83 FR 62250 - Drawbridge Operation Regulation; Delaware River, Burlington, NJ and Bristol, PA

DEPARTMENT OF HOMELAND SECURITY
Coast Guard

Federal Register Volume 83, Issue 232 (December 3, 2018)

Page Range62250-62250
FR Document2018-26148

The Coast Guard has issued a temporary deviation from the operating schedule that governs the SR 413/Burlington-Bristol bridge, which carries SR 413 across the Delaware River, mile 117.8, between Burlington, NJ and Bristol, PA. The deviation is necessary to facilitate an inspection and bridge maintenance. This deviation allows the bridge to remain in the closed-to-navigation position.

Federal Register, Volume 83 Issue 232 (Monday, December 3, 2018)
[Federal Register Volume 83, Number 232 (Monday, December 3, 2018)]
[Rules and Regulations]
[Page 62250]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-26148]



[[Page 62250]]

-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[Docket No. USCG-2018-1013]


Drawbridge Operation Regulation; Delaware River, Burlington, NJ 
and Bristol, PA

AGENCY: Coast Guard, DHS.

ACTION: Notice of deviation from drawbridge regulation.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard has issued a temporary deviation from the 
operating schedule that governs the SR 413/Burlington-Bristol bridge, 
which carries SR 413 across the Delaware River, mile 117.8, between 
Burlington, NJ and Bristol, PA. The deviation is necessary to 
facilitate an inspection and bridge maintenance. This deviation allows 
the bridge to remain in the closed-to-navigation position.

DATES: This deviation is effective without actual notice from December 
3, 2018 through 3 p.m. on December 14, 2018. For the purposes of 
enforcement, actual notice will be used from 7 a.m. on November 26, 
2018, until December 3, 2018.

ADDRESSES: The docket for this deviation, USCG-2018-1013 is available 
at http://www.regulations.gov. Type the docket number in the ``SEARCH'' 
box and click ``SEARCH''. Click on Open Docket Folder on the line 
associated with this deviation.

FOR FURTHER INFORMATION CONTACT: If you have questions on this 
temporary deviation, call or email Mr. Michael Thorogood, Bridge 
Administration Branch Fifth District, Coast Guard, telephone 757-398-
6557, email [email protected].

SUPPLEMENTARY INFORMATION:  The Burlington County Bridge Commission, 
owner and operator of the SR 413/Burlington-Bristol bridge, that 
carries SR 413 across the Delaware River, mile 117.8, between 
Burlington, NJ and Bristol, PA, has requested a temporary deviation 
from the current operating schedule to facilitate an inspection and 
maintenance of various mechanical components of the vertical lift span 
of the drawbridge. The bridge has a vertical clearance of 135 feet 
above mean high water in the open position, and 61 feet above mean high 
water in the closed position.
    The current operating schedule is set out in 33 CFR 117.716. Under 
this temporary deviation, the bridge will be in the closed-to-
navigation position from 7 a.m. through 3 p.m.; Monday through Friday; 
from 7 a.m. on November 26, 2018, through 3 p.m. on December 14, 2018.
    The Delaware River is used by a variety of vessels including deep 
draft commercial vessels, U.S. government and public vessels, small 
commercial vessels, tug and barge traffic, and recreational vessels. 
The Coast Guard has carefully coordinated the restrictions with 
waterway users in publishing this temporary deviation.
    Vessels able to pass through the bridge in the closed-to-navigation 
position may do so at any time. The bridge will open on signal, if at 
least eight hours prior notification is given. The bridge will not be 
able to open for emergencies and there is no immediate alternative 
route for vessels unable to pass through the bridge in the closed 
position. The Coast Guard will also inform the users of the waterway 
through our Local Notice and Broadcast Notices to Mariners of the 
change in operating schedule for the bridge so that vessel operators 
can arrange their transits to minimize any impact caused by the 
temporary deviation.
    In accordance with 33 CFR 117.35(e), the drawbridge must return to 
its regular operating schedule immediately at the end of the effective 
period of this temporary deviation. This deviation from the operating 
regulations is authorized under 33 CFR 117.35.

    Dated: November 27, 2018.
Hal R. Pitts,
Bridge Program Manager, Fifth Coast Guard District.
[FR Doc. 2018-26148 Filed 11-30-18; 8:45 am]
 BILLING CODE 9110-04-P


Current View
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionRules and Regulations
ActionNotice of deviation from drawbridge regulation.
DatesThis deviation is effective without actual notice from December 3, 2018 through 3 p.m. on December 14, 2018. For the purposes of enforcement, actual notice will be used from 7 a.m. on November 26, 2018, until December 3, 2018.
ContactIf you have questions on this temporary deviation, call or email Mr. Michael Thorogood, Bridge Administration Branch Fifth District, Coast Guard, telephone 757-398- 6557, email [email protected]
FR Citation83 FR 62250 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR