83_FR_45601 83 FR 45427 - Notice of Schedule for Environmental Review of the Rio Grande LNG, LLC and Rio Bravo Pipeline Company, LLC Rio Grande LNG Project

83 FR 45427 - Notice of Schedule for Environmental Review of the Rio Grande LNG, LLC and Rio Bravo Pipeline Company, LLC Rio Grande LNG Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 174 (September 7, 2018)

Page Range45427-45428
FR Document2018-19398

Federal Register, Volume 83 Issue 174 (Friday, September 7, 2018)
[Federal Register Volume 83, Number 174 (Friday, September 7, 2018)]
[Notices]
[Pages 45427-45428]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-19398]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP16-454-000; CP16-455-000]


Notice of Schedule for Environmental Review of the Rio Grande 
LNG, LLC and Rio Bravo Pipeline Company, LLC Rio Grande LNG Project

    On May 5, 2016, Rio Grande LNG, LLC (RG LNG) filed an application 
in Docket No. CP16-454-000 requesting authorization pursuant to Section 
3(a) of the Natural Gas Act (NGA) to construct and operate liquefied 
natural gas (LNG) export facilities. On the same day, Rio Bravo 
Pipeline Company, LLC (RB Pipeline) filed an application in Docket No. 
CP16-455-000, requesting a Certificate of Public Convenience and 
Necessity pursuant to Section 7(c) of the NGA to construct, operate, 
and maintain certain natural gas pipeline facilities. The combined 
projects, collectively referred to as the Rio Grande LNG Project, would 
provide gas and processing to produce up to 27 million tons per annum 
of LNG for export. On August 17, 2016, in Order No. 3869, the U.S. 
Department of Energy, Office of Fossil Energy, granted to RG LNG a 
long-term, multi-contract authorization to export LNG to Free Trade 
Agreement nations.
    On May 19, 2016, the Federal Energy Regulatory Commission (FERC or 
Commission) issued its Notice of Application for the project. Among 
other things, that notice alerted other agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on the request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's final 
Environmental Impact Statement (EIS) for the Rio Grande LNG Project. 
This instant notice identifies the FERC staff's planned schedule for 
completion of the final EIS for the project, which is based on an 
issuance of the draft EIS in October 2018. The forecasted schedule for 
both the draft and final EIS is based upon RG LNG and RB Pipeline 
providing complete and timely responses to any future data requests. In 
addition, the schedule assumes that the cooperating agencies will 
provide input on their areas of responsibility on a timely basis.

Schedule for Environmental Review

Issuance of Notice of Availability of the final EIS--April 26, 2019

90-Day Federal Authorization Decision Deadline--July 25, 2019

    If a schedule change becomes necessary for the final EIS, an 
additional notice will be provided so that the relevant agencies are 
kept informed of the project's progress.

Project Description

    RG LNG and RB Pipeline, collectively the Rio Grande Developers (RG 
Developers), propose to construct and operate natural gas pipelines and 
liquefaction facilities in Jim Wells, Kleberg, Kenedy, Willacy, and 
Cameron Counties, Texas. The Rio Bravo Pipeline would include two new 
parallel 42-inch-diameter natural gas pipelines, each about 135.5 miles 
long, capable of transporting 4.5 billion cubic feet per day of natural 
gas. In addition, a 2.4-mile-long header system at the origin of the 
pipelines would interconnect with existing natural gas transmission 
pipelines. The pipeline facilities would include three new compressor 
stations in Kleberg, Kenedy, and Cameron Counties and two new 
interconnect booster stations in Kenedy County.
    The Rio Grande LNG Terminal would be located on 750.4 acres of an 
approximately 1,000-acre site along the Brownsville Ship Channel about 
5.5 miles inland from the channel entrance, in Cameron County, Texas. 
The terminal would include six liquefaction trains capable of producing 
27 million tons per annum of LNG; marine facilities, including two LNG 
berths, a turning basin, and a material offloading facility; truck 
loading and unloading facilities for LNG and natural gas liquids; and 
four LNG storage tanks. If approved, RG Developers would construct the 
project in stages. Operation of the first liquefaction train, and one 
of the two parallel pipelines, is proposed to begin during the fourth 
quarter of 2021; operation of the full project is proposed for early 
2025.

Background

    On April 13, 2015, the Commission staff granted the RG Developers' 
request to use the FERC's Pre-filing environmental review process. On 
July 23, 2015, the Commission issued a Notice of Intent to Prepare an 
Environmental Impact Statement for the Planned Rio Grande LNG Project 
and Rio Bravo Pipeline Project, Request for Comments on Environmental 
Issues, and Notice of Public Scoping Meetings (NOI) in Docket No. PF15-
20-000. The NOI was issued during the pre-filing review of the project, 
and was sent to federal, state, and local government agencies; elected 
officials; affected landowners; environmental and public interest 
groups; Native American tribes and regional organizations; commentors 
and other interested parties; and local libraries and newspapers. Major 
issues raised during scoping include impacts on wildlife and wildlife 
habitat (including threatened and endangered species), aquatic 
resources, surface water, wetlands, public lands, visual resources, 
local ecotourism, public health and safety, air and noise quality, and 
cumulative impacts.
    The U.S Coast Guard, U.S. Department of Energy, U.S Department of 
Transportation, U.S. Environmental Protection Agency, U.S. Army Corps 
of Engineers, U.S. Fish and Wildlife Service, National Marine Fisheries 
Service, National Park Service, and Federal Aviation Administration are 
cooperating agencies in the preparation of the EIS.

[[Page 45428]]

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP16-454 or CP16-455), 
and follow the instructions. For assistance with access to eLibrary, 
the helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or 
at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website 
also provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-19398 Filed 9-6-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                           Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices                                           45427

                                                 The U.S. Department of                                NGA to construct, operate, and maintain               include three new compressor stations
                                               Transportation, U.S. Environmental                      certain natural gas pipeline facilities.              in Kleberg, Kenedy, and Cameron
                                               Protection Agency, and U.S. Department                  The combined projects, collectively                   Counties and two new interconnect
                                               of Energy are cooperating agencies in                   referred to as the Rio Grande LNG                     booster stations in Kenedy County.
                                               the preparation of the EA.                              Project, would provide gas and                           The Rio Grande LNG Terminal would
                                               Additional Information                                  processing to produce up to 27 million                be located on 750.4 acres of an
                                                                                                       tons per annum of LNG for export. On
                                                  In order to receive notification of the                                                                    approximately 1,000-acre site along the
                                                                                                       August 17, 2016, in Order No. 3869, the
                                               issuance of the EA and to keep track of                                                                       Brownsville Ship Channel about 5.5
                                                                                                       U.S. Department of Energy, Office of
                                               all formal issuances and submittals in                                                                        miles inland from the channel entrance,
                                                                                                       Fossil Energy, granted to RG LNG a
                                               specific dockets, the Commission offers                                                                       in Cameron County, Texas. The terminal
                                                                                                       long-term, multi-contract authorization
                                               a free service called eSubscription. This               to export LNG to Free Trade Agreement                 would include six liquefaction trains
                                               can reduce the amount of time you                       nations.                                              capable of producing 27 million tons
                                               spend researching proceedings by                           On May 19, 2016, the Federal Energy                per annum of LNG; marine facilities,
                                               automatically providing you with                        Regulatory Commission (FERC or                        including two LNG berths, a turning
                                               notification of these filings, document                 Commission) issued its Notice of                      basin, and a material offloading facility;
                                               summaries, and direct links to the                      Application for the project. Among                    truck loading and unloading facilities
                                               documents. Go to www.ferc.gov/docs-                     other things, that notice alerted other               for LNG and natural gas liquids; and
                                               filing/esubscription.asp.                               agencies issuing federal authorizations               four LNG storage tanks. If approved, RG
                                                  Additional information about the                     of the requirement to complete all                    Developers would construct the project
                                               Project is available from the                           necessary reviews and to reach a final                in stages. Operation of the first
                                               Commission’s Office of External Affairs                 decision on the request for a federal                 liquefaction train, and one of the two
                                               at (866) 208–FERC or on the FERC                                                                              parallel pipelines, is proposed to begin
                                                                                                       authorization within 90 days of the date
                                               website (www.ferc.gov). Using the                                                                             during the fourth quarter of 2021;
                                                                                                       of issuance of the Commission staff’s
                                               eLibrary link, select General Search                                                                          operation of the full project is proposed
                                                                                                       final Environmental Impact Statement
                                               from the eLibrary menu, enter the                                                                             for early 2025.
                                                                                                       (EIS) for the Rio Grande LNG Project.
                                               selected date range and Docket Number
                                                                                                       This instant notice identifies the FERC               Background
                                               excluding the last three digits (i.e.,
                                                                                                       staff’s planned schedule for completion
                                               CP17–470), and follow the instructions.
                                                                                                       of the final EIS for the project, which is               On April 13, 2015, the Commission
                                               For assistance with access to eLibrary,
                                                                                                       based on an issuance of the draft EIS in              staff granted the RG Developers’ request
                                               the helpline can be reached at (866)
                                                                                                       October 2018. The forecasted schedule                 to use the FERC’s Pre-filing
                                               208–3676, TTY (202) 502–8659, or at
                                                                                                       for both the draft and final EIS is based             environmental review process. On July
                                               FERCOnlineSupport@ferc.gov.
                                                  The eLibrary link on the FERC                        upon RG LNG and RB Pipeline                           23, 2015, the Commission issued a
                                               website also provides access to the texts               providing complete and timely                         Notice of Intent to Prepare an
                                               of formal documents issued by the                       responses to any future data requests. In             Environmental Impact Statement for the
                                               Commission, such as orders, notices,                    addition, the schedule assumes that the               Planned Rio Grande LNG Project and
                                               and rule makings.                                       cooperating agencies will provide input               Rio Bravo Pipeline Project, Request for
                                                                                                       on their areas of responsibility on a                 Comments on Environmental Issues,
                                                 Dated: August 31, 2018.                               timely basis.
                                               Nathaniel J. Davis, Sr.,
                                                                                                                                                             and Notice of Public Scoping Meetings
                                                                                                       Schedule for Environmental Review                     (NOI) in Docket No. PF15–20–000. The
                                               Deputy Secretary.
                                                                                                                                                             NOI was issued during the pre-filing
                                               [FR Doc. 2018–19402 Filed 9–6–18; 8:45 am]              Issuance of Notice of Availability of the
                                                                                                                                                             review of the project, and was sent to
                                               BILLING CODE 6717–01–P                                     final EIS—April 26, 2019
                                                                                                                                                             federal, state, and local government
                                                                                                       90-Day Federal Authorization Decision                 agencies; elected officials; affected
                                                                                                          Deadline—July 25, 2019                             landowners; environmental and public
                                               DEPARTMENT OF ENERGY
                                                                                                          If a schedule change becomes                       interest groups; Native American tribes
                                               Federal Energy Regulatory                               necessary for the final EIS, an additional            and regional organizations; commentors
                                               Commission                                              notice will be provided so that the                   and other interested parties; and local
                                                                                                       relevant agencies are kept informed of                libraries and newspapers. Major issues
                                               [Docket Nos. CP16–454–000; CP16–455–                    the project’s progress.
                                               000]                                                                                                          raised during scoping include impacts
                                                                                                       Project Description                                   on wildlife and wildlife habitat
                                               Notice of Schedule for Environmental                                                                          (including threatened and endangered
                                                                                                          RG LNG and RB Pipeline, collectively               species), aquatic resources, surface
                                               Review of the Rio Grande LNG, LLC
                                                                                                       the Rio Grande Developers (RG                         water, wetlands, public lands, visual
                                               and Rio Bravo Pipeline Company, LLC
                                                                                                       Developers), propose to construct and                 resources, local ecotourism, public
                                               Rio Grande LNG Project
                                                                                                       operate natural gas pipelines and
                                                                                                                                                             health and safety, air and noise quality,
                                                 On May 5, 2016, Rio Grande LNG,                       liquefaction facilities in Jim Wells,
                                                                                                                                                             and cumulative impacts.
                                               LLC (RG LNG) filed an application in                    Kleberg, Kenedy, Willacy, and Cameron
                                               Docket No. CP16–454–000 requesting                      Counties, Texas. The Rio Bravo Pipeline                  The U.S Coast Guard, U.S.
                                               authorization pursuant to Section 3(a) of               would include two new parallel 42-                    Department of Energy, U.S Department
                                               the Natural Gas Act (NGA) to construct                  inch-diameter natural gas pipelines,                  of Transportation, U.S. Environmental
daltland on DSKBBV9HB2PROD with NOTICES




                                               and operate liquefied natural gas (LNG)                 each about 135.5 miles long, capable of               Protection Agency, U.S. Army Corps of
                                               export facilities. On the same day, Rio                 transporting 4.5 billion cubic feet per               Engineers, U.S. Fish and Wildlife
                                               Bravo Pipeline Company, LLC (RB                         day of natural gas. In addition, a 2.4-               Service, National Marine Fisheries
                                               Pipeline) filed an application in Docket                mile-long header system at the origin of              Service, National Park Service, and
                                               No. CP16–455–000, requesting a                          the pipelines would interconnect with                 Federal Aviation Administration are
                                               Certificate of Public Convenience and                   existing natural gas transmission                     cooperating agencies in the preparation
                                               Necessity pursuant to Section 7(c) of the               pipelines. The pipeline facilities would              of the EIS.


                                          VerDate Sep<11>2014   17:55 Sep 06, 2018   Jkt 244001   PO 00000   Frm 00017   Fmt 4703   Sfmt 4703   E:\FR\FM\07SEN1.SGM   07SEN1


                                               45428                       Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices

                                               Additional Information                                  decision-making process to determine                  However, if the Commission approves
                                                  In order to receive notification of the              whether the project is in the public                  the project, that approval conveys with
                                               issuance of the EIS and to keep track of                convenience and necessity.                            it the right of eminent domain.
                                                                                                          This notice announces the opening of               Therefore, if you and the company do
                                               all formal issuances and submittals in
                                                                                                       the scoping process the Commission                    not reach an easement agreement, the
                                               specific dockets, the Commission offers
                                                                                                       will use to gather input from the public              pipeline company could initiate
                                               a free service called eSubscription. This
                                                                                                       and interested agencies about issues                  condemnation proceedings in court. In
                                               can reduce the amount of time you
                                                                                                       regarding the project. The National                   such instances, compensation would be
                                               spend researching proceedings by
                                                                                                       Environmental Policy Act (NEPA)                       determined by a judge in accordance
                                               automatically providing you with
                                                                                                       requires the Commission to take into                  with state law.
                                               notification of these filings, document
                                                                                                       account the environmental impacts that                   Gulf South provided landowners with
                                               summaries, and direct links to the
                                                                                                       could result from its action whenever it              a fact sheet prepared by the FERC
                                               documents. Go to www.ferc.gov/docs-
                                                                                                       considers the issuance of a Certificate of            entitled ‘‘An Interstate Natural Gas
                                               filing/esubscription.asp.
                                                                                                       Public Convenience and Necessity.                     Facility On My Land? What Do I Need
                                                  Additional information about the
                                                                                                       NEPA also requires the Commission to                  To Know?’’ This fact sheet addresses a
                                               project is available from the
                                                                                                       discover concerns the public may have                 number of typically asked questions,
                                               Commission’s Office of External Affairs
                                                                                                       about proposals. This process is referred             including the use of eminent domain
                                               at (866) 208–FERC or on the FERC
                                                                                                       to as ‘‘scoping.’’ The main goal of the               and how to participate in the
                                               website (www.ferc.gov). Using the
                                                                                                       scoping process is to focus the analysis              Commission’s proceedings. It is also
                                               eLibrary link, select General Search
                                                                                                       in the EA on the important                            available for viewing on the FERC
                                               from the eLibrary menu, enter the
                                                                                                       environmental issues. By this notice, the             website (www.ferc.gov).
                                               selected date range and Docket Number
                                                                                                       Commission requests public comments
                                               excluding the last three digits (i.e.,                                                                        Public Participation
                                                                                                       on the scope of the issues to address in
                                               CP16–454 or CP16–455), and follow the
                                                                                                       the EA. To ensure that your comments                     For your convenience, there are three
                                               instructions. For assistance with access
                                                                                                       are timely and properly recorded, please              methods you can use to submit your
                                               to eLibrary, the helpline can be reached
                                                                                                       submit your comments so that the                      comments to the Commission. The
                                               at (866) 208–3676, TTY (202) 502–8659,
                                                                                                       Commission receives them in                           Commission encourages electronic filing
                                               or at FERCOnlineSupport@ferc.gov. The
                                                                                                       Washington, DC on or before 5:00 p.m.                 of comments and has staff available to
                                               eLibrary link on the FERC website also
                                                                                                       Eastern Time on October 1, 2018.                      assist you at (866) 208–3676 or
                                               provides access to the texts of formal                     You can make a difference by
                                               documents issued by the Commission,                                                                           FercOnlineSupport@ferc.gov. Please
                                                                                                       submitting your specific comments or                  carefully follow these instructions so
                                               such as orders, notices, and rule                       concerns about the project. Your
                                               makings.                                                                                                      that your comments are properly
                                                                                                       comments should focus on the potential                recorded.
                                                 Dated: August 31, 2018.                               environmental effects, reasonable
                                                                                                                                                                (1) You can file your comments
                                               Nathaniel J. Davis, Sr.,                                alternatives, and measures to avoid or
                                                                                                                                                             electronically using the eComment
                                               Deputy Secretary.                                       lessen environmental impacts. Your
                                                                                                                                                             feature, which is located on the
                                               [FR Doc. 2018–19398 Filed 9–6–18; 8:45 am]              input will help the Commission staff
                                                                                                                                                             Commission’s website (www.ferc.gov)
                                                                                                       determine what issues they need to
                                               BILLING CODE 6717–01–P                                                                                        under the link to Documents and
                                                                                                       evaluate in the EA. Commission staff
                                                                                                                                                             Filings. Using eComment is an easy
                                                                                                       will consider and address all filed
                                                                                                                                                             method for submitting brief, text-only
                                               DEPARTMENT OF ENERGY                                    comments during the preparation of the
                                                                                                                                                             comments on a project;
                                                                                                       EA.
                                               Federal Energy Regulatory                                  If you sent comments on this project                  (2) You can file your comments
                                               Commission                                              to the Commission before the opening of               electronically by using the eFiling
                                                                                                       this docket on July 13, 2018, you will                feature, which is located on the
                                               [Docket No. CP18–525–000]                                                                                     Commission’s website (www.ferc.gov)
                                                                                                       need to file those comments in Docket
                                                                                                       No. CP18–525–000 to ensure they are                   under the link to Documents and
                                               Notice of Intent To Prepare an
                                                                                                       considered as part of this proceeding.                Filings. With eFiling, you can provide
                                               Environmental Assessment for the
                                                                                                          This notice is being sent to the                   comments in a variety of formats by
                                               Proposed Gulf South Pipeline
                                                                                                       Commission’s current environmental                    attaching them as a file with your
                                               Company, LP Willis Lateral Project,
                                                                                                       mailing list for this project. State and              submission. New eFiling users must
                                               and Request for Comments on
                                                                                                       local government representatives should               first create an account by clicking on
                                               Environmental Issues
                                                                                                       notify their constituents of this                     ‘‘eRegister.’’ You will be asked to select
                                                 The staff of the Federal Energy                       proposed project and encourage them to                the type of filing you are making; a
                                               Regulatory Commission (FERC or                          comment on their areas of concern.                    comment on a particular project is
                                               Commission) will prepare an                                If you are a landowner receiving this              considered a ‘‘Comment on a Filing’’; or
                                               environmental assessment (EA) that will                 notice, a pipeline company                               (3) You can file a paper copy of your
                                               discuss the environmental impacts of                    representative may contact you about                  comments by mailing them to the
                                               the Willis Lateral Project involving                    the acquisition of an easement to                     following address. Be sure to reference
                                               construction and operation of facilities                construct, operate, and maintain the                  the project docket number (CP18–525–
                                               by Gulf South Pipeline Company, LP                      proposed facilities. The company would                000) with your submission: Kimberly D.
                                               (Gulf South) in Montgomery and San                      seek to negotiate a mutually acceptable               Bose, Secretary, Federal Energy
daltland on DSKBBV9HB2PROD with NOTICES




                                               Jacinto Counties, Texas. The                            easement agreement. You are not                       Regulatory Commission, 888 First Street
                                               Commission will use this EA in its                      required to enter into an agreement.                  NE, Room 1A, Washington, DC 20426.




                                          VerDate Sep<11>2014   17:55 Sep 06, 2018   Jkt 244001   PO 00000   Frm 00018   Fmt 4703   Sfmt 4703   E:\FR\FM\07SEN1.SGM   07SEN1



Document Created: 2018-09-07 00:15:28
Document Modified: 2018-09-07 00:15:28
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 45427 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR