- [Docket No. CP17-443-000]
Take notice that on July 20, 2020, National Fuel Gas Supply Corporation (National Fuel) requested that the Federal Energy Regulatory Commission (Commission) grant an extension of time, until July 24, 2021, to complete the Wharton WH23 Storage Well Abandonment Project (Project), as authorized after the 60-day deadline of National Fuel's prior notice issued by the Commission on May 25, 2017.
National Fuel was initially required to abandon the facilities by July 24, 2018. On July 27, 2018, the Office of Energy Projects, by delegated order, extended the deadline through July 24, 2019. On July 12, 2019, the Office of Energy Projects, by delegated order, extended the deadline through July 24, 2020. National Fuel now requests a one-year extension of this deadline, through July 24, 2021. National Fuel states that it requires more time to continue and complete pressure evaluations of Well WH23, and to undertake the plugging, and final restoration of the Well WH23 site.
This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on National Fuel's request for an extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10).[1]
As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for Natural Gas Act facilities when such requests are contested before order issuance. For those extension requests that are contested,[2] the Commission will aim to issue an order acting on the request within 45 days.[3] The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.[4] The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission's environmental analysis for the certificate complied with the National Environmental Policy Act.[5] At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.[6] The OEP Director, or his or her designee, will act on all of those extension requests that are uncontested.
In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( https://www.ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to Commission's Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel ( printed page 55278) Coronavirus Disease (COVID-19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY, (202) 502-8659.
The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the “eFile” link at https://www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern Time on September 14, 2020.