Document

Southern Nuclear Operating Company, Inc. Vogtle Electric Generating Plant, Units 3 and 4 Inspections, Tests, Analyses, and Acceptance Criteria

The U.S. Nuclear Regulatory Commission (NRC) staff has determined that the inspections, tests, and analyses have been successfully completed, and that the specified acceptance c...

The U.S. Nuclear Regulatory Commission (NRC) staff has determined that the inspections, tests, and analyses have been successfully completed, and that the specified acceptance criteria are met for multiple inspections, tests, analyses, and acceptance criteria (ITAAC) for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4.

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

82 FR 19758

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Southern Nuclear Operating Company, Inc. Vogtle Electric Generating Plant, Units 3 and 4 Inspections, Tests, Analyses, and Acceptance Criteria,” thefederalregister.org (April 28, 2017), https://thefederalregister.org/documents/2017-08616/southern-nuclear-operating-company-inc-vogtle-electric-generating-plant-units-3-and-4-inspections-tests-analyses-and-acc.