City of Aspen; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Maroon Creek Hydroelectric Project

Department of Energy Federal Energy Regulatory Commission [Project No. 10441-020] Take notice that the following hydroelectric application has been filed with the Commission and...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 10441-020]

Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

a. Type of Application: Subsequent Minor License.

b. Project No.: 10441-020.

c. Date Filed: April 8, 2025.

d. Applicant: City of Aspen.

e. Name of Project: Maroon Creek Hydroelectric Project.

f. Location: On Maroon Creek near the city of Aspen in Pitkin County, Colorado. The project occupies 0.575 acres of land managed by the U.S. Forest Service in the White River National Forest.

g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).

h. Applicant Contact: Mr. Phil Overeynder, Utility Director, 427 Rio Grande Place, Aspen, CO 81611, (970) 920-5000, .

i. FERC Contact: Jane Dalgliesh, Coordinator, West Branch, Division of Hydropower Licensing; (503) 552-2718; .

j. The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental document that will discuss the environmental effects of relicensing the Maroon Creek Hydroelectric Project. The Commission will use this environmental document in its decision-making process to determine whether to issue a new license for the project.

k. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies regarding the project. This notice is intended to advise all participants as to the potential scope of the National Environmental Policy Act (NEPA) document and to seek additional information pertinent to this analysis. Commission staff does not intend to issue a separate scoping document.

As part of the NEPA review process, the Commission takes into account concerns the public may have about proposals and the environmental effects that could result from its action whenever it considers the issuance of a hydropower license. This gathering of public input is referred to as “scoping.” The main goal of the scoping process is to focus the analysis in the environmental document on the important environmental issues.

l. Scoping Comments: By this notice, the Commission requests written public comments on the scope of issues to address in the environmental document. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC by 5:00 p.m. Eastern Time on November 9, 2026.

Comments should focus on the potential environmental effects and reasonable alternatives. Your input will help the Commission staff determine what issues they need to evaluate in the environmental document. Commission staff will consider all written and oral comments during the preparation of the environmental document.

The Commission strongly encourages electronic filing. Please file scoping comments using the Commission's eFiling system at ferconline.ferc.gov/​FERCOnline.aspx. Commenters can submit brief comments up to 10,000 characters, without prior registration, using the eComment system at ferconline.ferc.gov/​QuickComment.aspx. For assistance, please contact FERC Online Support at , (866) 208-3676 (toll free), or (202) 502-8659 ( printed page 65202) (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. All filings must clearly identify the project name and docket number on the first page: Maroon Creek Hydroelectric Project (P-10441-020).

The Commission's Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

m. The application is not ready for environmental analysis at this time.

n. Project Description: The existing project consists of (a) a 10-foot-high, 40-foot-long reinforced concrete dam with a crest elevation of 8,245.75 feet mean sea level (the Maroon Creek diversion dam); (b) a small impoundment; (c) an intake structure at the dam; (d) a 39-inch-diameter, 5,563-foot-long buried reinforced concrete penstock; (e) a 27-inch-diameter, 1,317-foot-long buried reinforced concrete penstock together with a 110-foot section of steel penstock at the plant site; (f) a powerhouse with a 450-kilowatt (kW) turbine-generator unit; (g) a 200-foot-long trapezoidal open channel tailrace, returning the water to Maroon Creek; (h) 0.48-kilovolt (kV) generator leading to a three-phase, 0.48/24.9 kV step-up transformer; (i) an approximately 400-foot-long, 24.9 kV overhead power line tap connection to the Aspen Highlands circuit operated by Holy Cross Energy; and (j) appurtenant facilities.

The City of Aspen proposes the addition of up to 50 kW of generating capacity through two new small turbines, with two new attached generators placed at the existing diversion dam. These new units would generate power from the bypass flows released from the diversion dam without changing the timing or the amount of those releases. Flows utilized by new generation equipment would be returned to the same location on the stream immediately below the dam and headgate.

In addition, the City of Aspen proposes to continue implementing the following measures that are a part of the current license: (1) maintain a minimum flow of 6 cfs in the project's bypass reach, as measured immediately downstream from the confluence with Willow Creek, located a fourth of a mile downstream from the project's diversion dam, or maintain the natural flow in Maroon Creek downstream of the confluence with Willow Creek, whichever is less; (2) maintain streamflow gages to monitor minimum flow; (3) maintain the fish screening structure at the powerhouse intake; (4) use best management practices to minimize dust, noise, and traffic impacts to residents during delivery of equipment and construction; (5) revegetate any disturbed land surfaces; and (6) consult with Colorado Parks and Wildlife during the final design of the project.

o. A copy of the application, with details of the proposed project, can be viewed on the Commission's website at www.ferc.gov using the “eLibrary” link. Enter the project's docket number excluding the last three digits in the docket number field to access the document (P-10441-020). For assistance, contact FERC at , (866) 208-3676 (toll free), or (202) 502-8659 (TTY).

p. NEPA Process and the Environmental Document: Any environmental document issued by the Commission will discuss effects that could occur as a result of the project's relicensing under the relevant general resource areas, such as:

  • geology and soils;
  • aquatic resources;
  • terrestrial resources;
  • threatened and endangered species;
  • recreation, land use, and aesthetic resources;
  • cultural resources; and
  • developmental resources.

Commission staff will also evaluate reasonable alternatives to the proposed project or portions of the project and make recommendations on how to lessen or avoid effects on the various resource areas. Your comments will help Commission staff identify and focus on the issues that might have an effect on the human environment and potentially eliminate others from further discussion in the environmental document.

Following this scoping period, Commission staff will determine whether to prepare an Environmental Assessment (EA) or an Environmental Impact Statement (EIS). The EA or EIS will present Commission staff's independent analysis of the issues. If Commission staff prepares an EA, a Notice of Intent to Prepare an Environmental Assessment will be issued. The EA may be issued for an allotted public comment period. The Commission would consider timely comments on the EA before making its decision regarding the proposed project. If Commission staff prepares an EIS, a Notice of Intent to Prepare an Environmental Impact Statement will be issued. Staff will then prepare a draft EIS which will be issued for public comment. Commission staff will consider all timely comments received during the comment period on the draft EIS and revise the document, as necessary, before issuing a final EIS. Any EA or draft and final EIS will be available in electronic format in the public record through eLibrary. If eSubscribed, you will receive instant email notification when the environmental document is issued (see paragraph (s) of this notice for instructions on using eSubscription).

q. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact the Office of Public Participation at (202) 502-6595 or .

r. This notice is being distributed to the Commission's official mailing list for the project and any additional entities on the applicant's distribution list. You can access the Commission's official mailing list for this project at Mailing List/Recipients By State. If you want to receive future mailings for the project and are not included on the Commission's official mailing list, or if you wish to be removed from the Commission's official mailing list, please send your request by email to . In lieu of an email request, you may submit a paper request. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. All written or emailed requests must specify your wish to be added to or removed from the mailing list and must clearly identify the following on the first page: Maroon Creek Hydroelectric Project No. 10441-020.

Additionally, the Commission offers a free service called eSubscription, which makes it easy to stay informed of all issuances and submittals regarding the ( printed page 65203) dockets/projects to which you subscribe. These instant email notifications are the fastest way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. Go to www.ferc.gov/​ferc-online/​overview to register for eSubscription.

In addition to publishing the full text of this notice in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this notice, as well as other documents in the proceeding ( e.g., license application) via the internet through the Commission's Home Page ( www.ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document (P-10441-020). For assistance, contact FERC at , (866) 208-3676 (toll free), or (202) 502-8659 (TTY).

(Authority: 18 CFR 2.1)

Dated: October 8, 2026.

Debbie-Anne A. Reese,

Secretary.

[FR Doc. 2026-20996 Filed 10-13-26; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

91 FR 65201

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“City of Aspen; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Maroon Creek Hydroelectric Project,” thefederalregister.org (October 14, 2026), https://thefederalregister.org/documents/2026-20996/city-of-aspen-notice-of-scoping-period-requesting-comments-on-environmental-issues-for-the-proposed-maroon-creek-hydroel.