On May 12, 2016, the Tennessee Valley Authority (TVA) submitted an application to the U.S. Nuclear Regulatory Commission (NRC) for an early site permit (ESP) for the Clinch River Nuclear (CRN) Site located in Oak Ridge, Tennessee. A notice of receipt and availability of this application was published in the Federal Register on June 23, 2016. The TVA also provided supplemental information in support of the application to the NRC. Notice of the NRC's docketing of the application was published in the Federal Register on January 12, 2017. A hearing will be held, at a time and place to be set in the future by the NRC or designated by the Atomic Safety and Licensing Board (Board). The hearing will consider the application dated May 12, 2016.
Document
Tennessee Valley Authority; Clinch River Nuclear Site Early Site Permit Application and Associated Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information and Safeguards Information
On May 12, 2016, the Tennessee Valley Authority (TVA) submitted an application to the U.S. Nuclear Regulatory Commission (NRC) for an early site permit (ESP) for the Clinch Rive...
Legal Citation
Federal Register Citation
Use this for formal legal and research references to the published document.
82 FR 16436
Web Citation
Suggested Web Citation
Use this when citing the archival web version of the document.
“Tennessee Valley Authority; Clinch River Nuclear Site Early Site Permit Application and Associated Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information and Safeguards Information,” thefederalregister.org (April 4, 2017), https://thefederalregister.org/documents/2017-06625/tennessee-valley-authority-clinch-river-nuclear-site-early-site-permit-application-and-associated-order-imposing-procedu.