Document

Appalachian Power Company; Notice of Effectiveness of Withdrawal of Application for Temporary Variance of License

Department of Energy Federal Energy Regulatory Commission [Project No. 2514-215] On March 21, 2025, Appalachian Power Company (licensee) filed a request for a temporary variance...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 2514-215]

On March 21, 2025, Appalachian Power Company (licensee) filed a request for a temporary variance of license requirements for the 30.1-megawatt Byllesby and Buck Hydroelectric Project No. 2514. On May 12, 2025, the licensee filed a request to withdraw its request.

No motion in opposition to the request for withdrawal has been filed, and the Commission has taken no action to disallow the withdrawal. Pursuant to Rule 216(b) of the Commission's Rules of Practice and Procedure,[1] the withdrawal of the variance request became effective on May 27, 2025, and this proceeding is hereby terminated.

Dated: June 5, 2025.

Debbie-Anne A. Reese,

Secretary.

Footnotes

[FR Doc. 2025-10558 Filed 6-10-25; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

90 FR 24607

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Appalachian Power Company; Notice of Effectiveness of Withdrawal of Application for Temporary Variance of License,” thefederalregister.org (June 11, 2025), https://thefederalregister.org/documents/2025-10558/appalachian-power-company-notice-of-effectiveness-of-withdrawal-of-application-for-temporary-variance-of-license.