The Deputy Secretary of Energy extends, on an interim basis, the existing Pacific Northwest-Pacific Southwest Intertie Project (Intertie) transmission service rates through September 30, 2020. Existing Rate Schedules INT-FT5 and INT-NFT4 expired on April 30, 2018. The Administrator of the Western Area Power Administration (WAPA) approved rates for short-term sales of firm and non-firm transmission service on April 26, 2018, to cover the period between May 1, 2018, and the date this rate extension goes into effect or October 31, 2018, whichever occurs first. The extended transmission service rates will be in effect on an interim basis until the Federal Energy Regulatory Commission (FERC) confirms, approves, and places them into effect on a final basis, or until they are replaced by other rates.

Federal Register, Volume 83 Issue 184 (Friday, September 21, 2018)
[Federal Register Volume 83, Number 184 (Friday, September 21, 2018)]
[Notices]
[Pages 47921-47922]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-20597]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Western Area Power Administration


Pacific Northwest-Pacific Southwest Intertie Project--Rate Order 
No. WAPA-181

AGENCY: Western Area Power Administration, DOE.

ACTION: Notice of rate order extending transmission service rates.

-----------------------------------------------------------------------

SUMMARY: The Deputy Secretary of Energy extends, on an interim basis, 
the existing Pacific Northwest-Pacific Southwest Intertie Project 
(Intertie) transmission service rates through September 30, 2020. 
Existing Rate Schedules INT-FT5 and INT-NFT4 expired on April 30, 2018. 
The Administrator of the Western Area Power Administration (WAPA) 
approved rates for short-term sales of firm and non-firm transmission 
service on April 26, 2018, to cover the period between May 1, 2018, and 
the date this rate extension goes into effect or October 31, 2018, 
whichever occurs first. The extended transmission service rates will be 
in effect on an interim basis until the Federal Energy Regulatory 
Commission (FERC) confirms, approves, and places them into effect on a 
final basis, or until they are replaced by other rates.

DATES: Transmission Service Rate Schedules INT-FT5 and INT-NFT4 will 
become effective October 22, 2018, and will remain in effect through 
September 30, 2020.

FOR FURTHER INFORMATION CONTACT: Mr. Ronald E. Moulton, Regional 
Manager, Desert Southwest Customer Service Region, Western Area Power 
Administration, P.O. Box 6457, Phoenix, AZ 85005-6457, or Ms. Tina 
Ramsey, Rates Manager, Desert Southwest Customer Service Region, 
Western Area Power Administration, P.O. Box 6457, Phoenix, AZ 85005-
6457, (602) 605-2565, or e-mail dswpwrmrk@wapa.gov.

SUPPLEMENTARY INFORMATION: By Delegation Order No. 00-037.00B, 
effective November 19, 2016, the Secretary of Energy delegated: (1) The 
authority to develop power and transmission rates to WAPA's 
Administrator; (2) the authority to confirm, approve, and place such 
rates into effect on an interim basis to the Deputy Secretary of 
Energy; and (3) the authority to confirm, approve, and place into 
effect on a final basis, to remand, or to disapprove such rates to 
FERC.
    Rate Schedules INT-FT5 and INT-NFT4 under Rate Order No. WAPA-157 
\1\ were approved by FERC for a 5-year period through April 30, 2018. 
WAPA's Administrator approved the use of existing Intertie rates under 
his authority to set rates for short-term sales to cover the period 
between May 1, 2018, and the date this rate extension goes into effect 
or October 31, 2018, whichever occurs first.
---------------------------------------------------------------------------

    \1\ FERC confirmed and approved Rate Order No. WAPA-157 on 
August 22, 2013, in Docket No. EF13-4-000. See Order Confirming and 
Approving Rate Schedules on a Final Basis, 144 FERC ] 61,143.
---------------------------------------------------------------------------

    In accordance with 10 CFR 903.23(a), WAPA is extending the Intertie 
transmission service rates under Rates Schedules INT-FT5 and INT-NFT4. 
Extending these rate schedules through September 30, 2020, will provide 
WAPA and its customers time to evaluate the potential benefits of 
combining transmission rates on Federal projects located within WAPA's 
Desert Southwest Region. Combining rates may lead to more efficient use 
of the Federal transmission systems, diversify the customers who use 
those systems, and be financially advantageous. If, after a thorough 
evaluation, WAPA determines that combining transmission rates will 
produce material benefits, it would initiate a rate adjustment to 
combine the rates.
    The notice of proposed rate extension was published in the Federal 
Register on March 9, 2018 (83 FR 10475). In accordance with 10 CFR 
903.23(a), WAPA determined it was not necessary to hold a public 
information or public comment forum but provided a 30-day consultation 
and comment period on the proposed rate extension. The consultation and 
comment period ended on April 9, 2018.
    Following DOE's review of WAPA's proposal, I hereby approve Rate 
Order No. WAPA-181, which extends existing Transmission Service Rate 
Schedules INT-FT5 and INT-NFT4 through September 30, 2020. Rate Order 
No. WAPA-181 will be submitted to FERC for confirmation and approval on 
a final basis.

    Dated: September 11, 2018.
Dan Brouillette,
Deputy Secretary of Energy.

DEPARTMENT OF ENERGY

DEPUTY SECRETARY

    In the Matter of: Western Area Power Administration Rate 
Extension of Pacific Northwest-Pacific Southwest Intertie Project 
Transmission Service Rate Schedules

Rate Order No. WAPA-181

ORDER CONFIRMING AND APPROVING AN EXTENSION OF PACIFIC NORTHWEST-
PACIFIC SOUTHWEST INTERTIE PROJECT TRANSMISSION SERVICE RATE SCHEDULES

    Section 302 of the Department of Energy (DOE) Organization Act (42 
U.S.C. 7152) transferred to and vested in the Secretary of Energy the 
power marketing functions of the Secretary of the Department of the 
Interior and the Bureau of Reclamation under the Reclamation Act of 
1902 (ch. 1093, 32 Stat. 388), as amended and supplemented by 
subsequent laws, particularly section 9(c) of the Reclamation Project 
Act of 1939 (43 U.S.C. 485h(c)), and other acts that specifically apply 
to the project involved.
    By Delegation Order No. 00-037.00B, effective November 19, 2016, 
the Secretary of Energy delegated (1) the authority to develop power 
and transmission rates to the Administrator of the Western Area Power 
Administration (WAPA); (2) the

[[Page 47922]]

authority to confirm, approve, and place such rates into effect on an 
interim basis to the Deputy Secretary of Energy; and (3) the authority 
to confirm, approve, and place into effect on a final basis, to remand, 
or to disapprove such rates to the Federal Energy Regulatory Commission 
(FERC). This extension is issued pursuant to the Delegation Order and 
DOE rate extension procedures documented at 10 CFR 903.23(a).

BACKGROUND

    On August 22, 2013, FERC confirmed, approved, and placed into 
effect on a final basis Intertie Transmission Service Rate Schedules 
INT-FT5 and INT-NFT4 under Rate Order No. WAPA-157.\1\ These 
transmission service rate schedules were approved for 5-year period 
beginning May 1, 2013, and ending April 30, 2018.
---------------------------------------------------------------------------

    \1\ FERC confirmed and approved Rate Order No. WAPA-157 on 
August 22, 2013, in Docket No. EF13-4-000. See Order Confirming and 
Approving Rate Schedules on a Final Basis, 144 FERC ] 61,143.
---------------------------------------------------------------------------

    Pursuant to 10 CFR 903.23(a), WAPA filed a notice in the Federal 
Register on March 9, 2018, proposing to extend Rate Schedules INT-FT5 
and INT-NFT4 under Rate Order No. WAPA-181 (83 FR 10475). WAPA held a 
consultation and comment period on the proposed rate extension but did 
not conduct a public information forum or public comment forum. WAPA 
received no comments during the consultation and comment period, which 
ended on April 9, 2018.

DISCUSSION

    On April 30, 2018, existing Rate Schedules INT-FT5 and INT-NFT4 
expired. Pursuant to Delegation Order No. 00-037.00B, Section 1.5, 
rates for short-term sales were approved by WAPA's Administrator to 
cover the period between May 1, 2018, and the date the rate extension 
goes into effect or October 31, 2018, whichever occurs first. The 
existing transmission service rates provide adequate revenue to pay all 
annual costs, including interest expense, and to repay required 
investment according to the cost recovery criteria set forth in DOE 
Order RA 6120.2. Rate Order No. WAPA-181, which extends the existing 
rate schedules through September 30, 2020, ensures adequate revenue to 
pay all annual costs for the allowable period.

[FR Doc. 2018-20597 Filed 9-20-18; 8:45 am]
 BILLING CODE 6450-01-P



                                                                           Federal Register / Vol. 83, No. 184 / Friday, September 21, 2018 / Notices                                             47921

                                                  Accession Number: 20180914–5160.                     between May 1, 2018, and the date this                transmission systems, diversify the
                                                  Comments Due: 5 p.m. ET 10/5/18.                     rate extension goes into effect or                    customers who use those systems, and
                                                  Take notice that the Commission                      October 31, 2018, whichever occurs                    be financially advantageous. If, after a
                                               received the following public utility                   first. The extended transmission service              thorough evaluation, WAPA determines
                                               holding company filings:                                rates will be in effect on an interim basis           that combining transmission rates will
                                                  Docket Numbers: PH18–14–000.                         until the Federal Energy Regulatory                   produce material benefits, it would
                                                  Applicants: CMS Energy Corporation.                  Commission (FERC) confirms, approves,                 initiate a rate adjustment to combine the
                                                  Description: CMS Energy Corporation                  and places them into effect on a final                rates.
                                               submits FERC 65–B Notice of Material                    basis, or until they are replaced by other               The notice of proposed rate extension
                                               Change.                                                 rates.                                                was published in the Federal Register
                                                  Filed Date: 9/14/18.                                 DATES: Transmission Service Rate                      on March 9, 2018 (83 FR 10475). In
                                                  Accession Number: 20180914–5076.                     Schedules INT–FT5 and INT–NFT4 will                   accordance with 10 CFR 903.23(a),
                                                  Comments Due: 5 p.m. ET 10/5/18.                     become effective October 22, 2018, and                WAPA determined it was not necessary
                                                                                                       will remain in effect through September               to hold a public information or public
                                                  The filings are accessible in the                                                                          comment forum but provided a 30-day
                                                                                                       30, 2020.
                                               Commission’s eLibrary system by                                                                               consultation and comment period on
                                                                                                       FOR FURTHER INFORMATION CONTACT: Mr.
                                               clicking on the links or querying the                                                                         the proposed rate extension. The
                                               docket number.                                          Ronald E. Moulton, Regional Manager,
                                                                                                       Desert Southwest Customer Service                     consultation and comment period ended
                                                  Any person desiring to intervene or                                                                        on April 9, 2018.
                                               protest in any of the above proceedings                 Region, Western Area Power
                                                                                                       Administration, P.O. Box 6457,                           Following DOE’s review of WAPA’s
                                               must file in accordance with Rules 211                                                                        proposal, I hereby approve Rate Order
                                               and 214 of the Commission’s                             Phoenix, AZ 85005–6457, or Ms. Tina
                                                                                                       Ramsey, Rates Manager, Desert                         No. WAPA–181, which extends existing
                                               Regulations (18 CFR 385.211 and                                                                               Transmission Service Rate Schedules
                                               385.214) on or before 5:00 p.m. Eastern                 Southwest Customer Service Region,
                                                                                                       Western Area Power Administration,                    INT–FT5 and INT–NFT4 through
                                               time on the specified comment date.                                                                           September 30, 2020. Rate Order No.
                                               Protests may be considered, but                         P.O. Box 6457, Phoenix, AZ 85005–
                                                                                                       6457, (602) 605–2565, or e-mail                       WAPA–181 will be submitted to FERC
                                               intervention is necessary to become a                                                                         for confirmation and approval on a final
                                               party to the proceeding.                                dswpwrmrk@wapa.gov.
                                                                                                       SUPPLEMENTARY INFORMATION: By
                                                                                                                                                             basis.
                                                  eFiling is encouraged. More detailed
                                                                                                       Delegation Order No. 00–037.00B,                        Dated: September 11, 2018.
                                               information relating to filing
                                               requirements, interventions, protests,                  effective November 19, 2016, the                      Dan Brouillette,
                                               service, and qualifying facilities filings              Secretary of Energy delegated: (1) The                Deputy Secretary of Energy.
                                               can be found at: http://www.ferc.gov/                   authority to develop power and
                                                                                                       transmission rates to WAPA’s                          DEPARTMENT OF ENERGY
                                               docs-filing/efiling/filing-req.pdf. For
                                               other information, call (866) 208–3676                  Administrator; (2) the authority to                   DEPUTY SECRETARY
                                               (toll free). For TTY, call (202) 502–8659.              confirm, approve, and place such rates                  In the Matter of: Western Area Power
                                                                                                       into effect on an interim basis to the                Administration Rate Extension of Pacific
                                                 Dated: September 14, 2018.                            Deputy Secretary of Energy; and (3) the               Northwest-Pacific Southwest Intertie Project
                                               Nathaniel J. Davis, Sr.,                                authority to confirm, approve, and place              Transmission Service Rate Schedules
                                               Deputy Secretary.                                       into effect on a final basis, to remand,              Rate Order No. WAPA–181
                                               [FR Doc. 2018–20555 Filed 9–20–18; 8:45 am]             or to disapprove such rates to FERC.
                                               BILLING CODE 6717–01–P                                     Rate Schedules INT–FT5 and INT–                    ORDER CONFIRMING AND
                                                                                                       NFT4 under Rate Order No. WAPA–                       APPROVING AN EXTENSION OF
                                                                                                       157 1 were approved by FERC for a 5-                  PACIFIC NORTHWEST-PACIFIC
                                               DEPARTMENT OF ENERGY                                    year period through April 30, 2018.                   SOUTHWEST INTERTIE PROJECT
                                                                                                       WAPA’s Administrator approved the                     TRANSMISSION SERVICE RATE
                                               Western Area Power Administration                       use of existing Intertie rates under his              SCHEDULES
                                                                                                       authority to set rates for short-term sales              Section 302 of the Department of
                                               Pacific Northwest-Pacific Southwest
                                                                                                       to cover the period between May 1,                    Energy (DOE) Organization Act (42
                                               Intertie Project—Rate Order No.
                                                                                                       2018, and the date this rate extension                U.S.C. 7152) transferred to and vested in
                                               WAPA–181
                                                                                                       goes into effect or October 31, 2018,                 the Secretary of Energy the power
                                               AGENCY: Western Area Power                              whichever occurs first.                               marketing functions of the Secretary of
                                               Administration, DOE.                                       In accordance with 10 CFR 903.23(a),               the Department of the Interior and the
                                               ACTION: Notice of rate order extending
                                                                                                       WAPA is extending the Intertie                        Bureau of Reclamation under the
                                               transmission service rates.                             transmission service rates under Rates                Reclamation Act of 1902 (ch. 1093, 32
                                                                                                       Schedules INT–FT5 and INT–NFT4.                       Stat. 388), as amended and
                                               SUMMARY:  The Deputy Secretary of                       Extending these rate schedules through                supplemented by subsequent laws,
                                               Energy extends, on an interim basis, the                September 30, 2020, will provide                      particularly section 9(c) of the
                                               existing Pacific Northwest-Pacific                      WAPA and its customers time to                        Reclamation Project Act of 1939 (43
                                               Southwest Intertie Project (Intertie)                   evaluate the potential benefits of                    U.S.C. 485h(c)), and other acts that
                                               transmission service rates through                      combining transmission rates on Federal               specifically apply to the project
                                               September 30, 2020. Existing Rate                       projects located within WAPA’s Desert                 involved.
daltland on DSKBBV9HB2PROD with NOTICES




                                               Schedules INT–FT5 and INT–NFT4                          Southwest Region. Combining rates may                    By Delegation Order No. 00-037.00B,
                                               expired on April 30, 2018. The                          lead to more efficient use of the Federal             effective November 19, 2016, the
                                               Administrator of the Western Area                                                                             Secretary of Energy delegated (1) the
                                                                                                         1 FERC confirmed and approved Rate Order No.
                                               Power Administration (WAPA)                                                                                   authority to develop power and
                                                                                                       WAPA–157 on August 22, 2013, in Docket No.
                                               approved rates for short-term sales of                  EF13–4–000. See Order Confirming and Approving
                                                                                                                                                             transmission rates to the Administrator
                                               firm and non-firm transmission service                  Rate Schedules on a Final Basis, 144 FERC ¶           of the Western Area Power
                                               on April 26, 2018, to cover the period                  61,143.                                               Administration (WAPA); (2) the


                                          VerDate Sep<11>2014   17:30 Sep 20, 2018   Jkt 244001   PO 00000   Frm 00048   Fmt 4703   Sfmt 4703   E:\FR\FM\21SEN1.SGM   21SEN1


                                               47922                       Federal Register / Vol. 83, No. 184 / Friday, September 21, 2018 / Notices

                                               authority to confirm, approve, and place                ENVIRONMENTAL PROTECTION                              Amended Notices
                                               such rates into effect on an interim basis              AGENCY                                                EIS No. 20180211, Final, NIGC, CA,
                                               to the Deputy Secretary of Energy; and                                                                          ADOPTION—Wilton Rancheria,
                                                                                                       [ER–FRL–9041–4]
                                               (3) the authority to confirm, approve,                                                                          Review Period Ends: 10/15/2018,
                                               and place into effect on a final basis, to              Environmental Impact Statements;                        Contact: Austin Badger 202–632–
                                               remand, or to disapprove such rates to                  Notice of Availability                                  7003. Revision to the FR Notice
                                               the Federal Energy Regulatory                                                                                   Published 9/14/2018: The National
                                               Commission (FERC). This extension is                      Responsible Agency: Office of Federal
                                                                                                                                                               Indian Gaming Commission (NIGC)
                                                                                                       Activities, General Information (202)
                                               issued pursuant to the Delegation Order                                                                         has adopted the U.S. Bureau of Indian
                                                                                                       564–5632 or https://www.epa.gov/
                                               and DOE rate extension procedures                                                                               Affairs Final EIS No. 20160300, filed
                                                                                                       nepa/.
                                               documented at 10 CFR 903.23(a).                                                                                 12/08/2016 with the EPA. NIGC was
                                                                                                       Weekly receipt of Environmental Impact                  not a cooperating agency on this
                                               BACKGROUND                                                Statements                                            project. Therefore, recirculation of the
                                                                                                       Filed 09/10/2018 Through 09/14/2018                     document is necessary under Section
                                                  On August 22, 2013, FERC confirmed,                  Pursuant to 40 CFR 1506.9.
                                               approved, and placed into effect on a                                                                           1506.3(b) of the CEQ Regulations.
                                                                                                       Notice                                                  Dated: September 17, 2018.
                                               final basis Intertie Transmission Service
                                               Rate Schedules INT-FT5 and INT-NFT4                       Section 309(a) of the Clean Air Act                 Robert Tomiak,
                                               under Rate Order No. WAPA-157.1                         requires that EPA make public its                     Director, Office of Federal Activities.
                                               These transmission service rate                         comments on EISs issued by other                      [FR Doc. 2018–20531 Filed 9–20–18; 8:45 am]
                                               schedules were approved for 5-year                      Federal agencies. EPA’s comment letters               BILLING CODE 6560–50–P
                                               period beginning May 1, 2013, and                       on EISs are available at: https://
                                               ending April 30, 2018.                                  cdxnodengn.epa.gov/cdx-enepa-public/
                                                                                                       action/eis/search.
                                                  Pursuant to 10 CFR 903.23(a), WAPA                                                                         DEPARTMENT OF HEALTH AND
                                                                                                       EIS No. 20180212, Final, USFS, IL,                    HUMAN SERVICES
                                               filed a notice in the Federal Register on                 Cretaceous Hills Ecological
                                               March 9, 2018, proposing to extend Rate                   Restoration Project, Review Period                  Administration for Children and
                                               Schedules INT-FT5 and INT-NFT4                            Ends: 10/22/2018, Contact: Leonard                  Families
                                               under Rate Order No. WAPA-181 (83 FR                      Pitcher 618–833–8576
                                               10475). WAPA held a consultation and                    EIS No. 20180213, Draft, BLM, NV,                     Proposed Information Collection
                                               comment period on the proposed rate                       Rossi Mine Expansion Project,                       Activity; Comment Request
                                               extension but did not conduct a public                    Comment Period Ends: 11/05/2018,
                                               information forum or public comment                       Contact: Janice Stadelman 775–753–                     Title: Phase II Evaluation Activities
                                               forum. WAPA received no comments                          0346                                                for Implementing a Next Generation
                                                                                                       EIS No. 20180214, Draft, FRA, MS, Port                Evaluation Agenda for the Chafee Foster
                                               during the consultation and comment
                                                                                                         Bienville Railroad Draft                            Care Independence Program—
                                               period, which ended on April 9, 2018.
                                                                                                         Environmental Impact Statement,                     Extension.
                                               DISCUSSION                                                Comment Period Ends: 11/05/2018,                       OMB No.: 0970–0489.
                                                                                                         Contact: Kevin Wright 202–493–0845                     Description: The Administration for
                                                  On April 30, 2018, existing Rate                     EIS No. 20180215, Draft, FERC, LA,                    Children and Families (ACF), Office of
                                               Schedules INT-FT5 and INT-NFT4                            Driftwood LNG Project Draft                         Planning Research and Evaluation
                                               expired. Pursuant to Delegation Order                     Environmental Impact Statement,                     (OPRE) is proposing an extension to a
                                               No. 00-037.00B, Section 1.5, rates for                    Comment Period Ends: 11/05/2018,                    currently approved information
                                               short-term sales were approved by                         Contact: Kelley Munoz 202–502–6739                  collection (OMB no. 0970–0489). The
                                               WAPA’s Administrator to cover the                       EIS No. 20180216, Draft Supplement,                   information collection activities are part
                                               period between May 1, 2018, and the                       DOS, NE, Draft Supplemental                         of the Phase II Evaluation Activities for
                                               date the rate extension goes into effect                  Environmental Impact Statement                      Implementing a Next Generation
                                               or October 31, 2018, whichever occurs                     Keystone XL Mainline Alternative                    Evaluation Agenda for the Chafee Foster
                                               first. The existing transmission service                  Route, Comment Period Ends:                         Care Independence Program (now
                                               rates provide adequate revenue to pay                     11/05/2018, Contact: Marko Velikonja                known as the Chafee Foster Care
                                               all annual costs, including interest                      202–647–4828                                        Program for Successful Transition to
                                               expense, and to repay required                          EIS No. 20180217, Draft, BIA, CA, Draft               Adulthood). The purpose of the
                                               investment according to the cost                          Environmental Impact Statement,                     extension is to continue the ongoing
                                                                                                         Tule River Indian Tribe—Fee-to-Trust                information collection, which consists
                                               recovery criteria set forth in DOE Order
                                                                                                         and Eagle Mountain Casino                           of site visits by staff from the Urban
                                               RA 6120.2. Rate Order No. WAPA-181,
                                                                                                         Relocation Project, Comment Period                  Institute and Chapin Hall at the
                                               which extends the existing rate
                                                                                                         Ends: 11/05/2018, Contact: Chad                     University of Chicago to conduct
                                               schedules through September 30, 2020,                                                                         formative evaluations of programs
                                                                                                         Broussard 916–978–6165
                                               ensures adequate revenue to pay all                                                                           serving transition-age foster youth. The
                                                                                                       EIS No. 20180218, Draft Supplement,
                                               annual costs for the allowable period.                    BR, CA, California WaterFix EIS EIR,                evaluations include preliminary visits to
                                               [FR Doc. 2018–20597 Filed 9–20–18; 8:45 am]               Comment Period Ends:                                discuss the evaluation process with
                                               BILLING CODE 6450–01–P                                    11/05/2018, Contact: Brooke White                   program administrators and site visits to
daltland on DSKBBV9HB2PROD with NOTICES




                                                                                                         916–414–2402                                        each program to speak with program
                                                                                                       EIS No. 20180219, Final, USACE, CA,                   leaders, partners and key stakeholders,
                                                 1 FERC confirmed and approved Rate Order No.
                                                                                                         Delta Islands and Levees Integrated                 front-line staff, and participants. These
                                               WAPA-157 on August 22, 2013, in Docket No.
                                                                                                         Feasibility Study and Environmental                 formative evaluations will determine
                                               EF13–4–000. See Order Confirming and Approving            Impact Study, Review Period Ends:                   programs’ readiness for more rigorous
                                               Rate Schedules on a Final Basis, 144 FERC ¶               10/22/2018, Contact: Anne Baker                     evaluation in the future. The activities
                                               61,143.                                                   916–557–7277                                        and products from this project will help


                                          VerDate Sep<11>2014   17:30 Sep 20, 2018   Jkt 244001   PO 00000   Frm 00049   Fmt 4703   Sfmt 4703   E:\FR\FM\21SEN1.SGM   21SEN1



Document Created: 2018-09-21 00:23:37
Document Modified: 2018-09-21 00:23:37
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of rate order extending transmission service rates.
DatesTransmission Service Rate Schedules INT-FT5 and INT-NFT4 will become effective October 22, 2018, and will remain in effect through September 30, 2020.
ContactMr. Ronald E. Moulton, Regional Manager, Desert Southwest Customer Service Region, Western Area Power Administration, P.O. Box 6457, Phoenix, AZ 85005-6457, or Ms. Tina Ramsey, Rates Manager, Desert Southwest Customer Service Region, Western Area Power Administration, P.O. Box 6457, Phoenix, AZ 85005- 6457, (602) 605-2565, or e-mail [email protected]
FR Citation83 FR 47921 