83_FR_64089 83 FR 63851 - Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization

83 FR 63851 - Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 238 (December 12, 2018)

Page Range63851-63852
FR Document2018-26889

Federal Register, Volume 83 Issue 238 (Wednesday, December 12, 2018)
[Federal Register Volume 83, Number 238 (Wednesday, December 12, 2018)]
[Notices]
[Pages 63851-63852]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-26889]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-21-000]


Columbia Gas Transmission, LLC; Notice of Request Under Blanket 
Authorization

    Take notice that on November 27, 2018, Columbia Gas Transmission, 
LLC (Columbia) 700 Louisiana Street, Suite 700, Houston, Texas 77002-
2700, filed in Docket No. CP19-21-000 a prior notice request pursuant 
to sections 157.205 and 157.213 of the Commission's regulations under 
the Natural Gas Act (NGA), and Columbia's blanket certificate issued in 
Docket No. CP83-76-000, to construct and operate its Artemas A Storage 
Field New Wells Project (Project). The Project consists of three new 
directional storage wells and related pipelines and appurtenances at 
Columbia's Artemas A Storage Field, located in Bedford County, 
Pennsylvania.
    Columbia states that the Project is part of the efforts to improve 
storage deliverability of the Artemas A Storage Field, as part of the 
Modernization II Settlement that it entered with its shippers. The 
Artemas A Storage Field currently consists of 17 active wells and is 
operated with a total capacity of 14.457 billion cubic feet (Bcf) 
consisting of 13.70 Bcf of certificated base and working gas, and 
approximately 0.757 Bcf of residual native gas. Columbia asserts that 
the Project could provide 58 to 79 Million cubic feet per day of 
restored deliverability to the Columbia storage system. Columbia avers 
that the proposed three new wells will be drilled at three of four 
potential well sites that are currently under evaluation and that the 
selection will depend upon which combination of sites will provide the 
desired restored deliverability with the least risk. Columbia states 
that it will notify the Commission of the three well sites selected for 
the Project prior commencement of construction. Columbia estimates the 
cost of the Project to be between $25.4 million to $28.2 million, 
depending upon which three of the four potential well sites are 
selected, all as more fully set forth in the application which is on 
file with the Commission and open to public inspection. The filing may 
also be viewed on the web at http://www.ferc.gov using the eLibrary 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, please 
contact FERC Online Support at [email protected] or toll free 
at (866) 208-3676, or TTY, contact (202) 502-8659.
    Any questions concerning this application may be directed to Linda 
Farquhar, Manager, Project Determinations & Regulatory Administration, 
Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 700, 
Houston, Texas, 77002-2700, by telephone at (832) 320-5685, by 
facsimile at (832) 320-6685, or by email at 
[email protected].
    Any person or the Commission's staff may, within 60 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to section 157.205 of 
the regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the allowed time for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice, the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process.

[[Page 63852]]

Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions in lieu of paper using the eFiling link at 
http://www.ferc.gov. Persons unable to file electronically should 
submit an original and seven copies of the protest or intervention to 
the Federal Energy Regulatory Commission, 888 First Street, NE, 
Washington, DC 20426.

    Dated: December 6, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-26889 Filed 12-11-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                       Federal Register / Vol. 83, No. 238 / Wednesday, December 12, 2018 / Notices                                            63851

                                                Description: Tariff Cancellation:                     DEPARTMENT OF ENERGY                                  ferc.gov or toll free at (866) 208–3676, or
                                              Notice of Termination of Proxima Solar                                                                        TTY, contact (202) 502–8659.
                                              E&P Agreement to be effective 12/3/                     Federal Energy Regulatory                                Any questions concerning this
                                              2018.                                                   Commission                                            application may be directed to Linda
                                                Filed Date: 12/6/18.                                  [Docket No. CP19–21–000]
                                                                                                                                                            Farquhar, Manager, Project
                                                Accession Number: 20181206–5237.                                                                            Determinations & Regulatory
                                                                                                      Columbia Gas Transmission, LLC;                       Administration, Columbia Gas
                                                Comments Due: 5 p.m. ET 12/27/18.                                                                           Transmission, LLC, 700 Louisiana
                                                                                                      Notice of Request Under Blanket
                                                Docket Numbers: ER19–504–000.                         Authorization                                         Street, Suite 700, Houston, Texas,
                                                Applicants: Southern California                                                                             77002–2700, by telephone at (832) 320–
                                              Edison Company.                                            Take notice that on November 27,                   5685, by facsimile at (832) 320–6685, or
                                                                                                      2018, Columbia Gas Transmission, LLC                  by email at linda_farquhar@
                                                Description: Tariff Cancellation:                     (Columbia) 700 Louisiana Street, Suite
                                              Notice of Cancellation Distribution                                                                           transcanada.com.
                                                                                                      700, Houston, Texas 77002–2700, filed                    Any person or the Commission’s staff
                                              Service Agreement Decade Energy, LLC                    in Docket No. CP19–21–000 a prior
                                              to be effective 11/27/2017.                                                                                   may, within 60 days after issuance of
                                                                                                      notice request pursuant to sections                   the instant notice by the Commission,
                                                Filed Date: 12/6/18.                                  157.205 and 157.213 of the                            file pursuant to Rule 214 of the
                                                Accession Number: 20181206–5251.                      Commission’s regulations under the                    Commission’s Procedural Rules (18 CFR
                                                Comments Due: 5 p.m. ET 12/27/18.                     Natural Gas Act (NGA), and Columbia’s                 385.214) a motion to intervene or notice
                                                                                                      blanket certificate issued in Docket No.              of intervention and pursuant to section
                                                Docket Numbers: ER19–506–000.
                                                                                                      CP83–76–000, to construct and operate                 157.205 of the regulations under the
                                                Applicants: PJM Interconnection,                      its Artemas A Storage Field New Wells                 NGA (18 CFR 157.205), a protest to the
                                              L.L.C.                                                  Project (Project). The Project consists of            request. If no protest is filed within the
                                                Description: § 205(d) Rate Filing:                    three new directional storage wells and               time allowed therefore, the proposed
                                              Amendment to ISA No. 3198; Queue                        related pipelines and appurtenances at                activity shall be deemed to be
                                              No. T157 to be effective 1/16/2012.                     Columbia’s Artemas A Storage Field,                   authorized effective the day after the
                                                Filed Date: 12/6/18.                                  located in Bedford County,                            time allowed for filing a protest. If a
                                                Accession Number: 20181206–5269.                      Pennsylvania.                                         protest is filed and not withdrawn
                                                Comments Due: 5 p.m. ET 12/27/18.                        Columbia states that the Project is part           within 30 days after the allowed time
                                                                                                      of the efforts to improve storage                     for filing a protest, the instant request
                                                 Docket Numbers: ER19–507–000.                        deliverability of the Artemas A Storage               shall be treated as an application for
                                                 Applicants: Midcontinent                             Field, as part of the Modernization II                authorization pursuant to section 7 of
                                              Independent System Operator, Inc.                       Settlement that it entered with its                   the NGA.
                                                 Description: § 205(d) Rate Filing:                   shippers. The Artemas A Storage Field                    Pursuant to section 157.9 of the
                                              2018–12–06_Revisions to Attachment                      currently consists of 17 active wells and             Commission’s rules (18 CFR 157.9),
                                              FF re Cure Period for Recertification to                is operated with a total capacity of                  within 90 days of this Notice, the
                                              be effective 2/6/2019.                                  14.457 billion cubic feet (Bcf) consisting            Commission staff will either: complete
                                                 Filed Date: 12/6/18.                                 of 13.70 Bcf of certificated base and                 its environmental assessment (EA) and
                                                                                                      working gas, and approximately 0.757                  place it into the Commission’s public
                                                 Accession Number: 20181206–5280.
                                                                                                      Bcf of residual native gas. Columbia                  record (eLibrary) for this proceeding; or
                                                 Comments Due: 5 p.m. ET 12/27/18.                    asserts that the Project could provide 58             issue a Notice of Schedule for
                                                 The filings are accessible in the                    to 79 Million cubic feet per day of                   Environmental Review. If a Notice of
                                              Commission’s eLibrary system by                         restored deliverability to the Columbia               Schedule for Environmental Review is
                                              clicking on the links or querying the                   storage system. Columbia avers that the               issued, it will indicate, among other
                                              docket number.                                          proposed three new wells will be drilled              milestones, the anticipated date for the
                                                 Any person desiring to intervene or                  at three of four potential well sites that            Commission staff’s issuance of the EA
                                              protest in any of the above proceedings                 are currently under evaluation and that               for this proposal. The filing of the EA
                                              must file in accordance with Rules 211                  the selection will depend upon which                  in the Commission’s public record for
                                              and 214 of the Commission’s                             combination of sites will provide the                 this proceeding or the issuance of a
                                              Regulations (18 CFR 385.211 and                         desired restored deliverability with the              Notice of Schedule for Environmental
                                              385.214) on or before 5:00 p.m. Eastern                 least risk. Columbia states that it will              Review will serve to notify federal and
                                              time on the specified comment date.                     notify the Commission of the three well               state agencies of the timing for the
                                              Protests may be considered, but                         sites selected for the Project prior                  completion of all necessary reviews, and
                                              intervention is necessary to become a                   commencement of construction.                         the subsequent need to complete all
                                              party to the proceeding.                                Columbia estimates the cost of the                    federal authorizations within 90 days of
                                                 eFiling is encouraged. More detailed                 Project to be between $25.4 million to                the date of issuance of the Commission
                                              information relating to filing                          $28.2 million, depending upon which                   staff’s EA.
                                              requirements, interventions, protests,                  three of the four potential well sites are               Persons who wish to comment only
                                              service, and qualifying facilities filings              selected, all as more fully set forth in              on the environmental review of this
                                              can be found at: http://www.ferc.gov/                   the application which is on file with the             project should submit an original and
                                              docs-filing/efiling/filing-req.pdf. For                 Commission and open to public                         two copies of their comments to the
                                              other information, call (866) 208–3676                  inspection. The filing may also be                    Secretary of the Commission.
amozie on DSK3GDR082PROD with NOTICES1




                                              (toll free). For TTY, call (202) 502–8659.              viewed on the web at http://                          Environmental commenters will be
                                                                                                      www.ferc.gov using the eLibrary link.                 placed on the Commission’s
                                                Dated: December 6, 2018.                              Enter the docket number excluding the                 environmental mailing list, will receive
                                              Nathaniel J. Davis, Sr.,                                last three digits in the docket number                copies of the environmental documents,
                                              Deputy Secretary.                                       field to access the document. For                     and will be notified of meetings
                                              [FR Doc. 2018–26892 Filed 12–11–18; 8:45 am]            assistance, please contact FERC Online                associated with the Commission’s
                                              BILLING CODE 6717–01–P                                  Support at FERCOnlineSupport@                         environmental review process.


                                         VerDate Sep<11>2014   18:39 Dec 11, 2018   Jkt 247001   PO 00000   Frm 00027   Fmt 4703   Sfmt 4703   E:\FR\FM\12DEN1.SGM   12DEN1


                                              63852                    Federal Register / Vol. 83, No. 238 / Wednesday, December 12, 2018 / Notices

                                              Environmental commenters will not be                       Accession Number: 20181203–5185.                      Accession Number: 20181204–5080.
                                              required to serve copies of filed                          Comments Due: 5 p.m. ET 12/24/18.                     Comments Due: 5 p.m. ET 12/26/18.
                                              documents on all other parties.                            Docket Numbers: ER18–2253–001.                        Docket Numbers: ER19–466–000.
                                              However, the non-party commenters,                         Applicants: Martins Creek, LLC.                       Applicants: Golden Spread Electric
                                              will not receive copies of all documents                   Description: Compliance filing:                    Cooperative, Inc.
                                              filed by other parties or issued by the                 Reactive Service Rate Schedule                           Description: § 205(d) Rate Filing:
                                              Commission (except for the mailing of                   Compliance Filings to be effective 12/3/              Amended and Restated WPC—Rider F
                                              environmental documents issued by the                   2018.                                                 and REC to be effective 1/1/2019.
                                              Commission) and will not have the right                    Filed Date: 12/4/18.                                  Filed Date: 12/3/18.
                                              to seek court review of the                                Accession Number: 20181204–5107.                      Accession Number: 20181203–5249.
                                              Commission’s final order.                                  Comments Due: 5 p.m. ET 12/26/18.                     Comments Due: 5 p.m. ET 12/24/18.
                                                 The Commission strongly encourages                      Docket Numbers: ER18–2254–001.                        Docket Numbers: ER19–467–000.
                                              electronic filings of comments, protests,                  Applicants: MC Project Company                        Applicants: New York Independent
                                              and interventions in lieu of paper using                LLC.                                                  System Operator, Inc.
                                              the eFiling link at http://www.ferc.gov.                   Description: Compliance filing:                       Description: Compliance filing:
                                              Persons unable to file electronically                   Reactive Service Rate Schedule                        NYISO Order 841 compliance revisions
                                              should submit an original and seven                     Compliance Filings to be effective 12/3/              re: Electrice Storage Resources (ESRs) to
                                              copies of the protest or intervention to                2018.                                                 be effective 12/31/9998.
                                              the Federal Energy Regulatory                              Filed Date: 12/4/18.                                  Filed Date: 12/3/18.
                                              Commission, 888 First Street, NE,                          Accession Number: 20181204–5111.                      Accession Number: 20181203–5276.
                                              Washington, DC 20426.                                      Comments Due: 5 p.m. ET 12/26/18.                     Comments Due: 5 p.m. ET 12/24/18.
                                                Dated: December 6, 2018.                                 Docket Numbers: ER18–2496–001.                        Docket Numbers: ER19–468–000.
                                              Nathaniel J. Davis, Sr.,                                   Applicants: PJM Interconnection,                      Applicants: California Independent
                                              Deputy Secretary.                                       L.L.C.                                                System Operator Corporation.
                                              [FR Doc. 2018–26889 Filed 12–11–18; 8:45 am]               Description: Compliance filing:                       Description: Compliance filing: 2018–
                                              BILLING CODE 6717–01–P                                  Compliance Filing to the Commission’s                 12–03 Order No. 841 Compliance to be
                                                                                                      11/29/2018 re: Rate Schedule No. 48 to                effective 12/3/2018.
                                                                                                      be effective 12/1/2018.                                  Filed Date: 12/3/18.
                                              DEPARTMENT OF ENERGY                                       Filed Date: 12/4/18.                                  Accession Number: 20181203–5278.
                                                                                                         Accession Number: 20181204–5123.                      Comments Due: 5 p.m. ET 12/24/18.
                                              Federal Energy Regulatory                                  Comments Due: 5 p.m. ET 12/26/18.                     Docket Numbers: ER19–469–000.
                                              Commission                                                 Docket Numbers: ER19–29–004.                          Applicants: PJM Interconnection,
                                                                                                         Applicants: NorthWestern                           L.L.C.
                                              Combined Notice of Filings #1
                                                                                                      Corporation.                                             Description: Compliance filing:
                                                 Take notice that the Commission                         Description: Compliance filing:                    Compliance Filing re Order No. 841 ESR
                                              received the following electric rate                    Compliance Filing to Migrate Great Falls              Markets and Operations Proposal to be
                                              filings:                                                NITSA to Tariff ID 41 (Part 1 of 2) to be             effective 12/3/2019.
                                                 Docket Numbers: ER17–349–002.                        effective 10/8/2018.                                     Filed Date: 12/3/18.
                                                 Applicants: Transource Maryland,                        Filed Date: 12/3/18.                                  Accession Number: 20181203–5296.
                                              LLC, Transource Pennsylvania, LLC,                         Accession Number: 20181203–5190.                      Comments Due: 5 p.m. ET 12/24/18.
                                              PJM Interconnection, L.L.C.                                Comments Due: 5 p.m. ET 12/24/18.                     Docket Numbers: ER19–470–000.
                                                 Description: Compliance filing:                         Docket Numbers: ER19–29–005.                          Applicants: ISO New England Inc.,
                                              Compliance filing per the Commission’s                     Applicants: NorthWestern                           New England Power Pool Participants
                                              11/1/2018 order re: DEA, SA No. 4579                    Corporation.                                          Committee.
                                              to be effective 11/2/2016.                                 Description: Compliance filing:                       Description: Compliance filing:
                                                 Filed Date: 12/3/18.                                 Compliance Filing to Migrate Great Falls              Revisions to ISO–NE Tariff in
                                                 Accession Number: 20181203–5169.                     NITSA to Tariff ID 41 (Part 2 of 2) to be             Compliance with FERC Order No. 841 to
                                                 Comments Due: 5 p.m. ET 12/24/18.                    effective 11/1/2018.                                  be effective 12/3/2019.
                                                 Docket Numbers: ER17–1561–002.                          Filed Date: 12/3/18.                                  Filed Date: 12/3/18.
                                                 Applicants: New York Independent                        Accession Number: 20181203–5243.                      Accession Number: 20181203–5299.
                                              System Operator, Inc.                                      Comments Due: 5 p.m. ET 12/24/18.                     Comments Due: 5 p.m. ET 12/24/18.
                                                 Description: Compliance filing: Order                   Docket Numbers: ER19–314–001.                         Docket Numbers: ER19–471–000.
                                              No. 831 offer cap compliance to set                        Applicants: Bridgewater Power                         Applicants: Wisconsin Power and
                                              effective date to be effective 12/18/2018.              Company, L.P.                                         Light Company.
                                                 Filed Date: 12/4/18.                                    Description: Tariff Amendment:                        Description: § 205(d) Rate Filing:
                                                 Accession Number: 20181204–5038.                     Supplement to Bridgewater Power                       Amendment to WPL Wholesale Formula
                                                 Comments Due: 5 p.m. ET 12/26/18.                    Company L.P. MBR Tariff Application                   Rate Changes to be effective 12/31/2018.
                                                 Docket Numbers: ER18–463–002.                        to be effective 1/8/2019.                                Filed Date: 12/4/18.
                                                 Applicants: Midcontinent                                Filed Date: 12/3/18.                                  Accession Number: 20181204–5000.
                                              Independent System Operator, Inc.,                         Accession Number: 20181203–5114.                      Comments Due: 5 p.m. ET 12/26/18.
amozie on DSK3GDR082PROD with NOTICES1




                                              Ameren Transmission Company of                             Comments Due: 5 p.m. ET 12/24/18.                     Docket Numbers: ER19–472–000.
                                              Illinois.                                                  Docket Numbers: ER19–381–001.                         Applicants: Interstate Power and
                                                 Description: Compliance filing: 2018–                   Applicants: Power Holding LLC.                     Light Company.
                                              12–03_ATXI Revisions to Attachment O                       Description: Tariff Amendment:                        Description: § 205(d) Rate Filing:
                                              & MM for Mark Twain Incentive to be                     Amendment to Application of Market                    Amendment to IPL Wholesale Formula
                                              effective 2/14/2018.                                    Based Rate to be effective 11/21/2018.                Rate Application to be effective 12/31/
                                                 Filed Date: 12/3/18.                                    Filed Date: 12/4/18.                               2018.


                                         VerDate Sep<11>2014   18:39 Dec 11, 2018   Jkt 247001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\12DEN1.SGM   12DEN1



Document Created: 2018-12-12 01:39:46
Document Modified: 2018-12-12 01:39:46
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 63851 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR