DEPARTMENT OF THE INTERIOR
Bureau of Indian Affairs

Federal Register Volume 83, Issue 225 (November 21, 2018)

Page Range58784-58785
FR Document2018-25412

This notice advises the public that the Bureau of Indian Affairs (BIA), as lead agency, with the Campo Band of Diegueno Mission Indians of the Campo Indian Reservation (Tribe) as a cooperating agency, intends to gather information necessary for preparing an Environmental Impact Statement (EIS) for the proposed Campo Wind Project, located on the Campo Indian Reservation (Reservation) in southeastern San Diego County, approximately 60 miles east of San Diego, California. Construction of the Campo Wind Project is subject to BIA approval of a lease and sublease, which, as proposed, is a major Federal action under the National Environmental Policy Act of 1969 (NEPA), as amended. A brief description of the proposed action is provided below in the SUPPLEMENTARY INFORMATION section. This notice also announces a public scoping meeting to identify potential issues, concerns, and alternatives to be considered in the EIS. The scoping process will include notice to the public and Federal, State, local, and Tribal agencies of the proposed action.

Federal Register, Volume 83 Issue 225 (Wednesday, November 21, 2018)
[Federal Register Volume 83, Number 225 (Wednesday, November 21, 2018)]
[Notices]
[Pages 58784-58785]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-25412]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Indian Affairs

[190A2100DD/A0A501010.999900 253G]


Notice of Intent To Prepare an Environmental Impact Statement for 
the Proposed Campo Wind Energy Project, San Diego, California

AGENCY: Bureau of Indian Affairs, Interior.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: This notice advises the public that the Bureau of Indian 
Affairs (BIA), as lead agency, with the Campo Band of Diegueno Mission 
Indians of the Campo Indian Reservation (Tribe) as a cooperating 
agency, intends to gather information necessary for preparing an 
Environmental Impact Statement (EIS) for the proposed Campo Wind 
Project, located on the Campo Indian Reservation (Reservation) in 
southeastern San Diego County, approximately 60 miles east of San 
Diego, California. Construction of the Campo Wind Project is subject to 
BIA approval of a lease and sublease, which, as proposed, is a major 
Federal action under the National Environmental Policy Act of 1969 
(NEPA), as amended. A brief description of the proposed action is 
provided below in the SUPPLEMENTARY INFORMATION section. This notice 
also announces a public scoping meeting to identify potential issues, 
concerns, and alternatives to be considered in the EIS. The scoping 
process will include notice to the public and Federal, State, local, 
and Tribal agencies of the proposed action.

DATES: Written comments on the scope and implementation of this 
proposal must arrive by 11:59 p.m. on December 21, 2018. The date and 
location of the public hearing on the EIS will be announced at least 15 
days in advance through a notice to be published in local newspapers 
(The San Diego Union Tribune and The San Diego Business Journal) and 
online at: www.campowind.com.

ADDRESSES: The public may mail or hand-carry written comments to Ms. 
Amy Dutschke, Regional Director, Bureau of Indian Affairs, 2800 Cottage 
Way, Sacramento, California 95825. You may also submit comments through 
email to Mr. Dan (Harold) Hall, Acting Chief, Division of 
Environmental, Cultural Resource Management and Safety, Bureau of 
Indian Affairs, at [email protected]. More information can be found 
in the SUPPLEMENTARY INFORMATION section of this notice.
    Please include the commenter's name, title, return address, and 
``EIS Scoping Comments, Campo Wind Project, San Diego County, 
California,'' on the first page of the written comments. The scoping 
meeting will be held at Campo Indian Reservation Tribal Hall, 36190 
Church Road (BIA Road 10), Campo, California 91906.

FOR FURTHER INFORMATION CONTACT: Mr. Dan (Harold) Hall Acting Chief, 
Division of Environmental, Cultural Resource Management and Safety, 
Bureau of Indian Affairs, by telephone at (916) 978-6041, or by email 
at [email protected].

SUPPLEMENTARY INFORMATION:

Project Description

    BIA approval is required for a lease and sublease to build and 
operate a commercial wind power generation facility capable of 
generating up to 252 megawatts (MW) of electricity.
    The project would include the generation of up to 252 MW consisting 
of up to 60 turbines. The project study area covers approximately 2,200 
acres on the Campo Indian Reservation. The total area that would be 
disturbed by the project would be substantially less. The turbines 
proposed for the project would range from 2.5 MW to 4.2 MW in maximum 
output rating per turbine, tubular steel towers, with a rotor diameter 
of approximately 450 feet, a hub height of approximately 361 feet, and 
a total height of turbine (highest point) of approximately 586 feet. 
Each turbine would be set on a concrete foundation. Turbines would be 
connected by an underground electrical collection system to a project 
collector substation. The collector substation would be sited on 
approximately 2 acres and would consist of a graveled, fenced area 
containing transformer and switching equipment and an area for vehicle 
parking. A new 230 kV overhead generation transmission line would be 
constructed, on the Campo Indian Reservation and partially outside on 
private lands, from the project collector substation on the Reservation 
to a San Diego Gas & Electric (SDG&E) substation/switchyard that would 
be constructed on private lands adjacent to the Sunrise Powerlink 
northeast of the Reservation. The SDG&E substation/switchyard and 
related transmission line improvements will be subject to approval by 
the County of San Diego,

[[Page 58785]]

California, Public Utilities Commission (CPUC) and the BIA. Other 
required facilities, all located within the Reservation, would include: 
Up to three permanent meteorological towers; temporary material laydown 
areas during construction; temporary staging and construction trailer 
areas; an operations and maintenance building; underground cabling; 
telecommunications; new access roads and improvements to portions of 
existing roads; and a temporary concrete batch plant. The wind power 
generation facility would operate year-round for a minimum of 25 years.
    The EIS will analyze the potential environmental impacts of the 
construction and operation of a proposed wind generation facility, 
including access roads, a collector substation, as well as a 
substation/switchyard and transmission facilities. The EIS will be 
prepared in accordance with NEPA (42 U.S.C. 4321 et seq.); the Council 
on Environmental Quality (CEQ) regulations (40 CFR parts 1500-1508); 
Department of the Interior regulations (43 CFR part 46); and the BIA 
NEPA Handbook (59 IAM 3-H) and will also be compliant with the 
California Environmental Quality Act in accordance with Public 
Resources Code section 21083.7. A reasonable range of alternatives to 
the proposed action including a no-action alternative, will be analyzed 
in the EIS. The range of issues and alternatives included will be based 
on comments and information received during the scoping process. This 
notice initiates the public scoping process to identify alternatives 
and relevant issues associated with the proposed project.

Directions for Submitting Public Comments

    During the public scoping meetings, the public may submit written 
and verbal comments. Verbal comments given at the scoping meetings will 
have the same merit as written comments and will be addressed equally. 
The public may mail or hand-carry written comments to Ms. Amy Dutschke, 
Regional Director, Bureau of Indian Affairs, 2800 Cottage Way, 
Sacramento, California 95825. Please include the commenter's name, 
title, return address and ``EIS Scoping Comments, Campo Wind Project, 
San Diego County, California,'' on the first page of the written 
comments.

Public Availability of Comments

    Comments, including names and addresses of respondents, will be 
available for public review at the BIA address shown in the ADDRESSES 
section of this notice, during business hours, 8 a.m. to 4:30 p.m., 
Monday through Friday, except holidays. Individual respondents may 
request confidentiality. If a commenter wishes us to withhold 
commenter's name and/or address from public review or from disclosure 
under the Freedom of Information Act, the commenter must state this 
prominently at the beginning of the written comment. Such requests will 
be honored to the extent allowed by the law, however there is a 
possibility that the comment(s) may be made publicly available at any 
time.

Authority

    This notice is published in accordance with sections 1501.7 
(Scoping), 1506.6 (Public involvement), and 1508.22 (Notice of Intent) 
of the CEQ Regulations (40 CFR parts 1500 through 1508) and section 
46.305 of the Department of the Interior Regulations (43 CFR part 46), 
implementing the procedural requirements of NEPA, as amended (42 U.S.C. 
4321 et seq.), and is in the exercise of authority delegated to the 
Assistant Secretary--Indian Affairs by 209 DM 8.

    Dated: November 9, 2018.
Tara Sweeney,
Assistant Secretary--Indian Affairs.
[FR Doc. 2018-25412 Filed 11-20-18; 8:45 am]
BILLING CODE 4337-15-P



                                               58784                   Federal Register / Vol. 83, No. 225 / Wednesday, November 21, 2018 / Notices

                                               not for public use, would be located on                   Dated: November 9, 2018.                            Chief, Division of Environmental,
                                               East Ellis Road.                                        Tara Sweeney,                                         Cultural Resource Management and
                                                  The following alternatives are                       Assistant Secretary—Indian Affairs.                   Safety, Bureau of Indian Affairs, at
                                               considered in the DEIS: (1) Proposed                    [FR Doc. 2018–25411 Filed 11–20–18; 8:45 am]          harold.hall@bia.gov. More information
                                               Project; (2) Reduced Intensity                          BILLING CODE 4337–15–P
                                                                                                                                                             can be found in the SUPPLEMENTARY
                                                                                                                                                             INFORMATION section of this notice.
                                               Alternative; (3) Non-Gaming
                                                                                                                                                                Please include the commenter’s name,
                                               Alternative; (4) Custer Site Alternative
                                                                                                       DEPARTMENT OF THE INTERIOR                            title, return address, and ‘‘EIS Scoping
                                               and (5) No Action/No Development.
                                                                                                                                                             Comments, Campo Wind Project, San
                                               Environmental issues addressed in the                   Bureau of Indian Affairs                              Diego County, California,’’ on the first
                                               DEIS include geology and soils, water                                                                         page of the written comments. The
                                               resources, air quality, biological                      [190A2100DD/A0A501010.999900 253G]
                                                                                                                                                             scoping meeting will be held at Campo
                                               resources, cultural and paleontological                                                                       Indian Reservation Tribal Hall, 36190
                                               resources, socioeconomic conditions                     Notice of Intent To Prepare an
                                                                                                       Environmental Impact Statement for                    Church Road (BIA Road 10), Campo,
                                               (including environmental justice),                                                                            California 91906.
                                               transportation and circulation, land use,               the Proposed Campo Wind Energy
                                                                                                       Project, San Diego, California                        FOR FURTHER INFORMATION CONTACT: Mr.
                                               public services, noise, hazardous                                                                             Dan (Harold) Hall Acting Chief, Division
                                               materials, aesthetics, cumulative effects,              AGENCY:   Bureau of Indian Affairs,                   of Environmental, Cultural Resource
                                               and indirect and growth-inducing                        Interior.                                             Management and Safety, Bureau of
                                               effects.                                                ACTION: Notice of intent.                             Indian Affairs, by telephone at (916)
                                                  Locations where the DEIS is available                                                                      978–6041, or by email at harold.hall@
                                               for review: The DEIS will be available                  SUMMARY:   This notice advises the public             bia.gov.
                                               for review at the Fruitport Public                      that the Bureau of Indian Affairs (BIA),
                                                                                                       as lead agency, with the Campo Band of                SUPPLEMENTARY INFORMATION:
                                               Library located at 47 Park St., Fruitport,
                                                                                                       Diegueno Mission Indians of the Campo                 Project Description
                                               Michigan 49415, and online at
                                                                                                       Indian Reservation (Tribe) as a
                                               www.littlerivereis.com. To obtain a                                                                              BIA approval is required for a lease
                                                                                                       cooperating agency, intends to gather
                                               compact disk copy of the DEIS, please                                                                         and sublease to build and operate a
                                                                                                       information necessary for preparing an
                                               provide your name and address in                                                                              commercial wind power generation
                                                                                                       Environmental Impact Statement (EIS)
                                               writing to Mr. Felix Kitto, Bureau of                                                                         facility capable of generating up to 252
                                                                                                       for the proposed Campo Wind Project,
                                               Indian Affairs, Midwest Regional Office.                located on the Campo Indian                           megawatts (MW) of electricity.
                                               Contact information is listed in the FOR                Reservation (Reservation) in                             The project would include the
                                               FURTHER INFORMATION CONTACT section of
                                                                                                       southeastern San Diego County,                        generation of up to 252 MW consisting
                                               this notice. Individual paper copies of                 approximately 60 miles east of San                    of up to 60 turbines. The project study
                                               the DEIS will be provided only upon                     Diego, California. Construction of the                area covers approximately 2,200 acres
                                               payment of applicable printing expenses                 Campo Wind Project is subject to BIA                  on the Campo Indian Reservation. The
                                               by the requestor for the number of                      approval of a lease and sublease, which,              total area that would be disturbed by the
                                               copies requested.                                       as proposed, is a major Federal action                project would be substantially less. The
                                                                                                       under the National Environmental                      turbines proposed for the project would
                                                  Public comment availability:
                                                                                                       Policy Act of 1969 (NEPA), as amended.                range from 2.5 MW to 4.2 MW in
                                               Comments, including names and
                                                                                                       A brief description of the proposed                   maximum output rating per turbine,
                                               addresses of respondents, will be
                                                                                                       action is provided below in the                       tubular steel towers, with a rotor
                                               available for public review at the BIA
                                                                                                       SUPPLEMENTARY INFORMATION section.
                                                                                                                                                             diameter of approximately 450 feet, a
                                               address shown in the ADDRESSES
                                                                                                       This notice also announces a public                   hub height of approximately 361 feet,
                                               section, during regular business hours, 8                                                                     and a total height of turbine (highest
                                               a.m. to 4:30 p.m., Monday through                       scoping meeting to identify potential
                                                                                                       issues, concerns, and alternatives to be              point) of approximately 586 feet. Each
                                               Friday, except holidays. Before                                                                               turbine would be set on a concrete
                                               including your address, phone number,                   considered in the EIS. The scoping
                                                                                                       process will include notice to the public             foundation. Turbines would be
                                               email address, or other personal                                                                              connected by an underground electrical
                                               identifying information in your                         and Federal, State, local, and Tribal
                                                                                                       agencies of the proposed action.                      collection system to a project collector
                                               comment, you should be aware that                                                                             substation. The collector substation
                                               your entire comment—including your                      DATES: Written comments on the scope
                                                                                                                                                             would be sited on approximately 2 acres
                                               personal identifying information—may                    and implementation of this proposal                   and would consist of a graveled, fenced
                                               be made publicly available at any time.                 must arrive by 11:59 p.m. on December                 area containing transformer and
                                               While you can ask in your comment that                  21, 2018. The date and location of the                switching equipment and an area for
                                               your personal identifying information                   public hearing on the EIS will be                     vehicle parking. A new 230 kV overhead
                                               be withheld from public review, the BIA                 announced at least 15 days in advance                 generation transmission line would be
                                               cannot guarantee that this will occur.                  through a notice to be published in local             constructed, on the Campo Indian
                                                                                                       newspapers (The San Diego Union                       Reservation and partially outside on
                                                 Authority: This notice is published
                                                                                                       Tribune and The San Diego Business                    private lands, from the project collector
                                               pursuant to Sec. 1503.1 of the Council of
                                                                                                       Journal) and online at:                               substation on the Reservation to a San
                                               Environmental Quality Regulations (40 CFR
                                                                                                       www.campowind.com.                                    Diego Gas & Electric (SDG&E)
khammond on DSK30JT082PROD with NOTICES




                                               parts 1500 through 1508) and Sec. 46.305 of
                                               the Department of the Interior Regulations              ADDRESSES:  The public may mail or                    substation/switchyard that would be
                                               (43 CFR part 46), implementing the                      hand-carry written comments to Ms.                    constructed on private lands adjacent to
                                               procedural requirements of the NEPA of l969,            Amy Dutschke, Regional Director,                      the Sunrise Powerlink northeast of the
                                               as amended (42 U.S.C. 4371, et seq.), and is            Bureau of Indian Affairs, 2800 Cottage                Reservation. The SDG&E substation/
                                               in the exercise of authority delegated to the           Way, Sacramento, California 95825. You                switchyard and related transmission
                                               Assistant Secretary—Indian Affairs by 209               may also submit comments through                      line improvements will be subject to
                                               DM 8.                                                   email to Mr. Dan (Harold) Hall, Acting                approval by the County of San Diego,


                                          VerDate Sep<11>2014   16:08 Nov 20, 2018   Jkt 247001   PO 00000   Frm 00030   Fmt 4703   Sfmt 4703   E:\FR\FM\21NON1.SGM   21NON1


                                                                       Federal Register / Vol. 83, No. 225 / Wednesday, November 21, 2018 / Notices                                            58785

                                               California, Public Utilities Commission                 of this notice, during business hours, 8              for the NPR–A IAP/EIS project may be
                                               (CPUC) and the BIA. Other required                      a.m. to 4:30 p.m., Monday through                     submitted in writing until January 7,
                                               facilities, all located within the                      Friday, except holidays. Individual                   2019. The BLM will also provide
                                               Reservation, would include: Up to three                 respondents may request                               opportunities for public participation
                                               permanent meteorological towers;                        confidentiality. If a commenter wishes                during scoping meetings with
                                               temporary material laydown areas                        us to withhold commenter’s name and/                  appropriate public notice. The date(s)
                                               during construction; temporary staging                  or address from public review or from                 and location(s) of scoping meetings will
                                               and construction trailer areas; an                      disclosure under the Freedom of                       be announced in advance through local
                                               operations and maintenance building;                    Information Act, the commenter must                   media, newspapers, and the BLM
                                               underground cabling;                                    state this prominently at the beginning               website at: www.blm.gov/alaska.
                                               telecommunications; new access roads                    of the written comment. Such requests                    In order to be considered for the Draft
                                               and improvements to portions of                         will be honored to the extent allowed by              IAP/EIS, all comments must be received
                                               existing roads; and a temporary concrete                the law, however there is a possibility               prior to the close of the 45-day scoping
                                               batch plant. The wind power generation                  that the comment(s) may be made                       period. Federal, State or local agencies,
                                               facility would operate year-round for a                 publicly available at any time.                       or tribes who are interested in serving
                                               minimum of 25 years.                                                                                          as a cooperating agency for the
                                                  The EIS will analyze the potential                   Authority                                             development of the IAP/EIS are asked to
                                               environmental impacts of the                               This notice is published in                        submit such requests to the BLM.
                                               construction and operation of a                         accordance with sections 1501.7                       ADDRESSES: You may submit comments
                                               proposed wind generation facility,                      (Scoping), 1506.6 (Public involvement),               on issues related to the proposed NPR–
                                               including access roads, a collector                     and 1508.22 (Notice of Intent) of the                 A IAP/EIS project by any of the
                                               substation, as well as a substation/                    CEQ Regulations (40 CFR parts 1500                    following methods:
                                               switchyard and transmission facilities.                 through 1508) and section 46.305 of the                  • Online: http://www.blm.gov/alaska/
                                               The EIS will be prepared in accordance                  Department of the Interior Regulations                NPR-A-IAP-EIS.
                                               with NEPA (42 U.S.C. 4321 et seq.); the                 (43 CFR part 46), implementing the                       • Fax: (907) 271–5479.
                                               Council on Environmental Quality                        procedural requirements of NEPA, as                      • Mail: NPR–A IAP/EIS Scoping
                                               (CEQ) regulations (40 CFR parts 1500–                   amended (42 U.S.C. 4321 et seq.), and                 Comments, 222 West 7th Avenue,
                                               1508); Department of the Interior                       is in the exercise of authority delegated             Mailstop #13, Anchorage, AK 99513.
                                               regulations (43 CFR part 46); and the                   to the Assistant Secretary—Indian                        The 2013 IAP/EIS ROD can be
                                               BIA NEPA Handbook (59 IAM 3–H) and                      Affairs by 209 DM 8.                                  downloaded from the BLM’s website at
                                               will also be compliant with the                                                                               www.blm.gov/alaska, and you can view
                                                                                                         Dated: November 9, 2018.
                                               California Environmental Quality Act in                                                                       hard copies at the BLM Alaska Public
                                               accordance with Public Resources Code                   Tara Sweeney,
                                                                                                                                                             Information Center (‘‘Public Room’’),
                                               section 21083.7. A reasonable range of                  Assistant Secretary—Indian Affairs.                   Arctic District Office, 222 University
                                               alternatives to the proposed action                     [FR Doc. 2018–25412 Filed 11–20–18; 8:45 am]          Avenue, Fairbanks, Alaska, and at the
                                               including a no-action alternative, will                 BILLING CODE 4337–15–P                                BLM Alaska Public Information Center
                                               be analyzed in the EIS. The range of                                                                          (‘‘Public Room’’), Alaska State Office,
                                               issues and alternatives included will be                                                                      222 West 8th Avenue, Anchorage,
                                               based on comments and information                       DEPARTMENT OF THE INTERIOR                            Alaska.
                                               received during the scoping process.
                                                                                                       Bureau of Land Management                             FOR FURTHER INFORMATION CONTACT:
                                               This notice initiates the public scoping
                                                                                                                                                             Stephanie Rice; Planning and
                                               process to identify alternatives and                    [19X.LLAK930000.L13100000.DS0000]
                                                                                                                                                             Environmental Coordinator, 907–271–
                                               relevant issues associated with the
                                                                                                       Notice of Intent To Prepare an                        3202, srice@blm.gov. You may also
                                               proposed project.
                                                                                                       Integrated Activity Plan and                          request to be added to the mailing list.
                                               Directions for Submitting Public                        Environmental Impact Statement for                    People who use a telecommunications
                                               Comments                                                the National Petroleum Reserve in                     device for the deaf (TDD) may call the
                                                 During the public scoping meetings,                   Alaska                                                Federal Relay Service (FRS) at 1–800–
                                               the public may submit written and                                                                             877–8339 to contact the above
                                               verbal comments. Verbal comments                        AGENCY:   Bureau of Land Management,                  individual during normal business
                                               given at the scoping meetings will have                 Interior.                                             hours. The FRS is available 24 hours a
                                               the same merit as written comments and                  ACTION: Notice of intent.                             day, seven days a week, to leave a
                                               will be addressed equally. The public                                                                         message or question with the above
                                               may mail or hand-carry written                          SUMMARY:   In accordance with the Naval               individual. You will receive a reply
                                               comments to Ms. Amy Dutschke,                           Petroleum Reserves Production Act of                  during normal business hours.
                                               Regional Director, Bureau of Indian                     1976, as amended, the Bureau of Land                  SUPPLEMENTARY INFORMATION: This
                                               Affairs, 2800 Cottage Way, Sacramento,                  Management (BLM) Alaska State Office,                 notice initiates the public scoping
                                               California 95825. Please include the                    Anchorage, Alaska, intends to prepare a               process for the EIS. Comments regarding
                                               commenter’s name, title, return address                 new Integrated Activity Plan and                      management decisions, resources to be
                                               and ‘‘EIS Scoping Comments, Campo                       Environmental Impact Statement (IAP/                  addressed, and issues for analysis will
                                               Wind Project, San Diego County,                         EIS) for BLM-managed lands within the                 assist the BLM in defining the proposed
                                                                                                       National Petroleum Reserve in Alaska
khammond on DSK30JT082PROD with NOTICES




                                               California,’’ on the first page of the                                                                        actions and alternatives for the NPR–A
                                               written comments.                                       (NPR–A). By this notice, the BLM is                   IAP/EIS.
                                                                                                       announcing the beginning of the                          The Naval Petroleum Reserves
                                               Public Availability of Comments                         Environmental Impact Statement (EIS)                  Production Act (42 U.S.C. 6501), as
                                                 Comments, including names and                         scoping process to solicit public                     amended, excludes the NPR–A from the
                                               addresses of respondents, will be                       comments and identify issues.                         application of Section 202 of the Federal
                                               available for public review at the BIA                  DATES: Comments on relevant issues                    Land Policy and Management Act (43
                                               address shown in the ADDRESSES section                  that will influence the scope of the EIS              U.S.C. 1701), as amended, which is the


                                          VerDate Sep<11>2014   16:08 Nov 20, 2018   Jkt 247001   PO 00000   Frm 00031   Fmt 4703   Sfmt 4703   E:\FR\FM\21NON1.SGM   21NON1



Document Created: 2018-11-21 03:11:56
Document Modified: 2018-11-21 03:11:56
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of intent.
DatesWritten comments on the scope and implementation of this proposal must arrive by 11:59 p.m. on December 21, 2018. The date and location of the public hearing on the EIS will be announced at least 15 days in advance through a notice to be published in local newspapers (The San Diego Union Tribune and The San Diego Business Journal) and online at: www.campowind.com.
ContactMr. Dan (Harold) Hall Acting Chief, Division of Environmental, Cultural Resource Management and Safety, Bureau of Indian Affairs, by telephone at (916) 978-6041, or by email at [email protected]
FR Citation83 FR 58784 