The U.S. Nuclear Regulatory Commission (NRC) is soliciting public comment on draft NUREG-0800, "Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power ...

Nuclear Regulatory Commission
  1. [NRC-2014-0204]

AGENCY:

Nuclear Regulatory Commission.

ACTION:

Standard review plan—draft section revision; request for comment.

SUMMARY:

The U.S. Nuclear Regulatory Commission (NRC) is soliciting public comment on draft NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition,” Section 17.5, “Quality Assurance Program Description—Design Certification, Early Site Permit and New License Applicants.”

DATES:

Comments must be filed no later than November 24, 2014. Comments received after this date will be considered if it is practical to do so, but the Commission is able to ensure consideration only for comments received on or before this date.

ADDRESSES:

You may submit comments by any of the following methods (unless this document describes a different method for submitting comments on a specific subject):

  • Federal Rulemaking Web site: Go towww.regulations.gov and search for Docket ID NRC-2014-0204. Address questions about NRC dockets to Carol Gallagher; telephone: 301-287-3422; email: . For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
  • Mail comments to: Cindy Bladey, Office of Administration, Mail Stop: 3WFN-06-44M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.

For additional direction on accessing information and submitting comments, see “Obtaining Information and Submitting Comments” in the SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT:

Jonathan DeGange, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-6992 or email to: .

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments

A. Obtaining Information

Please refer to Docket ID NRC-2014-0204 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document by any of the following methods:

B. Submitting Comments

Please include Docket ID NRC-2014-0204 in the subject line of your comment submission, in order to ensure that the NRC is able to make your comment submission available to the public in this docket.

The NRC cautions you not to include identifying or contact information that you do not want to be publicly disclosed in you comment submission. The NRC will post all comment submissions at www.regulations.gov as well as enter the comment submissions into ADAMS. ( printed page 57144) The NRC does not routinely edit comment submissions to remove identifying or contact information.

If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment submissions into ADAMS.

II. Further Information

The NRC is seeking public comment on the proposed revision to SRP Section 17.5. This section has been developed to assist the NRC's staff review Quality Assurance (QA) program descriptions under part 50 of Title 10 of the Code of Federal Regulation s (10 CFR). The revisions to this SRP section reflect no changes in staff position, nor are new SRP acceptance criteria introduced. The changes simplify and reflect plain language throughout in accordance with the NRC's Plain Writing Action Plan. Additionally, the staff has aligned SRP Section 17.5 with Regulatory Guide (RG) 1.28, “Quality Assurance Program Criteria (Design and Construction),” Revision 4 and RG 1.33, “Quality Assurance Program Requirements (Operation),” Revision 2. The changes also reflect alignment with the latest edition of NQA-1-2008/2009a which the staff found acceptable for meeting the requirement of Appendix B to 10 CFR part 50.

Following the NRC staff's evaluation of public comments, the NRC intends to finalize SRP Section 17.5, Revision 1 in ADAMS and post it on the NRC's public Web site at www.nrc.gov/​reading-rm/​doc-collections/​nuregs/​staff/​sr0800/​. The SRP is guidance for the NRC staff. The SRP is not a substitute for the NRC's regulations, and compliance with the SRP is not required.

III. Backfitting and Issue Finality

Issuance of this draft SRP, if finalized, would not constitute backfitting as defined in 10 CFR 50.109 (the Backfit Rule) or otherwise be inconsistent with the issue finality provisions in 10 CFR part 52. The NRC's position is based upon the following considerations:

1. The draft SRP positions, if finalized, would not constitute backfitting, inasmuch as the SRP is internal guidance to the NRC staff.

The SRP provides internal guidance to the NRC staff on how to review an application for NRC regulatory approval in the form of licensing. Changes in internal staff guidance are not matters for which either nuclear power plant applicants or licensees are protected under either the Backfit Rule or the issue finality provisions of 10 CFR part 52.

2. The NRC staff has no intention to impose the SRP positions on existing licensees either now or in the future.

The NRC staff does not intend to impose or apply the positions described in the draft SRP to existing licenses and regulatory approvals. Hence, the issuance of a final SRP—even if considered guidance within the purview of the issue finality provisions in 10 CFR part 52—would not need to be evaluated as if it were a backfit or as being inconsistent with issue finality provisions. If, in the future, the NRC staff seeks to impose a position in the SRP on holders of already issued licenses in a manner that does not provide issue finality as described in the applicable issue finality provision, then the staff must make the showing as set forth in the Backfit Rule or address the criteria for avoiding issue finality as described in the applicable issue finality provision.

3. Backfitting and issue finality do not—with limited exceptions not applicable here—protect current or future applicants.

Applicants and potential applicants are not, with certain exceptions, protected by either the Backfit Rule or any issue finality provisions under 10 CFR part 52. Neither the Backfit Rule nor the issue finality provisions under 10 CFR part 52—with certain exclusions—were intended to apply to every NRC action that substantially changes the expectations of current and future applicants. The exceptions to the general principle are applicable whenever an applicant references a 10 CFR part 52 license (e.g., an early site permit) and/or NRC regulatory approval (e.g., a design certification rule) with specified issue finality provisions.

The NRC staff does not, at this time, intend to impose the positions represented in the draft SRP in a manner that is inconsistent with any issue finality provisions. If, in the future, the staff seeks to impose a position in the draft SRP in a manner that does not provide issue finality as described in the applicable issue finality provision, then the staff must address the criteria for avoiding issue finality as described in the applicable issue finality provision.

Dated at Rockville, Maryland, this 12th day of September, 2014.

For the Nuclear Regulatory Commission.

Joseph Colaccino,

Chief, New Reactor Rulemaking and Guidance Branch, Division of Advanced Reactors and Rulemaking, Office of New Reactors.

[FR Doc. 2014-22728 Filed 9-23-14; 8:45 am]

BILLING CODE 7590-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

79 FR 57143

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Quality Assurance Program Description-Design Certification, Early Site Permit and New License Applicants,” thefederalregister.org (September 24, 2014), https://thefederalregister.org/documents/2014-22728/quality-assurance-program-description-design-certification-early-site-permit-and-new-license-applicants.