83_FR_45609 83 FR 45435 - Pacific Connector Gas Pipeline LP, Jordan Cove Energy Project LP; Notice of Schedule for Environmental Review Pacific Connector Pipeline Project and Jordan Cove Energy Project

83 FR 45435 - Pacific Connector Gas Pipeline LP, Jordan Cove Energy Project LP; Notice of Schedule for Environmental Review Pacific Connector Pipeline Project and Jordan Cove Energy Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 174 (September 7, 2018)

Page Range45435-45436
FR Document2018-19403

Federal Register, Volume 83 Issue 174 (Friday, September 7, 2018)
[Federal Register Volume 83, Number 174 (Friday, September 7, 2018)]
[Notices]
[Pages 45435-45436]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-19403]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP17-494-000; CP17-495-000]


Pacific Connector Gas Pipeline LP, Jordan Cove Energy Project LP; 
Notice of Schedule for Environmental Review Pacific Connector Pipeline 
Project and Jordan Cove Energy Project

    On September 21, 2017, Pacific Connector Gas Pipeline LP (Pacific 
Connector) and Jordan Cove Energy Project L.P. (Jordan Cove) filed 
applications in Docket Nos. CP17-494-000 and CP17-495-000, 
respectively. Pacific Connector is requesting a Certificate of Public 
Convenience and Necessity pursuant to Section 7(c) of the Natural Gas 
Act (NGA) to construct, operate, and maintain certain natural gas 
pipeline facilities. Jordan Cove is requesting authorization pursuant 
to Section 3(a) of the NGA to construct and operate liquefied natural 
gas (LNG) export facilities. The proposed projects are collectively 
referred to as the Jordan Cove LNG Project (Project). Jordan Cove's LNG 
facilities would be designed to liquefy about 7.8 million metric tons 
of natural gas per annum for export to markets across the Pacific Rim. 
On August 20, 2015, in Order No. 3698, the U.S. Department of Energy, 
Office of Fossil Energy, granted to Jordon Cove a long-term, multi-
contract authorization to export LNG to Free Trade Agreement nations.
    On October 5, 2017, the Federal Energy Regulatory Commission (FERC 
or Commission) issued a Notice of Applications for the Projects. Among 
other things, that notice alerted other agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on the request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's final 
Environmental Impact Statement (EIS) for the Projects. This instant 
notice identifies the FERC staff's planned schedule for completion of 
the final EIS for the Projects, which is based on an issuance of the 
draft EIS in February 2019. The forecasted schedule for both the draft 
and final EIS is based upon Jordon Cove and Pacific Connector providing 
complete and timely responses to any future data requests. In addition, 
the schedule assumes that the cooperating agencies will provide input 
on their areas of responsibility on a timely basis.

Schedule for Environmental Review

Issuance of Notice of Availability of the final EIS--August 30, 2019
90-Day Federal Authorization Decision Deadline--November 28, 2019

    If a schedule change becomes necessary for the final EIS, an 
additional notice will be provided so that the relevant agencies are 
kept informed of the Project's progress.

Project Description

    Jordan Cove proposes to construct and operate an LNG export 
terminal on the North Spit of Coos Bay in Coos County, Oregon. The 
terminal would include five liquefaction trains and associated 
equipment, two full-containment LNG storage tanks, an LNG transfer 
line, LNG ship loading facilities, a marine slip, access channel, and 
modifications to the Coos Bay Navigation Channel.
    Pacific Connector proposes to construct and operate an 
approximately 230-mile-long, 36-inch-diameter interstate natural gas 
transmission pipeline and associated aboveground

[[Page 45436]]

facilities. The pipeline would originate near Malin in Klamath County, 
Oregon, traverse Douglas and Jackson Counties, and terminate (at the 
LNG Terminal) in Coos County. The associated aboveground facilities 
would include the new Klamath Compressor Station (62,200 horsepower) 
near Malin.

Background

    On February 10, 2017, the Commission staff granted Jordan Cove and 
Pacific Connector's requests to use the FERC's Pre-filing environmental 
review process and assigned them jointly to Docket No. PF17-4-000. On 
June 9, 2017, the Commission issued a Notice of Intent to Prepare an 
Environmental Impact Statement for the Planned Jordan Cove LNG Terminal 
and Pacific Connector Pipeline Projects, Request for Comments on 
Environmental Issues, and Notice of Public Scoping Sessions (NOI).
    The NOI was issued during the pre-filing review of the Projects in 
Docket No. PF17-4-000 and was sent to federal, state, and local 
government agencies; elected officials; affected landowners; 
environmental and public interest groups; Native American tribes and 
regional organizations; commentors and other interested parties; and 
local libraries and newspapers. Major issues raised during scoping 
include purpose and need, property rights, use of eminent domain, 
reliability and safety, cumulative impacts, cultural resources, 
threatened and endangered species, water resources, vegetation, and 
alternatives.
    The U.S. Forest Service, Bureau of Land Management, Bureau of 
Reclamation, U.S. Army Corps of Engineers, U.S. Coast Guard, U.S. 
Environmental Protection Agency, U.S. Fish and Wildlife Service, 
National Marine Fisheries Service, U.S. Department of Energy, Pipeline 
and Hazardous Materials Safety Administration, and the Coquille Indian 
Tribe are cooperating agencies in the preparation of the EIS.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP17-494 and/or CP17-
495), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

    Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-19403 Filed 9-6-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                           Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices                                            45435

                                               natural gas pipeline facilities at the                    The U.S. Department of                              Section 3(a) of the NGA to construct and
                                               existing Temple Liquefied Natural Gas                   Transportation is a cooperating agencies              operate liquefied natural gas (LNG)
                                               (LNG) Peak-shaving Facility in Berks                    in the preparation of the EA.                         export facilities. The proposed projects
                                               County, Pennsylvania. The proposed                                                                            are collectively referred to as the Jordan
                                                                                                       Additional Information
                                               project is known as the Temple Truck                                                                          Cove LNG Project (Project). Jordan
                                               Rack Expansion Project (Project), and                      In order to receive notification of the            Cove’s LNG facilities would be designed
                                               would allow UGI LNG, Inc. to more                       issuance of the EA and to keep track of               to liquefy about 7.8 million metric tons
                                               reliably serve the growing demand for                   all formal issuances and submittals in                of natural gas per annum for export to
                                               truck deliveries by UGI Energy Services.                specific dockets, the Commission offers               markets across the Pacific Rim. On
                                                  On November 29, 2016, the Federal                    a free service called eSubscription. This             August 20, 2015, in Order No. 3698, the
                                               Energy Regulatory Commission                            can reduce the amount of time you                     U.S. Department of Energy, Office of
                                               (Commission or FERC) issued its Notice                  spend researching proceedings by                      Fossil Energy, granted to Jordon Cove a
                                               of Application for the Project. Among                   automatically providing you with                      long-term, multi-contract authorization
                                               other things, that notice alerted agencies              notification of these filings, document               to export LNG to Free Trade Agreement
                                               issuing federal authorizations of the                   summaries, and direct links to the                    nations.
                                               requirement to complete all necessary                   documents. Go to www.ferc.gov/docs-                      On October 5, 2017, the Federal
                                               reviews and to reach a final decision on                filing/esubscription.asp.                             Energy Regulatory Commission (FERC
                                                                                                          Additional information about the                   or Commission) issued a Notice of
                                               a request for a federal authorization
                                                                                                       Project is available from the                         Applications for the Projects. Among
                                               within 90 days of the date of issuance
                                                                                                       Commission’s Office of External Affairs               other things, that notice alerted other
                                               of the Commission staff’s Environmental
                                                                                                       at (866) 208–FERC or on the FERC                      agencies issuing federal authorizations
                                               Assessment (EA) for the Project. This
                                                                                                       website (www.ferc.gov). Using the                     of the requirement to complete all
                                               instant notice identifies the FERC staff’s
                                                                                                       eLibrary link, select General Search                  necessary reviews and to reach a final
                                               planned schedule for the completion of
                                                                                                       from the eLibrary menu, enter the                     decision on the request for a federal
                                               the EA for the Project.
                                                                                                       selected date range and Docket Number                 authorization within 90 days of the date
                                               Schedule for Environmental Review                       excluding the last three digits (i.e.,                of issuance of the Commission staff’s
                                                                                                       CP17–14), and follow the instructions.                final Environmental Impact Statement
                                               Issuance of EA—September 18, 2018
                                                                                                       For assistance with access to eLibrary,               (EIS) for the Projects. This instant notice
                                               90-Day Federal Authorization Decision                   the helpline can be reached at (866)
                                                  Deadline—December 17, 2018                                                                                 identifies the FERC staff’s planned
                                                                                                       208–3676, TTY (202) 502–8659, or at                   schedule for completion of the final EIS
                                                  If a schedule change becomes                         FERCOnlineSupport@ferc.gov. The                       for the Projects, which is based on an
                                               necessary, additional notice will be                    eLibrary link on the FERC website also                issuance of the draft EIS in February
                                               provided so that the relevant agencies                  provides access to the texts of formal                2019. The forecasted schedule for both
                                               are kept informed of the Project’s                      documents issued by the Commission,                   the draft and final EIS is based upon
                                               progress.                                               such as orders, notices, and rule                     Jordon Cove and Pacific Connector
                                               Project Description                                     makings.                                              providing complete and timely
                                                                                                         Dated: August 31, 2018.                             responses to any future data requests. In
                                                  UGI LNG, Inc. proposes to expand its                                                                       addition, the schedule assumes that the
                                                                                                       Nathaniel J. Davis, Sr.,
                                               existing Temple LNG truck loading                                                                             cooperating agencies will provide input
                                               facility by constructing two additional                 Deputy Secretary.
                                                                                                       [FR Doc. 2018–19391 Filed 9–6–18; 8:45 am]            on their areas of responsibility on a
                                               trailer loading/unloading racks. The                                                                          timely basis.
                                               new facilities would consist of two                     BILLING CODE 6717–01–P

                                               racks with scales, trailer loading skid,                                                                      Schedule for Environmental Review
                                               pump skid, transfer piping, and                                                                               Issuance of Notice of Availability of the
                                               associated equipment. The Project                       DEPARTMENT OF ENERGY
                                                                                                                                                                final EIS—August 30, 2019
                                               would also include constructing a new                   Federal Energy Regulatory                             90-Day Federal Authorization Decision
                                               driveway connecting the expansion to                    Commission                                               Deadline—November 28, 2019
                                               Willow Creek Road. The Project is                                                                                If a schedule change becomes
                                               projected to increase truck volumes                     [Docket Nos. CP17–494–000; CP17–495–
                                                                                                                                                             necessary for the final EIS, an additional
                                               from an average of one to three trucks                  000]
                                                                                                                                                             notice will be provided so that the
                                               per day to an average of three to six                                                                         relevant agencies are kept informed of
                                                                                                       Pacific Connector Gas Pipeline LP,
                                               trucks per day.                                                                                               the Project’s progress.
                                                                                                       Jordan Cove Energy Project LP; Notice
                                               Background                                              of Schedule for Environmental Review                  Project Description
                                                                                                       Pacific Connector Pipeline Project and
                                                  On January 23, 2017, the Commission                                                                           Jordan Cove proposes to construct and
                                                                                                       Jordan Cove Energy Project
                                               issued a Notice of Intent to Prepare an                                                                       operate an LNG export terminal on the
                                               Environmental Assessment for the                          On September 21, 2017, Pacific                      North Spit of Coos Bay in Coos County,
                                               Proposed Temple Truck Rack                              Connector Gas Pipeline LP (Pacific                    Oregon. The terminal would include
                                               Expansion Project and Request for                       Connector) and Jordan Cove Energy                     five liquefaction trains and associated
                                               Comments on Environmental Issues                        Project L.P. (Jordan Cove) filed                      equipment, two full-containment LNG
                                               (NOI). The NOI was sent to affected                     applications in Docket Nos. CP17–494–                 storage tanks, an LNG transfer line, LNG
                                               landowners; federal, state, and local                   000 and CP17–495–000, respectively.                   ship loading facilities, a marine slip,
daltland on DSKBBV9HB2PROD with NOTICES




                                               government agencies; elected officials;                 Pacific Connector is requesting a                     access channel, and modifications to the
                                               environmental and public interest                       Certificate of Public Convenience and                 Coos Bay Navigation Channel.
                                               groups; other interested parties; and                   Necessity pursuant to Section 7(c) of the                Pacific Connector proposes to
                                               local libraries and newspapers. In                      Natural Gas Act (NGA) to construct,                   construct and operate an approximately
                                               response to the NOI, the Commission                     operate, and maintain certain natural                 230-mile-long, 36-inch-diameter
                                               received one public comment                             gas pipeline facilities. Jordan Cove is               interstate natural gas transmission
                                               concerning increased traffic.                           requesting authorization pursuant to                  pipeline and associated aboveground


                                          VerDate Sep<11>2014   17:55 Sep 06, 2018   Jkt 244001   PO 00000   Frm 00025   Fmt 4703   Sfmt 4703   E:\FR\FM\07SEN1.SGM   07SEN1


                                               45436                       Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices

                                               facilities. The pipeline would originate                Commission’s Office of External Affairs               Issuance of Final Order—February 6,
                                               near Malin in Klamath County, Oregon,                   at (866) 208–FERC or on the FERC                         2020
                                               traverse Douglas and Jackson Counties,                  website (www.ferc.gov). Using the                        If a schedule change becomes
                                               and terminate (at the LNG Terminal) in                  eLibrary link, select General Search                  necessary for the final order, an
                                               Coos County. The associated                             from the eLibrary menu, enter the                     additional notice will be provided so
                                               aboveground facilities would include                    selected date range and Docket Number                 that interested parties and government
                                               the new Klamath Compressor Station                      excluding the last three digits (i.e.,                agencies are kept informed of the
                                               (62,200 horsepower) near Malin.                         CP17–494 and/or CP17–495), and follow                 Project’s progress.
                                               Background                                              the instructions. For assistance with                   Dated: August 31, 2018.
                                                                                                       access to eLibrary, the helpline can be
                                                  On February 10, 2017, the                                                                                  Nathaniel J. Davis, Sr.,
                                                                                                       reached at (866) 208–3676, TTY (202)
                                               Commission staff granted Jordan Cove                    502–8659, or at FERCOnlineSupport@                    Deputy Secretary.
                                               and Pacific Connector’s requests to use                 ferc.gov. The eLibrary link on the FERC               [FR Doc. 2018–19396 Filed 9–6–18; 8:45 am]
                                               the FERC’s Pre-filing environmental                     website also provides access to the texts             BILLING CODE 6717–01–P
                                               review process and assigned them                        of formal documents issued by the
                                               jointly to Docket No. PF17–4–000. On                    Commission, such as orders, notices,
                                               June 9, 2017, the Commission issued a                   and rule makings.                                     DEPARTMENT OF ENERGY
                                               Notice of Intent to Prepare an
                                               Environmental Impact Statement for the                    Dated: August 31, 2018.                             Federal Energy Regulatory
                                               Planned Jordan Cove LNG Terminal and                    Nathaniel J. Davis, Sr.,                              Commission
                                               Pacific Connector Pipeline Projects,                    Deputy Secretary.
                                                                                                                                                             [Docket Nos. CP17–66–000; CP17–67–000]
                                               Request for Comments on                                 [FR Doc. 2018–19403 Filed 9–6–18; 8:45 am]
                                               Environmental Issues, and Notice of                     BILLING CODE 6717–01–P                                Notice of Schedule for Environmental
                                               Public Scoping Sessions (NOI).                                                                                Review of the Venture Global
                                                  The NOI was issued during the pre-                                                                         Plaquemines LNG, LLC and Venture
                                               filing review of the Projects in Docket                 DEPARTMENT OF ENERGY                                  Global Gator Express, LLC
                                               No. PF17–4–000 and was sent to federal,                                                                       Plaquemines LNG and Gator Express
                                               state, and local government agencies;                   Federal Energy Regulatory                             Pipeline Project
                                               elected officials; affected landowners;                 Commission
                                               environmental and public interest                                                                                On February 28, 2017, Venture Global
                                                                                                       [Docket Nos. CP17–178–000]
                                               groups; Native American tribes and                                                                            Plaquemines LNG, LLC (Plaquemines
                                               regional organizations; commentors and                  Notice of Anticipated Schedule of Final               LNG) filed an application in Docket No.
                                               other interested parties; and local                     Order for the Alaska Gasline                          CP17–66–000 requesting authorization
                                               libraries and newspapers. Major issues                  Development Corporation Alaska LNG                    pursuant to Section 3(a) of the Natural
                                               raised during scoping include purpose                   Project                                               Gas Act (NGA) to construct and operate
                                               and need, property rights, use of                                                                             liquefied natural gas (LNG) export
                                               eminent domain, reliability and safety,                    On April 17, 2017, Alaska Gasline                  facilities. On the same day, Venture
                                               cumulative impacts, cultural resources,                 Development Corporation filed an                      Global Gator Express, LLC (Gator
                                               threatened and endangered species,                      application in Docket No. CP17–178–                   Express Pipeline) filed an application in
                                               water resources, vegetation, and                        000, pursuant to section 3 of the Natural             Docket No. CP17–67–000, requesting a
                                               alternatives.                                           Gas Act and Part 153 of the                           Certificate of Public Convenience and
                                                  The U.S. Forest Service, Bureau of                   Commission’s regulations, for                         Necessity pursuant to Section 7(c) of the
                                               Land Management, Bureau of                              authorization to site, construct, and                 NGA to construct, operate, and maintain
                                               Reclamation, U.S. Army Corps of                         operate a new liquefied natural gas                   certain natural gas pipeline facilities.
                                               Engineers, U.S. Coast Guard, U.S.                       (LNG) export terminal and associated                  Combined, the proposed project is
                                               Environmental Protection Agency, U.S.                   facilities on the eastern shore of Cook               known as the Plaquemines LNG and
                                               Fish and Wildlife Service, National                     Inlet in the Nikiski area of the Kenai                Gator Express Pipeline Project (Project)
                                               Marine Fisheries Service, U.S.                          Peninsula in Alaska, and to construct                 and would provide gas and processing
                                               Department of Energy, Pipeline and                      approximately 871 miles of natural gas                to produce up to 20.0 million tonnes per
                                               Hazardous Materials Safety                              pipeline and associated facilities, all               annum of LNG for export. On July 21,
                                               Administration, and the Coquille Indian                 within the State of Alaska. The                       2016, in Order No. 3866, the U.S.
                                               Tribe are cooperating agencies in the                   proposed project, known as the Alaska                 Department of Energy, Office of Fossil
                                               preparation of the EIS.                                 LNG (Project), would liquefy and export               Energy, granted to Plaquemines LNG
                                                                                                       up to 20.0 million metric tons per                    authorization to export LNG to Free
                                               Additional Information                                  annum of LNG.                                         Trade Agreement nations.
                                                  In order to receive notification of the                 In accordance with Title 41 of the                    On March 13, 2017, the Federal
                                               issuance of the EIS and to keep track of                Fixing America’s Surface Transportation               Energy Regulatory Commission (FERC
                                               all formal issuances and submittals in                  Act, enacted on December 4, 2015,                     or Commission) issued its Notice of
                                               specific dockets, the Commission offers                 agencies are to publish completion dates              Application for the Project. Among
                                               a free service called eSubscription. This               for all federal environmental reviews                 other things, that notice alerted other
                                               can reduce the amount of time you                       and authorizations. This notice                       agencies issuing federal authorizations
                                               spend researching proceedings by                        identifies the Commission’s anticipated               of the requirement to complete all
daltland on DSKBBV9HB2PROD with NOTICES




                                               automatically providing you with                        schedule for issuance of the final order              necessary reviews and to reach a final
                                               notification of these filings, document                 for the Project, which is based on the                decision on the request for a federal
                                               summaries, and direct links to the                      anticipated date of issuance of the final             authorization within 90 days of the date
                                               documents. Go to www.ferc.gov/docs-                     Environmental Impact Statement.                       of issuance of the Commission staff’s
                                               filing/esubscription.asp.                               Accordingly, we currently anticipate                  final Environmental Impact Statement
                                                  Additional information about the                     issuing a final order in the Project no               (EIS) for the Plaquemines LNG and
                                               Project is available from the                           later than:                                           Gator Express Pipeline Project. This


                                          VerDate Sep<11>2014   17:55 Sep 06, 2018   Jkt 244001   PO 00000   Frm 00026   Fmt 4703   Sfmt 4703   E:\FR\FM\07SEN1.SGM   07SEN1



Document Created: 2018-09-07 00:15:30
Document Modified: 2018-09-07 00:15:30
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 45435 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR