83 FR 31386 - Notice of Modification of Procedural Schedule; Turlock Irrigation District, Modesto Irrigation District

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 129 (July 5, 2018)

Page Range31386-31387
FR Document2018-14345

Federal Register, Volume 83 Issue 129 (Thursday, July 5, 2018)
[Federal Register Volume 83, Number 129 (Thursday, July 5, 2018)]
[Notices]
[Pages 31386-31387]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-14345]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[ Project No. 14581-002; Project No. 2299-082]


Notice of Modification of Procedural Schedule; Turlock Irrigation 
District, Modesto Irrigation District

    Take notice that the schedule for processing the following 
hydroelectric applications has been modified.
    a. Type of Applications: Major Licenses.
    b. Project Nos.: 14581-002 and 2299-082.
    c. Date filed: October 11, 2017.
    d. Applicant: Turlock Irrigation District and Modesto Irrigation 
District (Districts).
    e. Name of Projects: La Grange and Don Pedro Hydroelectric 
Projects.
    f. Location: The La Grange Project is located on the Tuolumne River 
in

[[Page 31387]]

Stanislaus and Tuolumne Counties, California. The Don Pedro Project is 
located on the Tuolumne River in Tuolumne County, California. Portions 
of both projects occupy public lands managed by the Bureau of Land 
Management.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contacts: Steve Boyd, Turlock Irrigation District, 333 
East Canal Drive, Turlock, California 95381-0949, (209) 883-8300; and 
Anna Brathwaite, Modesto Irrigation District, P.O. Box 4060, Modesto, 
CA 95352, (209) 526-7384.
    i. FERC Contact: Jim Hastreiter at (503) 552-2760 or 
[email protected].
    j. Procedural Schedule: The Commission's November 30, 2017, Notice 
of Application Ready for Environmental Analysis for each of the 
projects established July 2018 as the estimated date for issuing the 
Draft Environmental Impact Statement (EIS). The revised estimate for 
issuing the Draft EIS is now November 2018. As such, the applications 
will be processed according to the following revised schedule. 
Revisions to the schedule may be made as appropriate. If a due date 
falls on a weekend or holiday, the due date will be the following 
business day.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Commission issues Draft EIS............  November 2018.
Comments on Draft EIS..................  January 2019.
Modified Terms and Conditions..........  March 2019.
Commission issues Final EIS............  May 2019.
------------------------------------------------------------------------


    Dated: June 27, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-14345 Filed 7-3-18; 8:45 am]
BILLING CODE 6717-01-P


Current View
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 31386 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR