Yuba County Water Agency; Notice of Revised Procedural Schedule for Environmental Assessment for the Proposed Project Relicense

Department of Energy Federal Energy Regulatory Commission [Project No. 1403-068] ( printed page 55308) On November 14, 2023, Yuba County Water Agency (YCWA) filed an application...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 1403-068]
( printed page 55308)

On November 14, 2023, Yuba County Water Agency (YCWA) filed an application to relicense the 12-megawatt Narrows Hydroelectric Project (Narrows Project) No. 1403. The project is located on the Yuba River, near the City of Marysville, in Nevada County, California. On May 12, 2025, Commission staff issued a notice of intent to prepare an environmental assessment (EA) to evaluate the effects of relicensing the Narrows Project. The notice included an anticipated schedule for issuing the EA in November 2025.

Staff are still evaluating the effects of relicensing the Narrows Project. In order for staff to fully consider all the information filed by YCWA, the procedural schedule for completing the EA is being revised as follows. Further revisions to the schedule may be made as appropriate.

Milestone Target date
Commission issues EA May 12, 2026.
Comments on the EA June 11, 2026.

Questions regarding this notice may be directed to Rebecca Kipp at (202) 502-8846, or by email at .

(Authority: 18 CFR 2.1)

Dated: November 26, 2025.

Carlos D. Clay,

Deputy Secretary.

[FR Doc. 2025-21756 Filed 12-1-25; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

90 FR 55308

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Yuba County Water Agency; Notice of Revised Procedural Schedule for Environmental Assessment for the Proposed Project Relicense,” thefederalregister.org (December 2, 2025), https://thefederalregister.org/documents/2025-21756/yuba-county-water-agency-notice-of-revised-procedural-schedule-for-environmental-assessment-for-the-proposed-project-rel.