Department of Energy
Federal Energy Regulatory Commission
- [Project No. 15021-012]
On August 12, 2026, Bard College (exemptee) filed revised Exhibit F drawings to incorporate the revised American eel downstream passage bypass at the project intake at the Annandale Micro Hydropower Project No. 15021.[1] On August 14, 2026, the exemptee filed a notice of withdrawal of the Exhibit F drawings. The unconstructed project is located on the Saw Kill, a tributary of the Hudson River, in the Town of Red Hook, Dutchess County, New York. The project does not occupy federal land.
No motion in opposition to the notice of withdrawal has been filed, and the Commission has taken no action to disallow the withdrawal. Pursuant to Rule 216(b) of the Commission's Rules of Practice and Procedure,[2] the withdrawal of the Exhibit F drawings became effective on August 31, 2026,[3] and this proceeding is hereby terminated.
(Authority: 18 CFR 2.1)
Dated: September 2, 2026.
Carlos D. Clay,
Deputy Secretary.