Department of Energy
Federal Energy Regulatory Commission
- [Project No. 5307-004]
1. On February 1, 2021, Green Mountain Power Corporation, exemptee for the Woodsville Hydroelectric Project No. 5307, filed a letter notifying the Commission that the project was transferred from Green Mountain Power Corporation to Hydro Power, LLC. The exemption from licensing was originally issued on February 5, 1982.[1] The project is located on the Ammonoosuc River, Grafton County, New Hampshire. The transfer of an exemption does not require Commission approval.
2. Hydro Power, LLC is now the exemptee of the Woodsville Hydroelectric Project No. 5307. All correspondence must be forwarded to: Mr. Brandon L. Boudreau, 87 Factory Street, St. Johnsbury, VT 05819, Email: Brandon@FairBanksMill.com.
Dated: February 24, 2021.
Kimberly D. Bose,
Secretary.