisdiction by law or special expertise                                                                      request for a hearing from any person.
                                              with respect to any environmental                       who register. Members of the public
                                                                                                      who have not registered may also have                    This biweekly notice includes all
                                              impact involved or that is authorized to                                                                      notices of amendments issued, or
                                              develop and enforce relevant                            an opportunity to speak if time permits.
                                                                                                      Public comments will be considered in                 proposed to be issued, from April 24,
                                              environmental standards;                                                                                      2018, to May 7, 2018. The last biweekly
                                                 c. Affected State and local                          the scoping process for the Turkey Point
                                                                                                                                                            notice was published on May 8, 2018.
                                              government agencies, including those                    subsequent license renewal supplement
                                                                                                      to the GEIS. Please contact Mr. Burton                DATES: Comments must be filed by June
                                              authorized to develop and enforce
                                                                                                      no later than May 24, 2018, if                        21, 2018. A request for a hearing must
                                              relevant environmental standards;
                                                 d. Any affected Indian Tribe;                        accommodations or special equipment                   be filed by July 23, 2018.
                                                 e. Any person who requests or has                    is needed to attend or present                        ADDRESSES: You may submit comments
                                              requested an opportunity to participate                 information at the public meeting, so                 by any of the following methods:
                                              in the scoping process; and                             that the NRC staff can determine                         • Federal Rulemaking Website: Go to
                                                 f. Any person who has petitioned or                  whether the request can be                            http://www.regulations.gov and search
                                              intends to petition for leave to                        accommodated.                                         for Docket ID NRC–2018–0096. Address
                                              intervene.                                                                                                    questions about NRC dockets to Jennifer
                                                                                                         Participation in the scoping process               Borges; telephone: 301–287–9127;
                                              IV. Public Scoping Meeting                              for the Turkey Point subsequent license               email: Jennifer.Borges@nrc.gov. For
                                                In accordance with 10 CFR 51.26, the                  renewal supplement to the GEIS does                   technical questions, contact the
                                              scoping process for an EIS may include                  not entitle participants to become                    individual listed in the FOR FURTHER
                                              a public scoping meeting to help                        parties to the proceeding to which the                INFORMATION CONTACT section of this
                                              identify significant issues related to a                supplement to the GEIS relates. Matters               document.
amozie on DSK3GDR082PROD with NOTICES1




                                              proposed activity and to determine the                  related to participation in any hearing                  • Mail comments to: May Ma, Office
                                              scope of issues to be addressed in an                   are outside the scope of matters to be                of Administration, Mail Stop: TWFN–7–
                                              EIS. The NRC will hold two public                       discussed at this public meeting.                     A60M, U.S. Nuclear Regulatory
                                              meetings for the Turkey Point license                     Dated at Rockville, Maryland, this 16th day
                                                                                                                                                            Commission, Washington, DC 20555–
                                              renewal supplement to the GEIS. The                     of May, 2018.
                                                                                                                                                            0001.
                                              scoping meetings will be held on May                                                                             For additional direction on obtaining
                                              31, 2018. The meetings will be held                                                                           information and submitting comments,


                                         VerDate Sep<11>2014   16:47 May 21, 2018   Jkt 241001   PO 00000   Frm 00104   Fmt 4703   Sfmt 4703   E:\FR\FM\22MYN1.SGM   22MYN1



Document Created: 2018-11-02 11:09:59
Document Modified: 2018-11-02 11:09:59
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionIntent to conduct scoping process and prepare environmental impact statement; public meeting and request for comment.
DatesSubmit comments by June 21, 2018. Comments received after this date will be considered if it is practical to do so, but assurance of consideration cannot be given to comments received after this date.
ContactWilliam Burton, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-6332, email: [email protected]
FR Citation83 FR 23726 