Lake Lynn Generation, LLC; Notice of Intent To Prepare an Environmental Assessment (March 5, 2025)

Department of Energy Federal Energy Regulatory Commission [Project No. 2459-279] On November 30, 2022, Lake Lynn Generation, LLC (Lake Lynn Generation) filed an application to r...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 2459-279]

On November 30, 2022, Lake Lynn Generation, LLC (Lake Lynn Generation) filed an application to relicense the 51.2-megawatt Lake Lynn Hydroelectric Project No. 2459. The project is located on the Cheat River, near the city of ( printed page 11734) Morgantown, in Monongalia County, West Virginia, and near the borough of Point Marion, in Fayette County, Pennsylvania.

In accordance with the Commission's regulations, on December 19, 2024, Commission staff issued a notice that the project was ready for environmental analysis (REA notice). Based on the information in the record, including comments filed on the REA Notice, staff does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an environmental assessment (EA) on the application to relicense the project.[1]

The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission's final licensing decision.

The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, community organizations, Tribal members, and others to access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502-6595 or .

The application will be processed according to the following schedule. The EA will be issued for a 45-day comment period. Revisions to the schedule may be made as appropriate.

Any questions regarding this notice may be directed to Allan Creamer at 202-502-8365, .

Milestone Target date
Commission issues EA September 30, 2025.

Dated: March 5, 2025.

Debbie-Anne A. Reese,

Secretary.

Footnotes

1.  For tracking purposes under the National Environmental Policy Act, the unique identification number for documents relating to this environmental review is EAXX-019-20-000-1740488411.

Back to Citation

[FR Doc. 2025-03879 Filed 3-10-25; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

90 FR 11733

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Lake Lynn Generation, LLC; Notice of Intent To Prepare an Environmental Assessment (March 5, 2025),” thefederalregister.org (March 11, 2025), https://thefederalregister.org/documents/2025-03879/lake-lynn-generation-llc-notice-of-intent-to-prepare-an-environmental-assessment-march-5-2025.