The U.S. Nuclear Regulatory Commission (NRC) is issuing for public comment draft regulatory guide (DG), DG-1336, ``Monitoring the Effectiveness of Maintenance at Nuclear Power Plants.'' This proposed guide, Revision 4, has been revised to addresses new issues identified since Revision 3 of RG 1.160 was issued and endorses with clarification NUMARC 93-01, ``Industry Guidelines for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants,'' Revision 4F. The proposed revision describes methods that are acceptable to the NRC staff for compliance with the requirements for monitoring the effectiveness of maintenance at nuclear power plants.

Federal Register, Volume 83 Issue 125 (Thursday, June 28, 2018)
[Federal Register Volume 83, Number 125 (Thursday, June 28, 2018)]
[Notices]
[Pages 30469-30470]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-13876]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2018-0131]


Monitoring the Effectiveness of Maintenance at Nuclear Power 
Plants

AGENCY: Nuclear Regulatory Commission.

ACTION: Draft regulatory guide; request for comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing for 
public comment draft regulatory guide (DG), DG-1336, ``Monitoring the 
Effectiveness of Maintenance at Nuclear Power Plants.'' This proposed 
guide, Revision 4, has been revised to addresses new issues identified 
since Revision 3 of RG 1.160 was issued and endorses with clarification 
NUMARC 93-01, ``Industry Guidelines for Monitoring the Effectiveness of 
Maintenance at Nuclear Power Plants,'' Revision 4F. The proposed 
revision describes methods that are acceptable to the NRC staff for 
compliance with the requirements for monitoring the effectiveness of 
maintenance at nuclear power plants.

DATES: Submit comments by July 30, 2018. Comments received after this 
date will be considered if it is practical to do so, but the NRC is 
able to ensure consideration only for comments received on or before 
this date. Although a time limit is given, comments and suggestions in 
connection with items for inclusion in guides currently being developed 
or improvements in all published guides are encouraged at any time.

ADDRESSES: You may submit comments by any of the following methods:
     Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0131. Address 
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: [email protected]. For technical questions, contact 
the individuals listed in the FOR FURTHER INFORMATION CONTACT section 
of this document.
     Mail comments to: May Ma, Office of Administration, Mail 
Stop: TWFN-7A60, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Ami Agrawal, Office of Nuclear Reactor 
Regulation, telephone: 301-415-8310, email: [email protected]; and 
Stephen Burton, Office of Nuclear Regulatory Research, telephone: 301-
415-7000, email: [email protected]. Both are staff of the U.S. 
Nuclear Regulatory Commission, Washington, DC 20555-0001.

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2018-0131 when contacting the NRC 
about the availability of information regarding this action. You may 
obtain publically-available information related to this action, by any 
of the following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0131.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
DG-1336 is available in ADAMS under Accession No. ML18129A080.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2018-0131 in your comment submission.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC posts all comment submissions at http://www.regulations.gov as well as enters the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment submissions into ADAMS.

II. Additional Information

    The NRC is issuing for public comment a DG in the NRC's 
``Regulatory Guide'' series. This series was developed to describe and 
make available to the public information regarding methods that are 
acceptable to the NRC staff for implementing specific parts of the 
NRC's regulations, techniques that the staff uses in evaluating 
specific issues or postulated events, and data that the staff needs in 
its review of applications for permits and licenses.
    The Maintenance Rule (Part 50.65 of title 10 of the Code of Federal 
Regulations (10 CFR)) requires each holder of an operating license for 
a nuclear power plant under 10 CFR part 50 and each holder of a 
combined license under 10 CFR part 52 (after the Commission makes 
certain findings) to monitor the performance or condition of 
structures, systems, or components, against licensee-established goals, 
in a manner sufficient to provide reasonable assurance that in-scope 
structures, systems, and components intended functions. The Maintenance 
Rule also applies to nuclear power plant for which the licensee has 
submitted the certifications that it has ceased operating permanently, 
but limited to structures, systems, or components associated with the 
storage, control, and maintenance of spent fuel in a safe condition, in 
a manner sufficient to provide reasonable assurance that these 
structures, systems, and components are

[[Page 30470]]

capable of fulfilling their intended functions. Last, an application 
for a combined license shall contain a final safety analysis report 
that provides a description of the program, and its implementation, for 
monitoring the effectiveness of maintenance necessary to meet the 
requirements of 10 CFR 50.65.
    The Nuclear Energy Institute (NEI) is submit revision 4F of NUMARC 
93-01, ``Industry Guideline for Monitoring the Effectiveness of 
Maintenance at Nuclear Power Plants'' for endorsement. NEI explained 
that NUMARC 93-01 was developed to establish an acceptable approach for 
licensees to meet the Maintenance Rule. Revision 4F of NUMARC 93-01 
addresses the application of the Maintenance Rule to the use of diverse 
and flexible coping strategies (FLEX) support guidelines (FSGs) in 
plant emergency operating procedures (EOPs), as well as some other 
minor wording changes.
    The DG, entitled, ``Monitoring the Effectiveness of Maintenance at 
Nuclear Power Plants,'' is a proposed revision temporarily identified 
by its task number, DG-1336. DG-1336 is proposed revision 4 of RG 
1.160, ``Monitoring the Effectiveness of Maintenance at Nuclear Power 
Plants.'' The NRC's proposed revision to RG 1.160 would endorse with 
clarification NUMARC 93-01 Revision 4F. The NRC finds that endorsement 
would be beneficial in that the agency positions with respect to FLEX 
equipment, the Maintenance Rule, and Revision 4F of NUMARC 93-01 would 
be readily understood.

III. Backfitting and Issue Finality

    This DG describes methods acceptable to the staff of the NRC for 
demonstrating compliance with the provisions of 10 CFR 50.65, 
``Requirements for Monitoring the Effectiveness of Maintenance at 
Nuclear Power Plants,'' of 10 CFR part 50, ``Domestic Licensing of 
Production and Utilization Facilities.'' As discussed in Section D. 
``Implementation'' of this DG, the NRC does not intend to impose this 
guide, if finalized, on applicants for, or holders of, licenses.
    This DG may be applied to applications for combined licenses under 
10 CFR part 52 docketed by the NRC as of the date of issuance of the 
final regulatory guide, as well as future applications submitted after 
the issuance of the regulatory guide. Such action would not constitute 
backfitting as defined in the 10 CFR 50.109 or be otherwise 
inconsistent with the applicable issue finality provision in 10 CFR 
part 52, inasmuch as such applicants or potential applicants, with 
certain exceptions, are not within the scope of entities that are the 
subject of the Backfit Rule or an issue finality provision in 10 CFR 
part 52. However, the scope of backfitting and issue finality extends 
only to the matters resolved in the license or regulatory approval. The 
matters addressed in this DG (concerning monitoring the effectiveness 
of maintenance at nuclear power plants) has not previously been 
proposed to be for a construction permit, design certification rule, or 
standard design approval. Therefore, the extent to which an applicant 
can rely on a backfitting or issue finality provision is limited to the 
extent that the applicant has addressed the matters in this regulatory 
guide during the review and approval of the construction permit, design 
certification rule, or standard design approval.

    Dated at Rockville, Maryland, this 22nd day of June, 2018.

    For the Nuclear Regulatory Commission.
Edward O'Donnell,
Acting Chief, Regulatory Guidance and Generic Issues Branch, Division 
of Engineering, Office of Nuclear Regulatory Research.
[FR Doc. 2018-13876 Filed 6-27-18; 8:45 am]
BILLING CODE 7590-01-P



                                                                            Federal Register / Vol. 83, No. 125 / Thursday, June 28, 2018 / Notices                                           30469

                                              participants are requested not to include                 • Federal Rulemaking Website: Go to                  B. Submitting Comments
                                              copyrighted materials in their                          http://www.regulations.gov and search                    Please include Docket ID NRC–2018–
                                              submission.                                             for Docket ID NRC–2018–0131. Address                   0131 in your comment submission.
                                                For further details with respect to this              questions about NRC dockets to Jennifer                  The NRC cautions you not to include
                                              action, see the application for license                 Borges; telephone: 301–287–9127;                       identifying or contact information that
                                              amendment dated June 15, 2018                           email: Jennifer.Borges@nrc.gov. For                    you do not want to be publicly
                                              (ADAMS Accession No. ML18169A222).                      technical questions, contact the                       disclosed in your comment submission.
                                                Attorney for licensee: General                        individuals listed in the FOR FURTHER                  The NRC posts all comment
                                              Counsel, Tennessee Valley Authority,                    INFORMATION CONTACT section of this                    submissions at http://
                                              400 West Summit Hill Drive, 6A West                     document.                                              www.regulations.gov as well as enters
                                              Tower, Knoxville, TN 37902.                               • Mail comments to: May Ma, Office                   the comment submissions into ADAMS.
                                                NRC Acting Branch Chief: Booma                        of Administration, Mail Stop: TWFN–                    The NRC does not routinely edit
                                              Venkataraman.                                           7A60, U.S. Nuclear Regulatory                          comment submissions to remove
                                                 Dated at Rockville, Maryland, this 22nd              Commission, Washington, DC 20555–                      identifying or contact information.
                                              day of June 2018.                                       0001.                                                    If you are requesting or aggregating
                                                 For the Nuclear Regulatory Commission.                 For additional direction on obtaining                comments from other persons for
                                              Andrew Hon,                                             information and submitting comments,                   submission to the NRC, then you should
                                              Project Manager, Plant Licensing Branch                 see ‘‘Obtaining Information and                        inform those persons not to include
                                              II–2, Division of Operating Reactor Licensing,          Submitting Comments’’ in the                           identifying or contact information that
                                              Office of Nuclear Reactor Regulation.                   SUPPLEMENTARY INFORMATION section of                   they do not want to be publicly
                                              [FR Doc. 2018–13874 Filed 6–27–18; 8:45 am]             this document.                                         disclosed in their comment submission.
                                              BILLING CODE 7590–01–P
                                                                                                      FOR FURTHER INFORMATION CONTACT:    Ami                Your request should state that the NRC
                                                                                                      Agrawal, Office of Nuclear Reactor                     does not routinely edit comment
                                                                                                      Regulation, telephone: 301–415–8310,                   submissions to remove such information
                                              NUCLEAR REGULATORY                                                                                             before making the comment
                                                                                                      email: Ami.Agrawal@nrc.gov; and
                                              COMMISSION                                                                                                     submissions available to the public or
                                                                                                      Stephen Burton, Office of Nuclear
                                              [NRC–2018–0131]                                         Regulatory Research, telephone: 301–                   entering the comment submissions into
                                                                                                      415–7000, email: Stephen.Burton@                       ADAMS.
                                              Monitoring the Effectiveness of                         nrc.gov. Both are staff of the U.S.                    II. Additional Information
                                              Maintenance at Nuclear Power Plants                     Nuclear Regulatory Commission,
                                                                                                                                                                The NRC is issuing for public
                                              AGENCY: Nuclear Regulatory                              Washington, DC 20555–0001.
                                                                                                                                                             comment a DG in the NRC’s ‘‘Regulatory
                                              Commission.                                             SUPPLEMENTARY INFORMATION:                             Guide’’ series. This series was
                                              ACTION: Draft regulatory guide; request                                                                        developed to describe and make
                                                                                                      I. Obtaining Information and
                                              for comment.                                                                                                   available to the public information
                                                                                                      Submitting Comments
                                                                                                                                                             regarding methods that are acceptable to
                                              SUMMARY:    The U.S. Nuclear Regulatory                 A. Obtaining Information                               the NRC staff for implementing specific
                                              Commission (NRC) is issuing for public                                                                         parts of the NRC’s regulations,
                                              comment draft regulatory guide (DG),                       Please refer to Docket ID NRC–2018–
                                                                                                                                                             techniques that the staff uses in
                                              DG–1336, ‘‘Monitoring the Effectiveness                 0131 when contacting the NRC about
                                                                                                                                                             evaluating specific issues or postulated
                                              of Maintenance at Nuclear Power                         the availability of information regarding
                                                                                                                                                             events, and data that the staff needs in
                                              Plants.’’ This proposed guide, Revision                 this action. You may obtain publically-
                                                                                                                                                             its review of applications for permits
                                              4, has been revised to addresses new                    available information related to this
                                                                                                                                                             and licenses.
                                              issues identified since Revision 3 of RG                action, by any of the following methods:
                                                                                                                                                                The Maintenance Rule (Part 50.65 of
                                              1.160 was issued and endorses with                         • Federal Rulemaking website: Go to                 title 10 of the Code of Federal
                                              clarification NUMARC 93–01, ‘‘Industry                  http://www.regulations.gov and search                  Regulations (10 CFR)) requires each
                                              Guidelines for Monitoring the                           for Docket ID NRC–2018–0131.                           holder of an operating license for a
                                              Effectiveness of Maintenance at Nuclear                    • NRC’s Agencywide Documents                        nuclear power plant under 10 CFR part
                                              Power Plants,’’ Revision 4F. The                        Access and Management System                           50 and each holder of a combined
                                              proposed revision describes methods                     (ADAMS): You may obtain publicly-                      license under 10 CFR part 52 (after the
                                              that are acceptable to the NRC staff for                available documents online in the                      Commission makes certain findings) to
                                              compliance with the requirements for                    ADAMS Public Documents collection at                   monitor the performance or condition of
                                              monitoring the effectiveness of                         http://www.nrc.gov/reading-rm/                         structures, systems, or components,
                                              maintenance at nuclear power plants.                    adams.html. To begin the search, select                against licensee-established goals, in a
                                              DATES: Submit comments by July 30,                      ‘‘ADAMS Public Documents’’ and then                    manner sufficient to provide reasonable
                                              2018. Comments received after this date                 select ‘‘Begin Web-based ADAMS                         assurance that in-scope structures,
                                              will be considered if it is practical to do             Search.’’ For problems with ADAMS,                     systems, and components intended
                                              so, but the NRC is able to ensure                       please contact the NRC’s Public                        functions. The Maintenance Rule also
                                              consideration only for comments                         Document Room (PDR) reference staff at                 applies to nuclear power plant for
                                              received on or before this date.                        1–800–397–4209, 301–415–4737, or by                    which the licensee has submitted the
                                              Although a time limit is given,                         email to pdr.resource@nrc.gov. The DG–                 certifications that it has ceased
amozie on DSK3GDR082PROD with NOTICES1




                                              comments and suggestions in                             1336 is available in ADAMS under                       operating permanently, but limited to
                                              connection with items for inclusion in                  Accession No. ML18129A080.                             structures, systems, or components
                                              guides currently being developed or                        • NRC’s PDR: You may examine and                    associated with the storage, control, and
                                              improvements in all published guides                    purchase copies of public documents at                 maintenance of spent fuel in a safe
                                              are encouraged at any time.                             the NRC’s PDR, Room O1–F21, One                        condition, in a manner sufficient to
                                              ADDRESSES: You may submit comments                      White Flint North, 11555 Rockville                     provide reasonable assurance that these
                                              by any of the following methods:                        Pike, Rockville, Maryland 20852.                       structures, systems, and components are


                                         VerDate Sep<11>2014   17:08 Jun 27, 2018   Jkt 244001   PO 00000   Frm 00073   Fmt 4703   Sfmt 4703   E:\FR\FM\28JNN1.SGM   28JNN1


                                              30470                         Federal Register / Vol. 83, No. 125 / Thursday, June 28, 2018 / Notices

                                              capable of fulfilling their intended                    applicants or potential applicants, with               II. Docketed Proceeding(s)
                                              functions. Last, an application for a                   certain exceptions, are not within the                 I. Introduction
                                              combined license shall contain a final                  scope of entities that are the subject of
                                              safety analysis report that provides a                  the Backfit Rule or an issue finality                     The Commission gives notice that the
                                              description of the program, and its                     provision in 10 CFR part 52. However,                  Postal Service filed request(s) for the
                                              implementation, for monitoring the                      the scope of backfitting and issue                     Commission to consider matters related
                                              effectiveness of maintenance necessary                  finality extends only to the matters                   to negotiated service agreement(s). The
                                              to meet the requirements of 10 CFR                      resolved in the license or regulatory                  request(s) may propose the addition or
                                              50.65.                                                  approval. The matters addressed in this                removal of a negotiated service
                                                 The Nuclear Energy Institute (NEI) is                DG (concerning monitoring the                          agreement from the market dominant or
                                              submit revision 4F of NUMARC 93–01,                     effectiveness of maintenance at nuclear                the competitive product list, or the
                                              ‘‘Industry Guideline for Monitoring the                 power plants) has not previously been                  modification of an existing product
                                              Effectiveness of Maintenance at Nuclear                 proposed to be for a construction                      currently appearing on the market
                                              Power Plants’’ for endorsement. NEI                     permit, design certification rule, or                  dominant or the competitive product
                                              explained that NUMARC 93–01 was                         standard design approval. Therefore, the               list.
                                              developed to establish an acceptable                    extent to which an applicant can rely on                  Section II identifies the docket
                                              approach for licensees to meet the                      a backfitting or issue finality provision              number(s) associated with each Postal
                                              Maintenance Rule. Revision 4F of                        is limited to the extent that the                      Service request, the title of each Postal
                                              NUMARC 93–01 addresses the                              applicant has addressed the matters in                 Service request, the request’s acceptance
                                              application of the Maintenance Rule to                  this regulatory guide during the review                date, and the authority cited by the
                                              the use of diverse and flexible coping                  and approval of the construction permit,               Postal Service for each request. For each
                                              strategies (FLEX) support guidelines                    design certification rule, or standard                 request, the Commission appoints an
                                              (FSGs) in plant emergency operating                     design approval.                                       officer of the Commission to represent
                                              procedures (EOPs), as well as some                                                                             the interests of the general public in the
                                              other minor wording changes.                              Dated at Rockville, Maryland, this 22nd
                                                                                                      day of June, 2018.                                     proceeding, pursuant to 39 U.S.C. 505
                                                 The DG, entitled, ‘‘Monitoring the                                                                          (Public Representative). Section II also
                                              Effectiveness of Maintenance at Nuclear                   For the Nuclear Regulatory Commission.
                                                                                                      Edward O’Donnell,
                                                                                                                                                             establishes comment deadline(s)
                                              Power Plants,’’ is a proposed revision                                                                         pertaining to each request.
                                              temporarily identified by its task                      Acting Chief, Regulatory Guidance and
                                                                                                      Generic Issues Branch, Division of                        The public portions of the Postal
                                              number, DG–1336. DG–1336 is
                                                                                                      Engineering, Office of Nuclear Regulatory              Service’s request(s) can be accessed via
                                              proposed revision 4 of RG 1.160,
                                                                                                      Research.                                              the Commission’s website (http://
                                              ‘‘Monitoring the Effectiveness of
                                              Maintenance at Nuclear Power Plants.’’                  [FR Doc. 2018–13876 Filed 6–27–18; 8:45 am]            www.prc.gov). Non-public portions of
                                              The NRC’s proposed revision to RG                       BILLING CODE 7590–01–P
                                                                                                                                                             the Postal Service’s request(s), if any,
                                              1.160 would endorse with clarification                                                                         can be accessed through compliance
                                              NUMARC 93–01 Revision 4F. The NRC                                                                              with the requirements of 39 CFR
                                              finds that endorsement would be                         POSTAL REGULATORY COMMISSION                           3007.40.
                                              beneficial in that the agency positions                                                                           The Commission invites comments on
                                                                                                      [Docket Nos. MC2018–186 and CP2018–260]                whether the Postal Service’s request(s)
                                              with respect to FLEX equipment, the
                                              Maintenance Rule, and Revision 4F of                                                                           in the captioned docket(s) are consistent
                                                                                                      New Postal Products                                    with the policies of title 39. For
                                              NUMARC 93–01 would be readily
                                              understood.                                             AGENCY:   Postal Regulatory Commission.                request(s) that the Postal Service states
                                                                                                      ACTION:   Notice.                                      concern market dominant product(s),
                                              III. Backfitting and Issue Finality                                                                            applicable statutory and regulatory
                                                 This DG describes methods acceptable                 SUMMARY:   The Commission is noticing a                requirements include 39 U.S.C. 3622, 39
                                              to the staff of the NRC for demonstrating               recent Postal Service filing for the                   U.S.C. 3642, 39 CFR part 3010, and 39
                                              compliance with the provisions of 10                    Commission’s consideration concerning                  CFR part 3020, subpart B. For request(s)
                                              CFR 50.65, ‘‘Requirements for                           negotiated service agreements. This                    that the Postal Service states concern
                                              Monitoring the Effectiveness of                         notice informs the public of the filing,               competitive product(s), applicable
                                              Maintenance at Nuclear Power Plants,’’                  invites public comment, and takes other                statutory and regulatory requirements
                                              of 10 CFR part 50, ‘‘Domestic Licensing                 administrative steps.                                  include 39 U.S.C. 3632, 39 U.S.C. 3633,
                                              of Production and Utilization                           DATES: Comments are due: July 2, 2018.                 39 U.S.C. 3642, 39 CFR part 3015, and
                                              Facilities.’’ As discussed in Section D.                                                                       39 CFR part 3020, subpart B. Comment
                                                                                                      ADDRESSES: Submit comments
                                              ‘‘Implementation’’ of this DG, the NRC                                                                         deadline(s) for each request appear in
                                                                                                      electronically via the Commission’s
                                              does not intend to impose this guide, if                                                                       section II.
                                                                                                      Filing Online system at http://
                                              finalized, on applicants for, or holders                www.prc.gov. Those who cannot submit                   II. Docketed Proceeding(s)
                                              of, licenses.                                           comments electronically should contact
                                                 This DG may be applied to                                                                                     1. Docket No(s).: MC2018–186 and
                                                                                                      the person identified in the FOR FURTHER
                                              applications for combined licenses                                                                             CP2018–260; Filing Title: Request of the
                                                                                                      INFORMATION CONTACT section by
                                              under 10 CFR part 52 docketed by the                                                                           United States Postal Service to Add
                                                                                                      telephone for advice on filing
                                              NRC as of the date of issuance of the                                                                          Global Expedited Package Services—
                                                                                                      alternatives.
                                              final regulatory guide, as well as future                                                                      Non-Published Rates 14 (GEPS—NPR
amozie on DSK3GDR082PROD with NOTICES1




                                              applications submitted after the                        FOR FURTHER INFORMATION CONTACT:                       14) to the Competitive Products List and
                                              issuance of the regulatory guide. Such                  David A. Trissell, General Counsel, at                 Notice of Filing GEPS—NPR 14 Model
                                              action would not constitute backfitting                 202–789–6820.                                          Contract and Application for Non-
                                              as defined in the 10 CFR 50.109 or be                   SUPPLEMENTARY INFORMATION:                             Public Treatment of Materials Filed
                                              otherwise inconsistent with the                                                                                Under Seal; Filing Acceptance Date:
                                              applicable issue finality provision in 10               Table of Contents                                      June 22, 2018; Filing Authority: 39
                                              CFR part 52, inasmuch as such                           I. Introduction                                        U.S.C. 3642 and 39 CFR 3020.30 et seq.;


                                         VerDate Sep<11>2014   17:08 Jun 27, 2018   Jkt 244001   PO 00000   Frm 00074   Fmt 4703   Sfmt 4703   E:\FR\FM\28JNN1.SGM   28JNN1



Document Created: 2018-11-06 09:55:21
Document Modified: 2018-11-06 09:55:21
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionDraft regulatory guide; request for comment.
DatesSubmit comments by July 30, 2018. Comments received after this date will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date. Although a time limit is given, comments and suggestions in connection with items for inclusion in guides currently being developed or improvements in all published guides are encouraged at any time.
ContactAmi Agrawal, Office of Nuclear Reactor Regulation, telephone: 301-415-8310, email: [email protected]; and Stephen Burton, Office of Nuclear Regulatory Research, telephone: 301- 415-7000, email: [email protected] Both are staff of the U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
FR Citation83 FR 30469 