Golden Triangle Storage, Inc; Request for Extension of Time

Department of Energy Federal Energy Regulatory Commission [Docket No. CP07-414-003] Take notice that on October 31, 2024, Golden Triangle Storage, Inc. (GTS) requested that the ...

Department of Energy
Federal Energy Regulatory Commission
  1. [Docket No. CP07-414-003]

Take notice that on October 31, 2024, Golden Triangle Storage, Inc. (GTS) requested that the Commission grant an extension of time, until December 31, 2027, to complete the development of Storage Caverns 1 and 2 to their certificated storage capacities for the GTS Project in Jefferson and Orange Counties, Texas as authorized in the Order Authorizing Certificates issued on December 31, 2007.[1] On January 11, 2022, the Commission granted GTS an extension of time until December 31, 2024, to complete construction of the GTS Project,[2] the currently effective deadline for constructing and placing the GTS Project into service at certificated levels.

GTS explains that as of June 16, 2012, GTS placed all certificated facilities into service except the completion of Caverns 1 and 2 to their maximum certificated capacities. GTS further explains that, prior to this request, it requested and received three extensions of time, primarily to accommodate the lengthy cavern rewatering process required to enlarge the caverns to their full capacity and to deal with salt creep which slowly reduces cavern capacity. GTS states that it will not be able to complete the expansion of Caverns 1 and 2 by December 31, 2024, and therefore requests an extension of time until December 31, 2027.

This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on GTS's request for an extension of time may do so. No reply ( printed page 89978) comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (NGA) (18 CFR 157.10).

As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for NGA facilities when such requests are contested before order issuance. For those extension requests that are contested,[3] the Commission will aim to issue an order acting on the request within 45 days.[4] The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.[5] The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission's environmental analysis for the certificate complied with the National Environmental Policy Act (NEPA).[6] At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.[7] The Director of the Office of Energy Projects, or his or her designee, will act on all of those extension requests that are uncontested.

In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( https://www.ferc.gov). From the Commission's Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field.

User assistance is available for eLibrary and the Commission's website during normal business hours from FERC Online Support at 202-502-6652 (toll free at 1-866-208-3676) or email at , or the Public Reference Room at (202) 502-8371, TTY (202) 502-8659. Email the Public Reference Room at .

The Commission strongly encourages electronic filings of comments in lieu of paper using the “eFile” link at https://www.ferc.gov. In lieu of electronic filing, you may submit a paper copy which must reference the Project docket number.

The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502-6595 or .

Comment Date: 5 p.m. Eastern Time on November 22, 2024.

To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426

To file via any other courier: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852

Dated: November 7, 2024.

Debbie-Anne A. Reese,

Secretary.

Footnotes

1.  Golden Triangle Storage, Inc., 121 FERC ¶ 61,313 (2007).

Back to Citation

2.  2 Golden Triangle Storage, Inc., Docket No. CP07-414-000, et al. (Jan. 11, 2022) (delegated letter order) (“2022 Order”).

Back to Citation

3.  Contested proceedings are those where an intervenor disputes any material issue of the filing. 18 CFR 385.2201(c)(1).

Back to Citation

4.   Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).

Back to Citation

5.   Id. at P 40.

Back to Citation

6.  Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether the Commission's environmental analysis for the permit order complied with NEPA.

Back to Citation

7.   Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).

Back to Citation

[FR Doc. 2024-26490 Filed 11-13-24; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

89 FR 89977

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Golden Triangle Storage, Inc; Request for Extension of Time,” thefederalregister.org (November 14, 2024), https://thefederalregister.org/documents/2024-26490/golden-triangle-storage-inc-request-for-extension-of-time.