Document

East Bay Municipal Utility District Supplemental Water Supply Project

Pursuant to the National Environmental Policy Act (NEPA) and the California Environmental Quality Act, the Bureau of Reclamation (Reclamation) and the East Bay Municipal Utility...

Department of the Interior
Bureau of Reclamation
  1. [FES00-54]

AGENCY:

Bureau of Reclamation, Interior.

ACTION:

Notice of availability of Final Environmental Impact Report/Final Environmental Impact Statement (FEIR/FEIS).

SUMMARY:

Pursuant to the National Environmental Policy Act (NEPA) and the California Environmental Quality Act, the Bureau of Reclamation (Reclamation) and the East Bay Municipal Utility District (EBMUD) have prepared a joint FEIR/FEIS for the EBMUD Supplemental Water Supply Project. Reclamation and EBMUD prepared a draft environmental impact report/draft environmental impact statement (DEIR/DEIS) for the proposed project in November 1997, and a draft recirculated environmental impact report/supplemental environmental impact statement (REIR/SEIS) in October 2000. The FEIR/FEIS incorporates the DEIR/DEIS and REIR/SEIS, by reference, and includes all comments received on the DEIR/DEIS and the REIR/SEIS, and responses to those comments.

DATES:

No decision will be made on the proposed action until at least 30 days after release of the FEIR/FEIS. After the 30-day waiting period, Reclamation will be preparing a Record of Decision (ROD) and EBMUD will be preparing a Notice of Determination, both of which will state the action that will be implemented and will discuss all factors leading to the respective decision of each agency. When an alternative is selected and the ROD is signed, Reclamation and EBMUD will resume negotiations on the amendatory contract to conform the contract terms to accurately reflect the selected alternative.

ADDRESSES:

Copies of the FEIR/FEIS may be requested from Ms. Ann Reis, Water Supply Improvements Division, EBMUD, P.O. Box 24055, MS #305, Oakland CA 94623, (510) 287-1197.

See “Supplementary Information” section for locations where copies of the FEIR/FEIS are available for inspection.

FOR FURTHER INFORMATION CONTACT:

Mr. Kurt Ladensack, Water Supply Improvements Division, EBMUD, P.O. Box 24055, MS #305, Oakland CA 94623, (510) 287-1197; or Mr. Robert Schroeder, Environmental Specialist, Reclamation, Central California Area Office, 7794 Folsom Dam Road, Folsom CA 95630, (916) 988-1707.

SUPPLEMENTARY INFORMATION:

The federal action supported by this FEIS/FEIR is execution of an amendment to the 1970 contract. The amendatory contract will provide for a selection of one of the following alternative diversion sites under the identified and other appropriate conditions:

The amendatory contract will prohibit deliveries of water diverted at Nimbus Dam as currently provided in Article 9(a) of the existing 1970 contract. However, if permitting and necessary agreements for another point of diversion are not completed by a certain date, EBMUD will have the right to deliveries as provided in Article 9(a) of the existing 1970 contract.

The amendatory contract will provide that in order for diversions to occur at any of the diversion sites identified above, all relevant state and federal laws and regulations must be complied with, and approval of the Contracting Officer is required. The Contracting Officer will initiate and complete consultation under Section 7 of the Endangered Species Act, and will comply with NEPA, as applicable, prior to approving any such diversions.

Included in the FEIR/FEIS, for clarity of reference only, is Appendix A. It is a draft amendatory contract that Reclamation circulated for public comment in December 1998. The REIR/SEIS and FEIR/FEIS refers to the provisions of the December 1998, draft amendatory contract. Although the entire 1998 draft amendatory contract is included in this FEIR/FEIS, Reclamation and EBMUD expect to replace this amendatory contract with a new draft amendatory contract that conforms to the provisions contained within the ROD.

Copies of the FEIR/FEIS are available for inspection at the following locations:

Dated: December 5, 2000.

Kirk C. Rodgers,

Deputy Regional Director.

[FR Doc. 00-31606 Filed 12-11-00; 8:45 am]

BILLING CODE 4310-MN-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

65 FR 77671

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“East Bay Municipal Utility District Supplemental Water Supply Project,” thefederalregister.org (December 12, 2000), https://thefederalregister.org/documents/00-31606/east-bay-municipal-utility-district-supplemental-water-supply-project.