83_FR_40917 83 FR 40758 - Extension of Comment Period, Draft Waste Incidental To Reprocessing Evaluation for Closure of Waste Management Area C at the Hanford Site, Washington

83 FR 40758 - Extension of Comment Period, Draft Waste Incidental To Reprocessing Evaluation for Closure of Waste Management Area C at the Hanford Site, Washington

DEPARTMENT OF ENERGY

Federal Register Volume 83, Issue 159 (August 16, 2018)

Page Range40758-40759
FR Document2018-17687

On June 4, 2018, the U.S. Department of Energy (``DOE'') published in the Federal Register a Notice of Availability of the Draft Waste Incidental to Reprocessing Evaluation for Closure of Waste Management Area C at the Hanford Site, Washington (Draft WIR Evaluation), which evaluates whether the stabilized tanks and ancillary structures in WMA C, as well as the residual material in these tanks and structures will meet the criteria in Section II.B.(2)(a) of DOE M. 435.1-1, Radioactive Waste Management Manual at closure. The original public comment period was from June 4, 2018 through September 7, 2018. This notice announces an extension of the public comment period on the Draft WIR Evaluation through November 7, 2018; any comments received after that date will be considered to the extent practical.

Federal Register, Volume 83 Issue 159 (Thursday, August 16, 2018)
[Federal Register Volume 83, Number 159 (Thursday, August 16, 2018)]
[Notices]
[Pages 40758-40759]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-17687]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY


Extension of Comment Period, Draft Waste Incidental To 
Reprocessing Evaluation for Closure of Waste Management Area C at the 
Hanford Site, Washington

AGENCY: U.S. Department of Energy.

ACTION: Extension of public comment period.

-----------------------------------------------------------------------

SUMMARY: On June 4, 2018, the U.S. Department of Energy (``DOE'') 
published in the Federal Register a Notice of Availability of the Draft 
Waste Incidental to Reprocessing Evaluation for Closure of Waste 
Management Area C at the Hanford Site, Washington (Draft WIR 
Evaluation), which evaluates whether the stabilized tanks and ancillary 
structures in WMA C, as well as the residual material in these tanks 
and structures will meet the criteria in Section II.B.(2)(a) of DOE M. 
435.1-1, Radioactive Waste Management Manual at closure. The original 
public comment period was from June 4, 2018 through September 7, 2018. 
This notice announces an extension of the public comment period on the 
Draft WIR Evaluation through November 7, 2018; any comments received 
after that date will be considered to the extent practical.

DATES: The comment period in the Notice of Availability, published on 
June 4, 2018 (83 FR 25657), is extended through November 7, 2018. Any 
comments received after that date will be considered to the extent 
practical.

ADDRESSES: Interested persons may submit comments by email to 
WMACDRAFTWIR@rl.gov. Alternately, written comments may also be sent by 
mail to: Mr. Jan Bovier, U.S. Department of Energy, Office of River 
Protection, P.O. Box 450, MSIN H6-60, Richland, WA 99354.

[[Page 40759]]

    The Draft WIR Evaluation is available on the internet at: https://www.hanford.gov/page.cfm/WasteManagementAreaC and is also publicly 
available for review at the following locations: U.S. DOE Public 
Reading Room, 1000 Independence Avenue SW, Washington, DC 20585, phone: 
(202) 586-5955, or fax: (202) 586-0575; and U.S. DOE Public Reading 
Room located at 2770 University Drive, Consolidated Information Center 
(CIC), Room 101L, Richland, WA 99354, phone: (509) 372-7303.

FOR FURTHER INFORMATION CONTACT: Mr. Jan Bovier by email at 
Jan_B_Bovier@orp.doe.gov, by mail at U.S. Department of Energy, Office 
of River Protection, P.O. Box 450, MSIN H6-60, Richland, WA 99354, or 
by phone at (509) 376-9630.

SUPPLEMENTARY INFORMATION: On June 4, 2018, DOE published in the 
Federal Register a notice of availability of the Draft WIR Evaluation 
for comment by States, Tribal Nations, and the public (83 FR 25657). 
The original public comment period was from June 4, 2018 through 
September 7, 2018.
    In response to several requests, DOE is extending the public 
comment period by 60 days, through November 7, 2018. DOE will consider 
comments received after that date to the extent practical.
    DOE will consider comments from States, Tribal Nations and the 
public, as well as NRC consultative recommendations, prior to 
finalizing DOE's analyses and prior to issuing a final WIR Evaluation. 
Based on the final WIR Evaluation, DOE may determine (in a WIR 
determination) whether the stabilized tanks, residuals and ancillary 
structures in WMA C at closure meet the criteria in Section II.B.(2)(a) 
of DOE M. 435.1-1, Radioactive Waste Management Manual, are not high-
level radioactive waste, and are to be managed as low-level radioactive 
waste.

    Signed in Washington, DC, on August 10, 2018.
Anne Marie White,
Assistant Secretary for Environmental Management.
[FR Doc. 2018-17687 Filed 8-15-18; 8:45 am]
 BILLING CODE 6450-01-P



                                                40758                       Federal Register / Vol. 83, No. 159 / Thursday, August 16, 2018 / Notices

                                                long-term multimodal transportation                     Commission (NCPC), the Virginia                         Pursuant to the requirements of the
                                                system for the Commonwealth of                          Department of Transportation (VDOT),                  National Environmental Policy Act of
                                                Virginia and Arlington County.                          and Arlington County. The ANC and the                 1969, as amended (NEPA), 42 U.S.C.
                                                DATES: The Draft EA is available for a                  USACE also considered the input of                    4321–4370, as implemented by the
                                                30-day review period. Written                           various stakeholder organizations and                 Council on Environmental Quality
                                                comments will be accepted until the                     the public.                                           Regulations (40 CFR parts 1500–1508),
                                                close of business on September 22,                        ANC is located within the eastern                   the ANC, as the lead federal agency, has
                                                2018.                                                   boundary of Arlington County, in the                  determined that the project does not
                                                                                                        northeastern corner of the                            have the potential to cause significant
                                                ADDRESSES: The public is invited to
                                                                                                        Commonwealth of Virginia, and at the                  impacts on the human environment,
                                                submit comments to Ms. Kathy Perdue,                    western terminus of Memorial Avenue,                  and has developed the Draft EA to
                                                Department of the Army, U.S. Army                       directly across the Arlington Memorial                examine and assess the impacts of the
                                                Corps of Engineers, Norfolk District,                   Bridge and the Potomac River from the                 Proposed Action.
                                                Planning and Policy Branch, 803 Front                   District of Columbia (Washington, DC).
                                                St., Norfolk, VA 23510 or via email:                                                                          Brenda S. Bowen,
                                                                                                        ANC is our nation’s most hallowed
                                                SouthernExpansion@usace.army.mil.                       ground. This Army cemetery consists of                Army Federal Register Liaison Officer.
                                                The Project title and the commenter’s                   624 acres and is the final resting place              [FR Doc. 2018–17573 Filed 8–15–18; 8:45 am]
                                                contact information should be included                  of over 400,000 service members and                   BILLING CODE 3720–58–P
                                                with submitted comments.                                their families. The proposed Southern
                                                FOR FURTHER INFORMATION CONTACT: Ms.                    Expansion site, bounded by Washington
                                                Kathy Perdue, (757) 201–7218.                           Boulevard (Route 27), I–395, the VDOT                 DEPARTMENT OF ENERGY
                                                SUPPLEMENTARY INFORMATION: As part of                   Maintenance Complex, the Foxcroft
                                                the public involvement process, notice                  Heights neighborhood, and the ANC,                    Extension of Comment Period, Draft
                                                is hereby given by the USACE Norfolk                    involves approximately 70 acres among                 Waste Incidental To Reprocessing
                                                District, on behalf of the ANC, of a                    three landowners: ANC, Arlington                      Evaluation for Closure of Waste
                                                public information meeting that will be                 County, and VDOT.                                     Management Area C at the Hanford
                                                held on August 22, 2018, from 5:00 to                     Proposed Action. The Proposed                       Site, Washington
                                                8:00 p.m., at the Sheraton Pentagon City                Action is to establish a single                       AGENCY:    U.S. Department of Energy.
                                                Hotel, 900 S Orme Street, Arlington, VA                 contiguous parcel of land south of the
                                                                                                        cemetery by closing and relocating local              ACTION:   Extension of public comment
                                                22204. The public information meeting                                                                         period.
                                                will allow participants the opportunity                 roadways and developing the parcel to
                                                to comment and ask questions on the                     increase interment capacity and                       SUMMARY:   On June 4, 2018, the U.S.
                                                Draft EA. Attendance at the public                      increase multimodal transportation                    Department of Energy (‘‘DOE’’)
                                                meeting is not necessary to provide                     capacity on Columbia Pike. The                        published in the Federal Register a
                                                comments. Written comments may also                     contiguous parcel would be created                    Notice of Availability of the Draft Waste
                                                be given to the contact listed under                    through the replacement of Southgate                  Incidental to Reprocessing Evaluation
                                                ADDRESSES.                                              Road with a new South Nash Street, and                for Closure of Waste Management Area
                                                   The document is available for review                 realignment of Columbia Pike and the                  C at the Hanford Site, Washington (Draft
                                                at the following locations:                             Columbia Pike/Washington Boulevard                    WIR Evaluation), which evaluates
                                                   (1) The USACE Norfolk District                       interchange (adjacent to the Pentagon).               whether the stabilized tanks and
                                                Arlington National Cemetery Southern                    The existing Air Force Memorial (AFM)                 ancillary structures in WMA C, as well
                                                Expansion website: http://www.nao                       would be incorporated into the                        as the residual material in these tanks
                                                .usace.army.mil/Missions/Military-                      cemetery expansion, and the existing                  and structures will meet the criteria in
                                                Construction/ANCSouthernExpansion/                      Operations Complex would be relocated                 Section II.B.(2)(a) of DOE M. 435.1–1,
                                                   (2) The ANC website: https://                        south of Columbia Pike.                               Radioactive Waste Management Manual
                                                www.arlingtoncemetery.mil/About/                          Alternatives. The Draft EA considers a              at closure. The original public comment
                                                Policies-and-Public-Notices/Public-                     full range of alternatives that meet the              period was from June 4, 2018 through
                                                Notices                                                 Proposed Action’s purpose and need,                   September 7, 2018. This notice
                                                   (3) Copies at the following Arlington                while avoiding and minimizing impacts
                                                                                                                                                              announces an extension of the public
                                                County, Virginia Public Libraries:                      to the maximum extent practicable.
                                                                                                                                                              comment period on the Draft WIR
                                                   a. Arlington County Central Library,                 Alternatives were developed that
                                                                                                                                                              Evaluation through November 7, 2018;
                                                1015 N Quincy Street, Arlington, VA                     leverage to varying degrees the Army-
                                                                                                                                                              any comments received after that date
                                                22201.                                                  owned land south of Columbia Pike to
                                                                                                                                                              will be considered to the extent
                                                   b. Aurora Hills Branch Public Library,               increase contiguous space for burials
                                                                                                                                                              practical.
                                                735 South 18th Street, Arlington, VA                    and cemetery operational effectiveness.
                                                22202.                                                  Alternatives considered in detail                     DATES: The comment period in the
                                                   c. Columbia Pike Branch Public                       included: (1) Relocate Operations                     Notice of Availability, published on
                                                Library, 816 South Walter Reed Drive,                   Complex Alternative (Preferred                        June 4, 2018 (83 FR 25657), is extended
                                                Arlington, VA 22204.                                    Alternative/Proposed Action); (2)                     through November 7, 2018. Any
                                                   The ANC is the lead federal agency                   Maintain Operations Complex with                      comments received after that date will
                                                for this Project, and the USACE has                     Tunnel Alternative; and (3) Maintain                  be considered to the extent practical.
                                                prepared the draft NEPA document on                                                                           ADDRESSES: Interested persons may
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                        Operations Complex without Tunnel
                                                its behalf, assisted by the HNTB                        Alternative.                                          submit comments by email to
                                                Corporation. The following are serving                    Public Involvement. A Notice of Intent              WMACDRAFTWIR@rl.gov. Alternately,
                                                as cooperating agencies during the                      to prepare an EA was published in the                 written comments may also be sent by
                                                NEPA process: Federal Highway                           Federal Register (81 FR 23281) on April               mail to: Mr. Jan Bovier, U.S. Department
                                                Administration (FHWA), the                              20, 2016. A public NEPA scoping                       of Energy, Office of River Protection,
                                                Environmental Protection Agency                         meeting was held on April 27, 2016, in                P.O. Box 450, MSIN H6–60, Richland,
                                                (EPA), the National Capital Planning                    Arlington County.                                     WA 99354.


                                           VerDate Sep<11>2014   17:15 Aug 15, 2018   Jkt 244001   PO 00000   Frm 00015   Fmt 4703   Sfmt 4703   E:\FR\FM\16AUN1.SGM   16AUN1


                                                                            Federal Register / Vol. 83, No. 159 / Thursday, August 16, 2018 / Notices                                           40759

                                                   The Draft WIR Evaluation is available                DEPARTMENT OF ENERGY                                  information are necessary for the proper
                                                on the internet at: https://                                                                                  performance of the functions of the
                                                www.hanford.gov/page.cfm/Waste                          Federal Energy Regulatory                             Commission, including whether the
                                                ManagementAreaC and is also publicly                    Commission                                            information will have practical utility;
                                                available for review at the following                   [Docket No. IC18–18–000]                              (2) the accuracy of the agency’s
                                                locations: U.S. DOE Public Reading                                                                            estimates of the burden and cost of the
                                                Room, 1000 Independence Avenue SW,                      Commission Information Collection                     collections of information, including the
                                                Washington, DC 20585, phone: (202)                      Activities (FERC–545 and FERC–549c);                  validity of the methodology and
                                                586–5955, or fax: (202) 586–0575; and                   Consolidated Comment Request;                         assumptions used; (3) ways to enhance
                                                                                                        Extension                                             the quality, utility and clarity of the
                                                U.S. DOE Public Reading Room located
                                                                                                                                                              information collections; and (4) ways to
                                                at 2770 University Drive, Consolidated                  AGENCY:  Federal Energy Regulatory                    minimize the burden of the collections
                                                Information Center (CIC), Room 101L,                    Commission, Department of Energy.                     of information on those who are to
                                                Richland, WA 99354, phone: (509) 372–                   ACTION: Notice of information                         respond, including the use of automated
                                                7303.                                                   collections and request for comments.                 collection techniques or other forms of
                                                FOR FURTHER INFORMATION CONTACT:     Mr.                                                                      information technology.
                                                                                                        SUMMARY:    In compliance with the
                                                Jan Bovier by email at Jan_B_Bovier@                                                                          FERC–545, Gas Pipeline Rates: Rate
                                                                                                        requirements of the Paperwork
                                                orp.doe.gov, by mail at U.S. Department                                                                       Change (Non-Formal)
                                                                                                        Reduction Act of 1995, the Federal
                                                of Energy, Office of River Protection,                  Energy Regulatory Commission                             Title: FERC–545, Gas Pipeline Rates:
                                                P.O. Box 450, MSIN H6–60, Richland,                     (Commission or FERC) is soliciting                    Rate Change (Non-formal).
                                                WA 99354, or by phone at (509) 376–                     public comment on the requirements                       OMB Control No.: 1902–0154.
                                                9630.                                                   and burden of the information                            Type of Request: Three-year extension
                                                                                                        collections described below.                          of the FERC–545 information collection
                                                SUPPLEMENTARY INFORMATION:       On June 4,                                                                   requirements with no changes to the
                                                2018, DOE published in the Federal                      DATES: Comments on the collections of
                                                                                                        information are due October 15, 2018.                 current reporting requirements.
                                                Register a notice of availability of the                                                                         Abstract: FERC–545 is required to
                                                Draft WIR Evaluation for comment by                     ADDRESSES: You may submit comments
                                                                                                                                                              implement sections 4, 5, and 16 of the
                                                States, Tribal Nations, and the public                  (identified by Docket No. IC18–18–000)                Natural Gas Act (NGA), (15 U.S.C. 717c–
                                                (83 FR 25657). The original public                      by either of the following methods:                   717o, PL 75 688, 52 Stat. 822 and 830).
                                                comment period was from June 4, 2018                       • eFiling at Commission’s Website:                 NGA sections 4, 5, and 16 authorize the
                                                through September 7, 2018.                              http://www.ferc.gov/docs-filing/                      Commission to inquire into rate
                                                                                                        efiling.asp.                                          structures and methodologies and to set
                                                   In response to several requests, DOE                    • Mail/Hand Delivery/Courier:
                                                is extending the public comment period                                                                        rates at a just and reasonable level.
                                                                                                        Federal Energy Regulatory Commission,                 Specifically, a natural gas company
                                                by 60 days, through November 7, 2018.                   Secretary of the Commission, 888 First
                                                DOE will consider comments received                                                                           must obtain Commission authorization
                                                                                                        Street NE, Washington, DC 20426.                      for all rates and charges made,
                                                after that date to the extent practical.                   Please reference the specific                      demanded, or received in connection
                                                   DOE will consider comments from                      collection number and/or title in your                with the transportation or sale of natural
                                                States, Tribal Nations and the public, as               comments.                                             gas in interstate commerce.
                                                well as NRC consultative                                   Instructions: All submissions must be                 Under the NGA, a natural gas
                                                recommendations, prior to finalizing                    formatted and filed in accordance with                company’s rates must be just and
                                                DOE’s analyses and prior to issuing a                   submission guidelines at: http://                     reasonable and not unduly
                                                final WIR Evaluation. Based on the final                www.ferc.gov/help/submission-                         discriminatory or preferential. The
                                                WIR Evaluation, DOE may determine (in                   guide.asp. For user assistance contact                Commission may act under different
                                                                                                        FERC Online Support by email at                       sections of the NGA to effect a change
                                                a WIR determination) whether the
                                                                                                        ferconlinesupport@ferc.gov, or by phone               in a natural gas company’s rates. When
                                                stabilized tanks, residuals and ancillary
                                                                                                        at: (866) 208–3676 (toll-free), or (202)              the Commission reviews rate increases
                                                structures in WMA C at closure meet the                 502–8659 for TTY.
                                                criteria in Section II.B.(2)(a) of DOE M.                                                                     that a natural gas company has
                                                                                                           Docket: Users interested in receiving              proposed, it is subject to the
                                                435.1–1, Radioactive Waste                              automatic notification of activity in this
                                                Management Manual, are not high-level                                                                         requirement of section 4(e) of the NGA.
                                                                                                        docket or in viewing/downloading                      Under section 4(e), the natural gas
                                                radioactive waste, and are to be                        comments and issuances in this docket
                                                managed as low-level radioactive waste.                                                                       company bears the burden of proving
                                                                                                        may do so at http://www.ferc.gov/docs-                that its proposed rates are just and
                                                  Signed in Washington, DC, on August 10,               filing/docs-filing.asp.                               reasonable. On the other hand, when the
                                                2018.                                                   FOR FURTHER INFORMATION CONTACT:                      Commission seeks to impose its own
                                                Anne Marie White,                                       Ellen Brown may be reached by email                   rate determination, it must do so in
                                                Assistant Secretary for Environmental                   at DataClearance@FERC.gov, telephone                  compliance with section 5(a) of the
                                                Management.                                             at (202) 502–8663, and fax at (202) 273–              NGA. Under section 5, the Commission
                                                [FR Doc. 2018–17687 Filed 8–15–18; 8:45 am]
                                                                                                        0873.                                                 must first establish that its alternative
                                                BILLING CODE 6450–01–P
                                                                                                        SUPPLEMENTARY INFORMATION:                            rate proposal is both just and
                                                                                                           Type of Request: Three-year extension
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                                                                              reasonable.
                                                                                                        of the information collection                            Section 16 of the NGA states that the
                                                                                                        requirements for all collections                      Commission ‘‘shall have the power to
                                                                                                        described below with no changes to the                perform any and all acts, and to
                                                                                                        current reporting requirements. Please                prescribe, issue, make, amend, and
                                                                                                        note the two collections are distinct.                rescind such orders, rules, and
                                                                                                           Comments: Comments are invited on:                 regulations as it may find necessary or
                                                                                                        (1) Whether the collections of                        appropriate to carry out provisions of


                                           VerDate Sep<11>2014   17:15 Aug 15, 2018   Jkt 244001   PO 00000   Frm 00016   Fmt 4703   Sfmt 4703   E:\FR\FM\16AUN1.SGM   16AUN1



Document Created: 2018-08-16 01:02:36
Document Modified: 2018-08-16 01:02:36
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionExtension of public comment period.
DatesThe comment period in the Notice of Availability, published on June 4, 2018 (83 FR 25657), is extended through November 7, 2018. Any comments received after that date will be considered to the extent practical.
ContactMr. Jan Bovier by email at [email protected], by mail at U.S. Department of Energy, Office of River Protection, P.O. Box 450, MSIN H6-60, Richland, WA 99354, or by phone at (509) 376-9630.
FR Citation83 FR 40758 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR