Department of Energy Federal Energy Regulatory Commission [Project No. 2533-062] On January 23, 2023, Brainerd Public Utilities filed an application for a license for the Braine...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 2533-062]

On January 23, 2023, Brainerd Public Utilities filed an application for a license for the Brainerd Hydroelectric Project in the above captioned docket. On February 1, 2023, the Minnesota Pollution Control Agency (Minnesota PCA) received a complete request for a Clean Water Act section 401(a)(1) water quality certification from Brainerd Public Utilities in conjunction with the above captioned project.

On February 2, 2023, staff provided Minnesota PCA with written notice that the applicable reasonable period of time for it to act on the certification request was one (1) year from the date of receipt of the request, and that the certification requirement for the license would be waived if the certifying authority failed to act by February 1, 2024. Because Minnesota PCA did not act by February 1, 2024, we are notifying you pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1), that waiver of the certification requirement has occurred.

Dated: March 15, 2024.

Debbie-Anne A. Reese,

Acting Secretary.

[FR Doc. 2024-06044 Filed 3-20-24; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

89 FR 20200

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Brainerd Public Utilities; Notice of Waiver of Water Quality Certification,” thefederalregister.org (March 21, 2024), https://thefederalregister.org/documents/2024-06044/brainerd-public-utilities-notice-of-waiver-of-water-quality-certification.