83_FR_54311 83 FR 54103 - Tenn-Tom Hydro, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

83 FR 54103 - Tenn-Tom Hydro, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 208 (October 26, 2018)

Page Range54103-54103
FR Document2018-23442

Federal Register, Volume 83 Issue 208 (Friday, October 26, 2018)
[Federal Register Volume 83, Number 208 (Friday, October 26, 2018)]
[Notices]
[Page 54103]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-23442]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14883-000]


Tenn-Tom Hydro, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

    On July 5, 2018, Tenn-Tom Hydro, LLC, filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act 
(FPA), proposing to study the feasibility of the Aberdeen Hydropower 
Project (Aberdeen Project or project) to be located at the U.S. Army 
Corps of Engineers' (Corps) Aberdeen Lock and Dam on the Tennessee-
Tombigbee Waterway, in Monroe County, Mississippi. The sole purpose of 
a preliminary permit, if issued, is to grant the permit holder priority 
to file a license application during the permit term. A preliminary 
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by 
others without the owners' express permission.
    The proposed project would consist of the following: (1) A 
cylindrical intake structure in each of the three existing gated 
spillways sections, on the eastern end of the dam; (2) four proprietary 
shaped penstocks with run underneath each of the existing three Corps' 
spillway gates; (3) four submerged generating units, below each 
spillway section for a total of twelve units, with a total combined 
capacity of 4.8 megawatts; (4) a 50-foot-long, 50-foot-wide control 
building with switchyard on the dam's east abutment; (5) a 0.8 mile-
long transmission line. The proposed project would have an estimated 
average annual generation of 32,000 megawatt-hours, and operate run-of-
river utilizing surplus water from the Aberdeen Lock & Dam, as directed 
by the Corps.
    Applicant Contact: Mr. Jeremy Wells, Wells Engineering, LLC, 101 
Yearwood Drive, Macon, Georgia 31206; phone: (478) 238-3054.
    FERC Contact: Michael Spencer, (202) 502-6093, 
[email protected]
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-14883-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's website at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14883) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: October 19, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-23442 Filed 10-25-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                             Federal Register / Vol. 83, No. 208 / Friday, October 26, 2018 / Notices                                               54103

                                               to this project. The Commission will                    DEPARTMENT OF ENERGY                                     The Commission strongly encourages
                                               consider these comments in                                                                                    electronic filing. Please file comments,
                                               determining the appropriate action to be                Federal Energy Regulatory                             motions to intervene, notices of intent,
                                               taken, but the filing of a comment alone                Commission                                            and competing applications using the
                                               will not serve to make the filer a party                                                                      Commission’s eFiling system at http://
                                               to the proceeding. The Commission’s                     [Project No. 14883–000]                               www.ferc.gov/docs-filing/efiling.asp.
                                               rules require that persons filing                       Tenn-Tom Hydro, LLC; Notice of                        Commenters can submit brief comments
                                               comments in opposition to the project                   Preliminary Permit Application                        up to 6,000 characters, without prior
                                               provide copies of their protests only to                Accepted for Filing and Soliciting                    registration, using the eComment system
                                               the party or parties directly involved in               Comments, Motions To Intervene, and                   at http://www.ferc.gov/docs-filing/
                                               the protest.                                            Competing Applications                                ecomment.asp. You must include your
                                                  Persons who wish to comment only                                                                           name and contact information at the end
                                               on the environmental review of this                        On July 5, 2018, Tenn-Tom Hydro,                   of your comments. For assistance,
                                               project should submit an original and                   LLC, filed an application for a                       please contact FERC Online Support at
                                               two copies of their comments to the                     preliminary permit, pursuant to section               FERCOnlineSupport@ferc.gov, (866)
                                               Secretary of the Commission.                            4(f) of the Federal Power Act (FPA),                  208–3676 (toll free), or (202) 502–8659
                                               Environmental commentors will be                        proposing to study the feasibility of the             (TTY). In lieu of electronic filing, please
                                               placed on the Commission’s                              Aberdeen Hydropower Project                           send a paper copy to: Secretary, Federal
                                               environmental mailing list, and will be                 (Aberdeen Project or project) to be                   Energy Regulatory Commission, 888
                                               notified of any meetings associated with                located at the U.S. Army Corps of                     First Street NE, Washington, DC 20426.
                                               the Commission’s environmental review                   Engineers’ (Corps) Aberdeen Lock and                  The first page of any filing should
                                               process. Environmental commentors                       Dam on the Tennessee-Tombigbee                        include docket number P–14883–000.
                                               will not be required to serve copies of                 Waterway, in Monroe County,                              More information about this project,
                                               filed documents on all other parties.                   Mississippi. The sole purpose of a                    including a copy of the application, can
                                               However, the non-party commentors                       preliminary permit, if issued, is to grant            be viewed or printed on the ‘‘eLibrary’’
                                               will not receive copies of all documents                the permit holder priority to file a                  link of Commission’s website at http://
                                               filed by other parties or issued by the                 license application during the permit                 www.ferc.gov/docs-filing/elibrary.asp.
                                               Commission and will not have the right                  term. A preliminary permit does not                   Enter the docket number (P–14883) in
                                               to seek court review of the                             authorize the permit holder to perform                the docket number field to access the
                                               Commission’s final order.                               any land-disturbing activities or                     document. For assistance, contact FERC
                                                  As of the February 27, 2018 date of                  otherwise enter upon lands or waters                  Online Support.
                                               the Commission’s order in Docket No.                    owned by others without the owners’                     Dated: October 19, 2018.
                                               CP16–4–001, the Commission will                         express permission.                                   Nathaniel J. Davis, Sr.,
                                               apply its revised practice concerning                      The proposed project would consist of              Deputy Secretary.
                                               out-of-time motions to intervene in any                 the following: (1) A cylindrical intake               [FR Doc. 2018–23442 Filed 10–25–18; 8:45 am]
                                               new Natural Gas Act section 3 or section                structure in each of the three existing
                                                                                                                                                             BILLING CODE 6717–01–P
                                               7 proceeding.1 Persons desiring to                      gated spillways sections, on the eastern
                                               become a party to a certificate                         end of the dam; (2) four proprietary
                                               proceeding are to intervene in a timely                 shaped penstocks with run underneath                  DEPARTMENT OF ENERGY
                                               manner. If seeking to intervene out-of-                 each of the existing three Corps’
                                               time, the movant is required to ‘‘show                  spillway gates; (3) four submerged                    Federal Energy Regulatory
                                               good cause why the time limitation                      generating units, below each spillway                 Commission
                                               should be waived,’’ and should provide                  section for a total of twelve units, with
                                               justification by reference to factors set               a total combined capacity of 4.8                      Combined Notice of Filings #1
                                               forth in Rule 214(d)(1) of the                          megawatts; (4) a 50-foot-long, 50-foot-
                                                                                                       wide control building with switchyard                    Take notice that the Commission
                                               Commission’s Rules and Regulations.2                                                                          received the following electric corporate
                                                  The Commission strongly encourages                   on the dam’s east abutment; (5) a 0.8
                                                                                                       mile-long transmission line. The                      filings:
                                               electronic filings of comments, protests                                                                         Docket Numbers: EC19–14–000.
                                               and interventions in lieu of paper using                proposed project would have an
                                                                                                       estimated average annual generation of                   Applicants: Fawkes Holdings, LLC,
                                               the ‘‘eFiling’’ link at http://                                                                               Wheelabrator Technologies Inc.
                                               www.ferc.gov. Persons unable to file                    32,000 megawatt-hours, and operate
                                                                                                       run-of-river utilizing surplus water from                Description: Joint Application for
                                               electronically should submit an original                                                                      Authorization Under Section 203 of the
                                               and 3 copies of the protest or                          the Aberdeen Lock & Dam, as directed
                                                                                                       by the Corps.                                         Federal Power Act, et al. of
                                               intervention to the Federal Energy                                                                            Wheelabrator Technologies Inc., et al.
                                               Regulatory Commission, 888 First Street                    Applicant Contact: Mr. Jeremy Wells,
                                                                                                       Wells Engineering, LLC, 101 Yearwood                     Filed Date: 10/19/18.
                                               NE, Washington, DC 20426.
                                                                                                       Drive, Macon, Georgia 31206; phone:                      Accession Number: 20181019–5233.
                                                  Comment Date: 5:00 p.m. Eastern                                                                               Comments Due: 5 p.m. ET 11/9/18.
                                                                                                       (478) 238–3054.
                                               Time on November 9, 2018.
                                                                                                          FERC Contact: Michael Spencer, (202)                  Docket Numbers: EC19–15–000.
                                                 Dated: October 19, 2018.                              502–6093, michael.spencer@ferc.gov                       Applicants: Bishop Hill Energy III
                                               Nathaniel J. Davis, Sr.,                                   Deadline for filing comments, motions              LLC, Bishop Hill Interconnection LLC.
khammond on DSK30JT082PROD with NOTICES




                                               Deputy Secretary.                                       to intervene, competing applications                     Description: Joint Application for
                                               [FR Doc. 2018–23440 Filed 10–25–18; 8:45 am]            (without notices of intent), or notices of            Authorization Under Section 203 of the
                                               BILLING CODE 6717–01–P                                  intent to file competing applications: 60             Federal Power Act, et al. of Bishop Hill
                                                                                                       days from the issuance of this notice.                Energy III LLC, et al.
                                                 1 Tennessee Gas Pipeline Company, L.L.C., 162         Competing applications and notices of                    Filed Date: 10/19/18.
                                               FERC ¶61,167 at ¶50 (2018).                             intent must meet the requirements of 18                  Accession Number: 20181019–5235.
                                                 2 18 CFR 385.214(d)(1).                               CFR 4.36.                                                Comments Due: 5 p.m. ET 11/9/18.


                                          VerDate Sep<11>2014   18:32 Oct 25, 2018   Jkt 247001   PO 00000   Frm 00024   Fmt 4703   Sfmt 4703   E:\FR\FM\26OCN1.SGM   26OCN1



Document Created: 2018-10-26 02:27:55
Document Modified: 2018-10-26 02:27:55
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 54103 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR