Department of Energy
Federal Energy Regulatory Commission
- [Project No. 2853-073]
On June 30, 2022, the Montana Department of Natural Resources and Conservation (Montana DNRC) filed an application for a new major license for the 9.66-megawatt Broadwater Hydroelectric Project (Broadwater Project; FERC No. 2853). On September 20, 2023, Commission staff issued a notice of intent to prepare a draft and final Environmental Assessment (EA) to evaluate the effects of relicensing the Broadwater Project. The notice of intent included an anticipated schedule for issuing the draft and final EA. By this notice, Commission staff is updating the procedural schedule for completing the draft and final EAs. The revised schedule is shown below. Further revisions to the schedule may be made as appropriate.
| Milestone | Target date |
|---|---|
| Commission issues draft EA | May 2024. |
| Comments on draft EA | June 2024. |
| Commission issues final EA | August 2024.1 |
Any questions regarding this notice may be directed to Ingrid Brofman at (202) 502-8347, or Ingrid.brofman@ferc.gov.
Dated: April 11, 2024.
Debbie-Anne A. Reese,