Green Lake Water Power Company; Notice of Intent To Prepare an Environmental Assessment

Department of Energy Federal Energy Regulatory Commission [Project No. 7189-015] On March 31, 2022, Green Lake Water Power Company filed a relicense application for the 500-kilo...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 7189-015]

On March 31, 2022, Green Lake Water Power Company filed a relicense application for the 500-kilowatt Green Lake Hydroelectric Project No. 7189 (project). The project is located on Green Lake and Reeds Brook in Hancock County, Maine.

In accordance with the Commission's regulations, on March 23, 2023, Commission staff issued a notice that the project was ready for environmental analysis (REA Notice). Based on the information in the record, including comments filed on the REA Notice, staff does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to relicense the project.

The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission's final licensing decision.

The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502-6595 or .

The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate.

Any questions regarding this notice may be directed to Amanda Gill at (202) 502-6773 or .

Milestone Target date
Commission issues EA November 2023.1
Comments on EA December 2023.

Dated: May 31, 2023.

Kimberly D. Bose,

Secretary.

Footnotes

1.  The Council on Environmental Quality's (CEQ) regulations under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 year of the federal action agency's decision to prepare an EA. This notice establishes the Commission's intent to prepare an EA for the Green Lake Hydroelectric Project. Therefore, in accordance with CEQ's regulations, the EA must be issued within 1 year of the issuance date of this notice.

Back to Citation

[FR Doc. 2023-12076 Filed 6-5-23; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

88 FR 37063

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Green Lake Water Power Company; Notice of Intent To Prepare an Environmental Assessment,” thefederalregister.org (June 6, 2023), https://thefederalregister.org/documents/2023-12076/green-lake-water-power-company-notice-of-intent-to-prepare-an-environmental-assessment.