Department of Energy Federal Energy Regulatory Commission [Project No. 15416-001] On April 8, 2026, as supplemented on May 21, 2026, Millwood Hydro AE, LLC (the applicant), file...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 15416-001]

On April 8, 2026, as supplemented on May 21, 2026, Millwood Hydro AE, LLC (the applicant), filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Millwood Hydroelectric Project (or project). The proposed project would be located at the existing U.S. Army Corps of Engineers' (Corps) Millwood Dam on the Little River in Little River and Hempstead Counties, Arkansas. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners' express permission.

The proposed project would consist of the following: (1) a new 150-foot-long by 220-foot-wide forebay located immediately upstream from the existing Corps dam; (2) two new penstocks, 7.5-foot in diameter and 180-foot long; (3) a new 220-foot-long by 100-foot-wide by 30-foot-high reinforced concrete powerhouse housing two 9.0 megawatt turbines; (4) a new 60-foot-long by 60-foot-wide substation adjacent to the powerhouse; (5) a new 300-foot-long by 300-foot-wide tailrace area; (6) a new 4,700-foot long transmission line interconnecting to existing Southwest Electric Power company 138-kilovolt line. The project is estimated to generate an average of 88,000 megawatt-hours annually.

Applicant Contact: Roy Powers, Millwood Hydro LLC., 850 New Burton Road, Suite 201, Dover, DE 19904, (914) 805-2522.

FERC Contact: Prabharanjani Madduri at (202) 502-8017, or by email at .

Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: by 5:00 p.m. Eastern Time on August 3, 2026. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36.

The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission's eFiling system at https://ferconline.ferc.gov/​eFiling.aspx. Commenters can submit brief comments up to 10,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/​QuickComment.aspx. For assistance, please contact FERC Online Support at , (866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P-15416-001.

For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact the Office of Public Participation at (202) 502-6595 or .

More information about this project, including a copy of the application, can be viewed or printed on the “eLibrary” link of Commission's website at http://www.ferc.gov/​docs-filing/​elibrary.asp. Enter the docket (P-15416) number in the docket number field to access the document. For assistance, contact FERC Online Support.

(Authority: 18 CFR 2.1)

Dated: June 4, 2026.

Carlos D. Clay,

Deputy Secretary.

[FR Doc. 2026-11536 Filed 6-8-26; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

91 FR 34825

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Millwood Hydro AE, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications,” thefederalregister.org (June 9, 2026), https://thefederalregister.org/documents/2026-11536/millwood-hydro-ae-llc-notice-of-preliminary-permit-application-accepted-for-filing-and-soliciting-comments-motions-to-in.