DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 174 (September 7, 2018)

Page Range45433-45433
FR Document2018-19406

Federal Register, Volume 83 Issue 174 (Friday, September 7, 2018)
[Federal Register Volume 83, Number 174 (Friday, September 7, 2018)]
[Notices]
[Page 45433]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-19406]



[[Page 45433]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP18-512-000, CP18-513-000]


Corpus Christi Liquefaction Stage III, LLC; Corpus Christi 
Liquefaction, LLC; and Cheniere Corpus Christi Pipeline, L.P.; Notice 
of Schedule for Environmental Review of the Stage 3 Project

    On June 28, 2018, Corpus Christi Liquefaction Stage III, LLC and 
Corpus Christi Liquefaction, LLC (collectively with Cheniere Corpus 
Christi Pipeline, L.P. referred to as Cheniere) filed an application in 
Docket No. CP18-512-000 requesting an authorization for siting, 
construction, and operation of a liquefied natural gas (LNG) export 
facility pursuant to Section 3(a) of the Natural Gas Act (NGA). On the 
same day, Cheniere Corpus Christi Pipeline, L.P. filed an application 
in Docket No. CP18-513-000 requesting a Certificate of Public 
Convenience and Necessity pursuant to Section 7(c) of the NGA to 
construct, operate, and maintain certain natural gas pipeline 
facilities. Combined, the proposed project is known as the Stage 3 
Project (Project) and would provide gas and processing to produce up to 
11.45 million tonnes per annum of LNG for export.
    On July 12, 2018, the Federal Energy Regulatory Commission (FERC or 
Commission) issued its Notice of Application for the Project. Among 
other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on the request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for completion of the EA 
for the Project. The forecasted schedule for the EA is based upon 
Cheniere providing complete and timely responses to any data requests. 
In addition, the schedule assumes that the cooperating agencies will 
provide input on their areas of responsibility on a timely basis.

Schedule for Environmental Review

Issuance of EA: February 8, 2019
90-Day Federal Authorization Decision Deadline: May 9, 2019

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Cheniere proposes to install seven mid-scale liquefaction trains 
and one new LNG storage tank expanding the previously authorized and 
currently under construction Corpus Christi Liquefaction Project in 
Nueces County, Texas. The proposed LNG facilities would be located 
primarily within areas previously disturbed for construction and/or 
operation of the Corpus Christi Liquefaction Project. Cheniere would 
also construct a new 21-mile-long, 42-inch-diameter natural gas 
pipeline from the recently completed Sinton Compressor Station (FERC 
Docket No. CP12-508-000) to the proposed Stage 3 liquefaction 
facilities, all of which would be located within Nueces County, Texas. 
The Project would also include the addition of two compressor units 
totaling approximately 44,000 horsepower at the Sinton Compressor 
Station. No new marine facilities would be installed as part of the 
Project; however, Cheniere anticipates that an annual increase of 100 
LNG carriers would utilize the LNG terminal during operation of the 
Project.

Background

    On June 9, 2015, the Commission staff granted Cheniere's request to 
use the FERC's pre-filing environmental review process and assigned the 
Stage 3 Project Docket No. PF15-26-000. On August 17, 2015, the 
Commission issued a Notice of Intent to Prepare an Environmental 
Assessment for the Planned Stage 3 Project, and Request for Comments on 
Environmental Issues (NOI). The NOI was issued during the pre-filing 
review of the Project in Docket No. PF15-26-000 and was sent to 
federal, state, and local government agencies; elected officials; 
affected landowners; environmental and public interest groups; Native 
American tribes and regional organizations; commenters and other 
interested parties; and local libraries and newspapers. In response to 
the NOI, the Commission received comments from the U.S. Fish and 
Wildlife Service, U.S. Environmental Protection Agency, Tonkawa Tribe 
of Oklahoma, Federal Emergency Management Agency, and Texas Parks and 
Wildlife Department. The primary issues raised by the commenters 
include effects on threatened and endangered species and vegetation, 
water quality impacts, greenhouse gas emissions, and cumulative 
impacts.
    The U.S. Department of Transportation Pipeline and Hazardous 
Materials Administration, U.S. Coast Guard, U.S. Department of Energy, 
U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service, and U.S. 
Environmental Protection Agency are cooperating agencies in the 
preparation of the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP18-512 and CP18-513), 
and follow the instructions. For assistance with access to eLibrary, 
the helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or 
at FERCOnlin[email protected]. The eLibrary link on the FERC website 
also provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rulemakings.

    Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-19406 Filed 9-6-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                           Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices                                                 45433

                                               DEPARTMENT OF ENERGY                                    Project Description                                   Wildlife Service, and U.S.
                                                                                                          Cheniere proposes to install seven                 Environmental Protection Agency are
                                               Federal Energy Regulatory                                                                                     cooperating agencies in the preparation
                                                                                                       mid-scale liquefaction trains and one
                                               Commission                                                                                                    of the EA.
                                                                                                       new LNG storage tank expanding the
                                               [Docket Nos. CP18–512–000, CP18–513–                    previously authorized and currently                   Additional Information
                                               000]                                                    under construction Corpus Christi
                                                                                                                                                                In order to receive notification of the
                                                                                                       Liquefaction Project in Nueces County,
                                               Corpus Christi Liquefaction Stage III,                                                                        issuance of the EA and to keep track of
                                                                                                       Texas. The proposed LNG facilities
                                               LLC; Corpus Christi Liquefaction, LLC;                                                                        all formal issuances and submittals in
                                                                                                       would be located primarily within areas
                                               and Cheniere Corpus Christi Pipeline,                                                                         specific dockets, the Commission offers
                                                                                                       previously disturbed for construction
                                               L.P.; Notice of Schedule for                                                                                  a free service called eSubscription. This
                                                                                                       and/or operation of the Corpus Christi
                                               Environmental Review of the Stage 3                                                                           can reduce the amount of time you
                                                                                                       Liquefaction Project. Cheniere would
                                               Project                                                                                                       spend researching proceedings by
                                                                                                       also construct a new 21-mile-long, 42-
                                                                                                                                                             automatically providing you with
                                                  On June 28, 2018, Corpus Christi                     inch-diameter natural gas pipeline from
                                                                                                                                                             notification of these filings, document
                                               Liquefaction Stage III, LLC and Corpus                  the recently completed Sinton
                                                                                                                                                             summaries, and direct links to the
                                               Christi Liquefaction, LLC (collectively                 Compressor Station (FERC Docket No.
                                                                                                                                                             documents. Go to www.ferc.gov/docs-
                                               with Cheniere Corpus Christi Pipeline,                  CP12–508–000) to the proposed Stage 3
                                                                                                                                                             filing/esubscription.asp.
                                               L.P. referred to as Cheniere) filed an                  liquefaction facilities, all of which
                                                                                                                                                                Additional information about the
                                               application in Docket No. CP18–512–                     would be located within Nueces
                                                                                                                                                             Project is available from the
                                               000 requesting an authorization for                     County, Texas. The Project would also
                                                                                                                                                             Commission’s Office of External Affairs
                                               siting, construction, and operation of a                include the addition of two compressor
                                                                                                                                                             at (866) 208–FERC or on the FERC
                                               liquefied natural gas (LNG) export                      units totaling approximately 44,000
                                                                                                                                                             website (www.ferc.gov). Using the
                                               facility pursuant to Section 3(a) of the                horsepower at the Sinton Compressor
                                                                                                                                                             eLibrary link, select General Search
                                               Natural Gas Act (NGA). On the same                      Station. No new marine facilities would
                                                                                                                                                             from the eLibrary menu, enter the
                                               day, Cheniere Corpus Christi Pipeline,                  be installed as part of the Project;
                                                                                                                                                             selected date range and Docket Number
                                               L.P. filed an application in Docket No.                 however, Cheniere anticipates that an
                                                                                                                                                             excluding the last three digits (i.e.,
                                               CP18–513–000 requesting a Certificate                   annual increase of 100 LNG carriers
                                                                                                                                                             CP18–512 and CP18–513), and follow
                                               of Public Convenience and Necessity                     would utilize the LNG terminal during
                                                                                                                                                             the instructions. For assistance with
                                               pursuant to Section 7(c) of the NGA to                  operation of the Project.
                                                                                                                                                             access to eLibrary, the helpline can be
                                               construct, operate, and maintain certain                Background                                            reached at (866) 208–3676, TTY (202)
                                               natural gas pipeline facilities.                                                                              502–8659, or at FERCOnlineSupport@
                                               Combined, the proposed project is                          On June 9, 2015, the Commission staff
                                                                                                       granted Cheniere’s request to use the                 ferc.gov. The eLibrary link on the FERC
                                               known as the Stage 3 Project (Project)                                                                        website also provides access to the texts
                                               and would provide gas and processing                    FERC’s pre-filing environmental review
                                                                                                       process and assigned the Stage 3 Project              of formal documents issued by the
                                               to produce up to 11.45 million tonnes                                                                         Commission, such as orders, notices,
                                               per annum of LNG for export.                            Docket No. PF15–26–000. On August
                                                                                                       17, 2015, the Commission issued a                     and rulemakings.
                                                  On July 12, 2018, the Federal Energy
                                               Regulatory Commission (FERC or                          Notice of Intent to Prepare an                          Dated: August 31, 2018.
                                               Commission) issued its Notice of                        Environmental Assessment for the                      Nathaniel J. Davis, Sr.,
                                               Application for the Project. Among                      Planned Stage 3 Project, and Request for              Deputy Secretary.
                                               other things, that notice alerted agencies              Comments on Environmental Issues                      [FR Doc. 2018–19406 Filed 9–6–18; 8:45 am]
                                               issuing federal authorizations of the                   (NOI). The NOI was issued during the                  BILLING CODE 6717–01–P
                                               requirement to complete all necessary                   pre-filing review of the Project in Docket
                                               reviews and to reach a final decision on                No. PF15–26–000 and was sent to
                                               the request for a federal authorization                 federal, state, and local government                  DEPARTMENT OF ENERGY
                                               within 90 days of the date of issuance                  agencies; elected officials; affected
                                               of the Commission staff’s Environmental                 landowners; environmental and public                  Federal Energy Regulatory
                                               Assessment (EA) for the Project. This                   interest groups; Native American tribes               Commission
                                               instant notice identifies the FERC staff’s              and regional organizations; commenters
                                                                                                                                                             [Docket No. CP18–45–000]
                                               planned schedule for completion of the                  and other interested parties; and local
                                               EA for the Project. The forecasted                      libraries and newspapers. In response to              Notice of Availability of the
                                               schedule for the EA is based upon                       the NOI, the Commission received                      Environmental Assessment for the
                                               Cheniere providing complete and timely                  comments from the U.S. Fish and                       Proposed Dominion Energy
                                               responses to any data requests. In                      Wildlife Service, U.S. Environmental                  Transmission, Inc. Sweden Valley
                                               addition, the schedule assumes that the                 Protection Agency, Tonkawa Tribe of                   Project
                                               cooperating agencies will provide input                 Oklahoma, Federal Emergency
                                               on their areas of responsibility on a                   Management Agency, and Texas Parks                      The staff of the Federal Energy
                                               timely basis.                                           and Wildlife Department. The primary                  Regulatory Commission (FERC or
                                                                                                       issues raised by the commenters include               Commission) has prepared an
                                               Schedule for Environmental Review                       effects on threatened and endangered                  environmental assessment (EA) for the
                                               Issuance of EA: February 8, 2019                        species and vegetation, water quality                 Sweden Valley Project (Project),
daltland on DSKBBV9HB2PROD with NOTICES




                                               90-Day Federal Authorization Decision                   impacts, greenhouse gas emissions, and                proposed by Dominion Energy
                                                  Deadline: May 9, 2019                                cumulative impacts.                                   Transmission, Inc. (Dominion) in the
                                                  If a schedule change becomes                            The U.S. Department of                             above-referenced docket. The Project is
                                               necessary, additional notice will be                    Transportation Pipeline and Hazardous                 designed to provide 120 million cubic
                                               provided so that the relevant agencies                  Materials Administration, U.S. Coast                  feet per day of firm transportation
                                               are kept informed of the Project’s                      Guard, U.S. Department of Energy, U.S.                service from an existing point of
                                               progress.                                               Army Corps of Engineers, U.S. Fish and                interconnection located on Dominion’s


                                          VerDate Sep<11>2014   17:55 Sep 06, 2018   Jkt 244001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\07SEN1.SGM   07SEN1



Document Created: 2018-09-07 00:15:02
Document Modified: 2018-09-07 00:15:02
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 45433 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR