- [Project No. 7189-015]
On March 31, 2022, Green Lake Water Power Company filed an application for a subsequent license to continue to operate and maintain the 425-kilowatt Green Lake Hydroelectric Project No. 7189 (Green Lake Project). On May 31, 2023, Commission staff issued a notice of intent to prepare an environmental assessment (EA) to evaluate the effects of relicensing the Green Lake Project. The notice included an anticipated schedule for issuing the EA.
By this notice, Commission staff is updating the procedural schedule for completing the EA. The revised schedule is shown below. Further revisions to the schedule may be made as appropriate.
| Milestone | Target date |
|---|---|
| Issue EA | May 2024.1 |
Any questions regarding this notice may be directed to Amanda Gill at (202) 502-6773, or by email at amanda.gill@ferc.gov.
Dated: April 11, 2024.
Debbie-Anne A. Reese,
Acting Secretary.