Document
Southern Nuclear Operating Company, Inc; Vogtle Electric Generating Plant, Units 3 and 4; Inspections, Tests, Analyses, and Acceptance Criteria
The U.S. Nuclear Regulatory Commission (NRC) staff has determined that specified inspections, tests, and analyses have been successfully completed, and that specified acceptance...
SUPPLEMENTARY INFORMATION:
I. Licensee Notification of Completion of ITAAC
Southern Nuclear Operating Company, Inc. (SNC) (hereafter called the licensee) has submitted ITAAC closure notifications (ICNs) under § 52.99(c)(1) of title 10 of the
Code of Federal Regulations
(10 CFR), informing the NRC that the licensee has successfully performed the required inspections, tests, and analyses, and that the acceptance criteria are met for:
VEGP Unit 3 ITAAC
2.1.02.01 (12), 2.1.02.09b.ii (43), 2.1.02.12a.i (53), 2.1.03.13 (88), 2.2.01.07.i (107), 2.2.01.11a.i (114), 2.2.02.05c (130), 2.2.02.07a.iii (137), 2.2.03.08c.i.01 (177), 2.2.03.12a.iv (216), 2.2.04.01 (219), 2.2.05.01 (252), 2.3.01.03.ii (281), 2.3.02.08a.iii (303), 2.3.02.11a.i (309), 2.3.04.02.i (327), 2.3.04.02.ii (328), 2.3.04.04.i (330), 2.3.05.03b.iii (348), 2.3.06.12a.i (384), 2.3.08.02.i (415), 2.3.08.02.iii (417), 2.3.14.04 (480), 2.4.06.02 (504), 2.5.01.03b (512), 2.6.03.04b (602), 2.7.01.02a (678), 2.7.01.05.i (684), 3.3.00.02b (770), 3.3.00.02f (774), 3.3.00.02h (776), 3.3.00.07e (812), 3.3.00.13 (819), E.3.9.03.00.01 (847), E.3.9.05.01.08 (856), E.3.9.07.01.02 (866), E.3.9.08.01.01 (870), and E.3.9.08.01.02 (871).
VEGP Unit 4 ITAAC
2.3.03.03a (320) and 2.6.03.04b (602).
The ITAAC for VEGP Unit 3 are in Appendix C of the VEGP Unit 3 combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP Unit 4 are in Appendix C of VEGP Unit 4 combined license (ADAMS Accession No. ML14100A135).
II. Licensee ITAAC Post-Closure Notifications (IPCNs)
SNC has submitted an IPCN under 10 CFR 52.99(c)(2), informing the NRC of new information that materially alters the basis for determining either that inspections, tests, or analyses was performed as required, or that acceptance criteria are met for:
VEGP Unit 4 ITAAC
2.3.05.03a.ii (344).
III. NRC Staff Determination of Completion of ITAAC
The NRC staff has determined that the specified inspections, tests, and analyses have been successfully completed, and that the specified acceptance criteria are met. The documentation of the NRC staff's determination is in the ITAAC Closure Verification Evaluation Form (VEF) for each ITAAC. The VEF is a form that represents the NRC staff's structured process for reviewing ICNs and IPCNs.
Each ICN presents a narrative description of how the ITAAC was completed. The NRC's ICN review process involves a determination on whether, among other things: (1) Each ICN provides sufficient information, including a summary of the methodology used to perform the ITAAC, to demonstrate that the inspections, tests, and analyses have been successfully completed; (2) each ICN provides sufficient information to demonstrate that the acceptance criteria of the ITAAC are met; and (3) any NRC inspections for the ITAAC have been completed and any ITAAC findings associated with that ITAAC have been closed. The NRC's review process for IPCNs is similar to that for ICNs but focuses on how the licensee addressed the new, material information giving rise to the IPCN.
The NRC staff's determination of the successful completion of these ITAAC is based on information available at this time and is subject to the licensee's ability to maintain the condition that the acceptance criteria are met. If the NRC staff receives new information that suggests the NRC staff's determination on any of these ITAAC is incorrect, then the NRC staff will determine whether to reopen that ITAAC (including withdrawing the NRC staff's determination on that ITAAC). The NRC staff's determination will be used to support a subsequent finding, pursuant to 10 CFR 52.103(g), at the end of construction that all acceptance criteria in the combined license are met. The ITAAC closure process is not finalized for these ITAAC until the NRC makes an affirmative finding under 10 CFR 52.103(g). Any future updates to the status of these ITAAC can be found by selecting the link “ITAAC Status Report” on the NRC's websites:
https://www.nrc.gov/reactors/new-reactors/col-holder/vog3.html
and
https://www.nrc.gov/reactors/new-reactors/col-holder/vog4.html.
This notice fulfills the NRC staff's obligations under 10 CFR 52.99(e)(1) to publish a notice in the
Federal Register
of the NRC staff's determination of the successful completion of inspections, tests, and analyses.
Vogtle Electric Generating Plant Unit 3, Docket No. 5200025
A complete list of the review status for VEGP Unit 3 ITAAC, including the submission date and ADAMS Accession Number for each ICN received, the ADAMS Accession Number for each VEF, and the ADAMS Accession Numbers for the inspection reports associated with these specific ITAAC, can be found by selecting the link “ITAAC Status Report” at the NRC's website
https://www.nrc.gov/reactors/new-reactors/col-holder/vog3.html.
Vogtle Electric Generating Plant Unit 4, Docket No. 5200026
A complete list of the review status for VEGP Unit 4 ITAAC, including the submission date and ADAMS Accession Number for each ICN and IPCN received, the ADAMS Accession Number for each VEF, and the ADAMS Accession Numbers for the inspection reports associated with these specific ITAAC, can be found by selecting the link “ITAAC Status Report” on the NRC's website
https://www.nrc.gov/reactors/new-reactors/col-holder/vog4.html.
Dated: April 28, 2021.
For the Nuclear Regulatory Commission.
Omar R. Lopez-Santiago,
Chief, Vogtle Project Office, Office of Nuclear Reactor Regulation.