Golden Pass LNG Terminal, LLC; Notice of Request for Extension of Time

Department of Energy Federal Energy Regulatory Commission [Docket No. CP14-517-002] Take notice that on August 28, 2024, Golden Pass LNG Terminal, LLC (GPLNG) requested that the...

Department of Energy
Federal Energy Regulatory Commission
  1. [Docket No. CP14-517-002]

Take notice that on August 28, 2024, Golden Pass LNG Terminal, LLC (GPLNG) requested that the Commission grant an extension of time, until November 30, 2029, to construct and place into service its Golden Pass Export Terminal Project (Project), located in the vicinity of Sabine Pass, Texas, as authorized in the December 21, 2016 Order Granting Authorizations under Sections 3 and 7 of the Natural Gas Act (Order).[1] The Order required GPLNG to complete construction of the Project and make it available for service within five years of the date of the Order, or by December 21, 2021.

On December 11, 2019, the Commission granted GPLNG an extension of time, until November 30, 2026, to complete construction of the Project and make it available for service.[2]

GPLNG states that, due to delays caused by the bankruptcy filing of the lead construction contractor, remaining schedule uncertainties related to the transition to a new lead contractor, and other possible delays outside of GPLNG's control that may occur, such as potential hurricane impacts, and for commissioning and start-up activities, that additional time is required for completing construction of the project and placing it into service.

This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on GPLNG's request for an extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (NGA) (18 CFR 157.10).

As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for NGA facilities when such requests are contested before order issuance. For those extension requests that are contested,[3] the Commission will aim to issue an order acting on the request within 45 days.[4] The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.[5] The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission's environmental analysis for the certificate complied with the National Environmental Policy Act (NEPA).[6] At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission ( printed page 72837) will not re-litigate their issuance.[7] The Director of the Office of Energy Projects, or his or her designee, will act on all of those extension requests that are uncontested.

In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( https://www.ferc.gov). From the Commission's Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field.

User assistance is available for eLibrary and the Commission's website during normal business hours from FERC Online Support at (202) 502-6652 (toll free at 1-866-208-3676) or email at , or the Public Reference Room at (202) 502-8371, TTY (202) 502-8659. Email the Public Reference Room at .

The Commission strongly encourages electronic filings of comments in lieu of paper using the “eFile” link at https://www.ferc.gov. In lieu of electronic filing, you may submit a paper copy which must reference the Project docket number.

The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502-6595 or .

Comment Date: 5:00 p.m. Eastern Time on September 16, 2024.

To file via USPS: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426

To file via any other courier: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852

Dated: August 30, 2024.

Debbie-Anne A. Reese,

Acting Secretary.

Footnotes

1.   See Golden Pass Products, LLC and Golden Pass Pipeline, LLC, 157 FERC ¶ 61,222 (2016), order amending Section 3 authorization, Golden Pass LNG Terminal, LLC, 174 FERC ¶ 61,053 (2021).

Back to Citation

2.   See, Docket No. CP14-517-000, et al, (December 11, 2019) (delegated letter order).

Back to Citation

3.  Contested proceedings are those where an intervenor disputes any material issue of the filing. 18 CFR 385.2201(c)(1).

Back to Citation

4.   Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).

Back to Citation

5.   Id. at P 40.

Back to Citation

6.  Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether the Commission's environmental analysis for the permit order complied with NEPA.

Back to Citation

7.   Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).

Back to Citation

[FR Doc. 2024-20142 Filed 9-5-24; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

89 FR 72836

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Golden Pass LNG Terminal, LLC; Notice of Request for Extension of Time,” thefederalregister.org (September 6, 2024), https://thefederalregister.org/documents/2024-20142/golden-pass-lng-terminal-llc-notice-of-request-for-extension-of-time.