DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 37 (February 23, 2018)

Page Range8072-8073
FR Document2018-03715

Federal Register, Volume 83 Issue 37 (Friday, February 23, 2018)
[Federal Register Volume 83, Number 37 (Friday, February 23, 2018)]
[Notices]
[Pages 8072-8073]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-03715]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-463-000]


Notice of Schedule for Environmental Review of the Okeechobee 
Lateral Pipeline Project Florida Southeast Connection, LLC

    On August 22, 2017, Florida Southeast Connection, LLC (FSC) filed 
an application to construct and operate certain natural gas pipeline 
facilities. The Federal Energy Regulatory Commission (Commission) is 
considering this application in Docket No. CP17-463-000 for a 
Certificate of Public Convenience and Necessity pursuant to Section 
7(c) of the Natural Gas Act (NGA). The proposed project is known as the 
Okeechobee Lateral Pipeline Project (Project), and would connect FSC's 
mainline system with the Florida Power & Light Company's (FPL) 
Okeechobee Clean Energy Center (OCEC). The Project would be capable of 
transporting up to 400 million cubic feet per day of natural gas to the 
OCEC.
    This Notice of Schedule for Environmental Review indicates the 
anticipated date for the Commission staff's issuance of an 
environmental assessment (EA) for this proposal. The issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's EA.

Schedule for Environmental Review

Issuance of EA--March 16, 2018
90-day Federal Authorization Decision Deadline--June 14, 2018

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    FSC requests authorization to construct and operate approximately 
5.2 miles of 20-inch-diameter natural gas transmission pipeline and 
associated facilities including an inspection tool launcher and a 
receiver and a meter station in Okeechobee County, Florida. As 
described above, this lateral pipeline would connect FSC's mainline 
system with FPL's OCEC. FSC anticipates construction would require four 
to five months.

Background

    On October 24, 2017, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Okeechobee Lateral 
Pipeline Project and Request for Comments on Environmental Issues 
(NOI). The NOI was sent to affected landowners; federal, state, and 
local government agencies; elected officials; environmental and public 
interest groups; Native American tribes; other interested parties; and 
local libraries and newspapers. In response to the NOI, the Commission 
received comments from the Treasure Coast Democratic Environmental 
Caucus, Seminole Tribe of Florida, Sierra Club, and the Economic 
Council of Okeechobee County. The primary issues raised by the 
commentors concern air quality, cumulative impacts, potential future 
projects and connected actions, cultural resources, purpose and need, 
alternatives, and greenhouse gas and upstream emissions.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs

[[Page 8073]]

at (866) 208-FERC or on the FERC website (www.ferc.gov). Using the 
eLibrary link, select General Search from the eLibrary menu, enter the 
selected date range and Docket Number excluding the last three digits 
(i.e., CP17-463), and follow the instructions. For assistance with 
access to eLibrary, the helpline can be reached at (866) 208-3676, TTY 
(202) 502-8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on 
the FERC website also provides access to the texts of formal documents 
issued by the Commission, such as orders, notices, and rule makings.

    Dated: February 16, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-03715 Filed 2-22-18; 8:45 am]
 BILLING CODE 6717-01-P



                                               8072                          Federal Register / Vol. 83, No. 37 / Friday, February 23, 2018 / Notices

                                               A. Curtiss, Deputy General Counsel for                  filed by other parties or issued by the               date of issuance of the Commission
                                               National Fuel, 6363 Main Street,                        Commission (except for the mailing of                 staff’s EA.
                                               Williamsville, New York 14221, by                       environmental documents issued by the
                                                                                                                                                             Schedule for Environmental Review
                                               phone (716) 857–7075, by fax (716) 857–                 Commission) and will not have the right
                                               7206, or by email at curtissa@                          to seek court review of the                           Issuance of EA—March 16, 2018
                                               natfuel.com.                                            Commission’s final order.                             90-day Federal Authorization Decision
                                                  Any person may, within 60 days after                    The Commission strongly encourages                    Deadline—June 14, 2018
                                               the issuance of the instant notice by the               electronic filings of comments, protests,                If a schedule change becomes
                                               Commission, file pursuant to Rule 214                   and interventions via the internet in lieu            necessary, additional notice will be
                                               of the Commission’s Procedural Rules                    of paper. See 18 CFR 385.2001(a)(1)(iii)              provided so that the relevant agencies
                                               (18 CFR 385.214) a motion to intervene                  and the instructions on the                           are kept informed of the Project’s
                                               or notice of intervention. Any person                   Commission’s website (www.ferc.gov)                   progress.
                                               filing to intervene or the Commission’s                 under the e-Filing link. Persons unable               Project Description
                                               staff may, pursuant to section 157.205 of               to file electronically should submit
                                               the Commission’s Regulations under the                  original and 5 copies of the protest or                  FSC requests authorization to
                                               NGA (18 CFR 157.205) file a protest to                  intervention to the Federal Energy                    construct and operate approximately 5.2
                                               the request. If no protest is filed within              Regulatory Commission, 888 First Street               miles of 20-inch-diameter natural gas
                                               the time allowed therefor, the proposed                 NE, Washington, DC 20426.                             transmission pipeline and associated
                                               activity shall be deemed to be                                                                                facilities including an inspection tool
                                               authorized effective the day after the                    Dated: February 16, 2018.                           launcher and a receiver and a meter
                                               time allowed for protest. If a protest is               Nathaniel J. Davis, Sr.,                              station in Okeechobee County, Florida.
                                               filed and not withdrawn within 30 days                  Deputy Secretary.                                     As described above, this lateral pipeline
                                               after the time allowed for filing a                     [FR Doc. 2018–03717 Filed 2–22–18; 8:45 am]           would connect FSC’s mainline system
                                               protest, the instant request shall be                   BILLING CODE 6717–01–P                                with FPL’s OCEC. FSC anticipates
                                               treated as an application for                                                                                 construction would require four to five
                                               authorization pursuant to section 7 of                                                                        months.
                                               the NGA.                                                DEPARTMENT OF ENERGY
                                                  Pursuant to section 157.9 of the                                                                           Background
                                               Commission’s rules, 18 CFR 157.9,                       Federal Energy Regulatory                                On October 24, 2017, the Commission
                                               within 90 days of this Notice the                       Commission                                            issued a Notice of Intent to Prepare an
                                               Commission staff will either: Complete                                                                        Environmental Assessment for the
                                               its environmental assessment (EA) and                   [Docket No. CP17–463–000]                             Proposed Okeechobee Lateral Pipeline
                                               place it into the Commission’s public                                                                         Project and Request for Comments on
                                               record (eLibrary) for this proceeding; or               Notice of Schedule for Environmental                  Environmental Issues (NOI). The NOI
                                               issue a Notice of Schedule for                          Review of the Okeechobee Lateral                      was sent to affected landowners; federal,
                                               Environmental Review. If a Notice of                    Pipeline Project Florida Southeast                    state, and local government agencies;
                                               Schedule for Environmental Review is                    Connection, LLC                                       elected officials; environmental and
                                               issued, it will indicate, among other                                                                         public interest groups; Native American
                                               milestones, the anticipated date for the                   On August 22, 2017, Florida                        tribes; other interested parties; and local
                                               Commission staff’s issuance of the final                Southeast Connection, LLC (FSC) filed                 libraries and newspapers. In response to
                                               environmental impact statement (FEIS)                   an application to construct and operate               the NOI, the Commission received
                                               or EA for this proposal. The filing of the              certain natural gas pipeline facilities.              comments from the Treasure Coast
                                               EA in the Commission’s public record                    The Federal Energy Regulatory                         Democratic Environmental Caucus,
                                               for this proceeding or the issuance of a                Commission (Commission) is                            Seminole Tribe of Florida, Sierra Club,
                                               Notice of Schedule for Environmental                    considering this application in Docket                and the Economic Council of
                                               Review will serve to notify federal and                 No. CP17–463–000 for a Certificate of                 Okeechobee County. The primary issues
                                               state agencies of the timing for the                    Public Convenience and Necessity                      raised by the commentors concern air
                                               completion of all necessary reviews, and                pursuant to Section 7(c) of the Natural               quality, cumulative impacts, potential
                                               the subsequent need to complete all                     Gas Act (NGA). The proposed project is                future projects and connected actions,
                                               federal authorizations within 90 days of                known as the Okeechobee Lateral                       cultural resources, purpose and need,
                                               the date of issuance of the Commission                  Pipeline Project (Project), and would                 alternatives, and greenhouse gas and
                                               staff’s FEIS or EA.                                     connect FSC’s mainline system with the                upstream emissions.
                                                  Persons who wish to comment only                     Florida Power & Light Company’s (FPL)
                                               on the environmental review of this                     Okeechobee Clean Energy Center                        Additional Information
                                               project should submit an original and                   (OCEC). The Project would be capable of                  In order to receive notification of the
                                               two copies of their comments to the                     transporting up to 400 million cubic feet             issuance of the EA and to keep track of
                                               Secretary of the Commission.                            per day of natural gas to the OCEC.                   all formal issuances and submittals in
                                               Environmental commenters will be                           This Notice of Schedule for                        specific dockets, the Commission offers
                                               placed on the Commission’s                              Environmental Review indicates the                    a free service called eSubscription. This
                                               environmental mailing list, will receive                anticipated date for the Commission                   can reduce the amount of time you
                                               copies of the environmental documents,                  staff’s issuance of an environmental                  spend researching proceedings by
                                               and will be notified of meetings                        assessment (EA) for this proposal. The                automatically providing you with
daltland on DSKBBV9HB2PROD with NOTICES




                                               associated with the Commission’s                        issuance of a Notice of Schedule for                  notification of these filings, document
                                               environmental review process.                           Environmental Review will serve to                    summaries, and direct links to the
                                               Environmental commenters will not be                    notify federal and state agencies of the              documents. Go to www.ferc.gov/docs-
                                               required to serve copies of filed                       timing for the completion of all                      filing/esubscription.asp.
                                               documents on all other parties.                         necessary reviews, and the subsequent                    Additional information about the
                                               However, the non-party commentary                       need to complete all federal                          Project is available from the
                                               will not receive copies of all documents                authorizations within 90 days of the                  Commission’s Office of External Affairs


                                          VerDate Sep<11>2014   18:52 Feb 22, 2018   Jkt 244001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\23FEN1.SGM   23FEN1


                                                                             Federal Register / Vol. 83, No. 37 / Friday, February 23, 2018 / Notices                                                 8073

                                               at (866) 208–FERC or on the FERC                        the public regarding EPA’s preliminary                   The proposed federal action under
                                               website (www.ferc.gov). Using the                       determination.                                        consideration in this EA is approving or
                                               eLibrary link, select General Search                    DATES: Comments must be received by                   denying IFA’s application by either
                                               from the eLibrary menu, enter the                       March 25, 2018.                                       issuing or not issuing a WIFIA loan. The
                                               selected date range and Docket Number                                                                         IFA provides loans for the design,
                                                                                                       ADDRESSES: Submit your comments,
                                               excluding the last three digits (i.e.,                                                                        construction, operation, and
                                               CP17–463), and follow the instructions.                 identified by Docket ID No. EPA–HQ–                   maintenance of eligible water and
                                               For assistance with access to eLibrary,                 OW–2018–0079 to the Federal                           wastewater infrastructure projects as
                                               the helpline can be reached at (866)                    eRulemaking Portal: Go to http://                     described in section 603(c) of the
                                               208–3676, TTY (202) 502–8659, or at                     www.regulations.gov. Please follow the                Federal Water Pollution Control Act (33
                                               FERCOnlineSupport@ferc.gov. The                         online instructions for submitting                    U.S.C. 1383(c)) and section 1452(a)(2) of
                                               eLibrary link on the FERC website also                  comments. Once submitted, comments                    the Safe Drinking Water Act (42 U.S.C.
                                               provides access to the texts of formal                  cannot be edited or withdrawn. The                    300j–12(a)(2)). IFA applied for a WIFIA
                                               documents issued by the Commission,                     EPA may publish public comments                       loan to help fund the 2017 3rd Quarter
                                               such as orders, notices, and rule                       received to its public docket. Do not                 Project Priority Lists for the Drinking
                                               makings.                                                submit electronically any information                 Water SRF (DWSRF) and Clean Water
                                                                                                       you consider to be Confidential                       SRF (CWSRF) Loan Programs for
                                                 Dated: February 16, 2018.                             Business Information (CBI) or other
                                               Nathaniel J. Davis, Sr.,
                                                                                                                                                             projects applying for financial
                                                                                                       information whose disclosure is                       assistance in State Fiscal Year 2017. The
                                               Deputy Secretary.                                       restricted by statute. Multimedia                     proposed action involves the planning,
                                               [FR Doc. 2018–03715 Filed 2–22–18; 8:45 am]             submissions (audio, video, etc.) must be              design, construction, operation, and
                                               BILLING CODE 6717–01–P                                  accompanied by a written comment.                     maintenance for a wide range of water
                                                                                                       The written comment is considered the                 and wastewater infrastructure projects,
                                                                                                       official comment and should include                   which are eligible for WIFIA credit
                                                                                                       discussion of all points you wish to                  assistance.
                                               ENVIRONMENTAL PROTECTION                                make. The EPA will generally not
                                               AGENCY                                                                                                           The environmental review process,
                                                                                                       consider comments or comment
                                                                                                                                                             which is documented by the EA,
                                                                                                       contents located outside of the primary
                                               [EPA–HQ–OW–2018–0079] [ER–FRL–9037–                                                                           indicates that no potential significant
                                               7]                                                      submission (i.e., on the web, cloud, or
                                                                                                                                                             adverse environmental impacts are
                                                                                                       other file sharing system). For
                                                                                                                                                             anticipated from the proposed action.
                                               Availability of an Environmental                        additional submission methods, the full
                                                                                                                                                             The EA, which analyzed the potential
                                               Assessment (EA) and Finding of No                       EPA public comment policy,
                                                                                                                                                             environmental impacts of issuing of
                                               Significant Impact (FONSI)                              information about CBI or multimedia
                                                                                                                                                             credit assistance to IFA for SRF Loans
                                                                                                       submissions, and general guidance on
                                               AGENCY:  Environmental Protection                                                                             under the WIFIA program, considered
                                                                                                       making effective comments, please visit
                                               Agency (EPA).                                                                                                 the potential environmental impacts
                                                                                                       https://www.epa.gov/dockets/
                                               ACTION: Environmental Assessment
                                                                                                                                                             from water and waste water
                                                                                                       commenting-epa-dockets.
                                               (EA)/Finding of No Significant Impact                                                                         infrastructure projects.
                                                                                                       FOR FURTHER INFORMATION CONTACT:                         Based on the environmental impact
                                               (FONSI).                                                Danusha Chandy, Water Infrastructure                  analysis in the EA, EPA has determined
                                               SUMMARY:    Pursuant to the National                    Division, Office of Wastewater                        that no significant environmental
                                               Environmental Policy Act (NEPA), the                    Management, WIFIA Program, Mail                       impacts are anticipated from the
                                               Council on Environmental Quality’s                      Code: 4201T, Environmental Protection                 issuance of credit assistance to IFA for
                                               NEPA regulations, and EPA’s                             Agency, 1200 Pennsylvania Avenue                      SRF Loans and the proposed action does
                                               regulations for implementing NEPA,                      NW, Washington, DC 20460; telephone                   not constitute a major Federal action
                                               EPA has prepared an Environmental                       number: 202–564–2165; email address                   significantly affecting the quality of the
                                               Assessment (EA) to analyze the                          chandy.danusha@epa.gov.                               human environment, making the
                                               potential environmental impacts related                 SUPPLEMENTARY INFORMATION: EPA is                     preparation of an Environmental Impact
                                               to the issuance of credit assistance to                 seeking public comment regarding its                  Statement (EIS) unnecessary. Therefore,
                                               the Indiana Finance Authority (IFA) for                 preliminary Finding of No Significant                 EPA is issuing a preliminary FONSI.
                                               State Revolving Fund (SRF) Loans                        Impact (FONSI) to document its                           Dated: February 20, 2018.
                                               under the Water Infrastructure Finance                  determination that no significant                     Kelly Knight,
                                               and Innovation Act (WIFIA) program.                     environmental impacts are anticipated
                                                                                                                                                             Director, NEPA Compliance Division, Office
                                               The EA evaluates the potential                          from the issuance of credit assistance to             of Federal Activities.
                                               environmental impacts of water                          IFA for SRF Loans under the WIFIA
                                                                                                                                                             [FR Doc. 2018–03730 Filed 2–22–18; 8:45 am]
                                               infrastructure projects funded under the                program. EPA invites the public to
                                                                                                                                                             BILLING CODE 6560–50–P
                                               WIFIA credit assistance program in                      submit comments through
                                               compliance with NEPA and the required                   Regulations.gov during the 30-day
                                               environmental cross-cutters and other                   comment period following the                          ENVIRONMENTAL PROTECTION
                                               federal, state, and local environmental                 publication of this notice in the Federal             AGENCY
                                               reviews. Based on the environmental                     Register.
                                               impact analysis in the EA, EPA has                        Congress enacted the WIFIA as part of
daltland on DSKBBV9HB2PROD with NOTICES




                                                                                                                                                             [ER–FRL–9037–8]
                                               made a preliminary determination that                   the Water Resources Reform and
                                               no significant environmental impacts                    Development Act of 2014, as amended                   Environmental Impact Statements;
                                               are anticipated from the issuance of the                by sec. 1445 of Public Law 114–94 [1]                 Notice of Availability
                                               credit assistance to IFA. This notice                   and codified at 33 U.S.C. 3901–3914.
                                               initiates the 30-day review period and                  WIFIA establishes a new federal credit                  Responsible Agency: Office of Federal
                                               invites comments from Federal, State,                   program for water infrastructure projects             Activities, General Information 202–
                                               and local agencies, Indian tribes, and                  to be administered by EPA.                            564–7156 or http://www2.epa.gov/nepa.


                                          VerDate Sep<11>2014   18:52 Feb 22, 2018   Jkt 244001   PO 00000   Frm 00029   Fmt 4703   Sfmt 4703   E:\FR\FM\23FEN1.SGM   23FEN1



Document Created: 2018-02-23 01:32:25
Document Modified: 2018-02-23 01:32:25
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106: