City of Aspen, Colorado; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests

Department of Energy Federal Energy Regulatory Commission [Project No. 10441-020] Take notice that the following hydroelectric application has been filed ( printed page 59124) w...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 10441-020]

Take notice that the following hydroelectric application has been filed ( printed page 59124) with the Commission and is available for public inspection.

a. Type of Application: Subsequent Minor License.

b. Project No.: 10441-020.

c. Date filed: April 8, 2025.

d. Applicant: City of Aspen, Colorado.

e. Name of Project: Maroon Creek Hydroelectric Project.

f. Location: The existing project is located on Maroon Creek near the city of Aspen in Pitkin County, Colorado. The project occupies 0.575 acres of land managed by the U.S. Forest Service in the White River National Forest.

g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).

h. Applicant Contact: Mr. Phil Overeynder, Utility Director, 427 Rio Grande Place, Aspen, CO 81611 (970) 920-5000, .

i. FERC Contact: Jane Dalgliesh, Coordinator, West Branch, Division of Hydropower Licensing; (503) 552-2718; .

j. Deadline for filing motions to intervene and protests: By 5:00 p.m. Eastern Time on November 16, 2026.

The Commission strongly encourages electronic filing. Please file motions to intervene and protests and requests for cooperating agency status using the Commission's eFiling system at ferconline.ferc.gov/​FERCOnline.aspx. Commenters can submit brief comments up to 10,000 characters, without prior registration, using the eComment system at ferconline.ferc.gov/​QuickComment.aspx. For assistance, please contact FERC Online Support at, (866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, please send a paper copy via U.S. Postal Service to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Maroon Creek Hydroelectric Project P-10441-020.

The Commission's Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

k. This application has been accepted but is not ready for environmental analysis at this time.

l. Project Description: The existing project works consist of (a) a 10-foot-high, 40-foot-long reinforced concrete dam with a crest elevation of 8,245.75 feet (the Maroon Creek diversion dam); (b) a small impoundment; (c) an intake structure at the dam; (d) a 39-inch-diameter, 5,563-foot-long buried reinforced concrete penstock; (e) a 27-inch-diameter, 1,317-foot-long buried reinforced concrete penstock together with a 110-foot section of steel penstock at the plant site; (f) a powerhouse with a 450 kW turbine-generator unit; (g) a 200-foot-long trapezoidal open channel tailrace, returning the water to Maroon Creek; (h) 0.48 kV generator leads to a three-phase, 0.48/24.9 kV step-up transformer; (i)an approximately 400-foot-long, 24.9 kV overhead power line tap connection to the Aspen Highlands circuit operated by Holy Cross Energy; and (j) appurtenant facilities.

The application describes the addition of up to 50 kW of generating capacity through two new small turbines, with two new attached generators placed at the existing diversion dam. These new units would generate power from the bypass flows released from the diversion dam without changing the time or the amount of those releases. Flows utilized by new generation equipment would be returned to the same location on the stream immediately below the dam and headgate.

m. A copy of the application can be viewed on the Commission's website at www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at or call toll-free, (866) 208-3676 or (202) 502-8659 (TTY).

You may also register online at ferconline.ferc.gov/​FERCOnline.aspx to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

n. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact the Office of Public Participation at (202) 502-6595 or .

o. Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application.

All filings must (1) bear in all capital letters the title “PROTEST” or “MOTION TO INTERVENE”; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.

p. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate

Milestone Date
Issue Scoping Notice October 2026.
Scoping Comments Due November 2026.
Issue Notice of Ready for Environmental Analysis January 2027.
( printed page 59125)

(Authority: 18 CFR 2.1.)

Dated: September 15, 2026.

Carlos D. Clay,

Deputy Secretary.

[FR Doc. 2026-19180 Filed 9-17-26; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

91 FR 59123

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“City of Aspen, Colorado; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests,” thefederalregister.org (September 18, 2026), https://thefederalregister.org/documents/2026-19180/city-of-aspen-colorado-notice-of-application-accepted-for-filing-and-soliciting-motions-to-intervene-and-protests.