Pacific Gas and Electric Company; Notice of Intent To File License Application, Filing of Pre-Application Document (Pad), Commencement of Pre-Filing Process, and Scoping; Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests

Department of Energy Federal Energy Regulatory Commission [Project No. 137-242] a. Type of Filing: Notice of Intent to File License Application for a New License and Commencing ...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 137-242]

a. Type of Filing: Notice of Intent to File License Application for a New License and Commencing Pre-filing Process.

b. Project No.: 137-242.

c. Dated Filed: September 2, 2026.

d. Submitted By: Pacific Gas and Electric Company.

e. Name of Project: Mokelumne River Hydroelectric Project.

f. Location: The project occupies lands within the Sierra Nevada and includes portions of the North Fork of the Mokelumne River (NFMR), Bear River, mainstem Mokelumne River, and associated tributaries of the NFMR in Alpine, Amador, and Calaveras Counties, California. Portions of the Project occupy lands within the U.S. Department of Agriculture, Forest Service's Stanislaus National Forest, Eldorado National Forest, and Humboldt-Toiyabe National Forest, and lands managed by the U.S. Department of the Interior, Bureau of Land Management.

g. Filed Pursuant to:18 CFR part 5 of the Commission's Regulations.

h. Potential Applicant Contact: Susan Kester, Relicensing Senior Project Manager, Pacific Gas and Electric Company, 12840 Bill Clark Way, Auburn, CA 95602; (415) 264-7197 or email at .

i. FERC Contact: Benjamin Man at (202) 502-8127 or email at .

j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item o below. Cooperating agencies should note the Commission's policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See 94 FERC ¶ 61,076 (2001).

k. With this notice, we are initiating informal consultation with: (a) the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402 and (b) the State Historic Preservation Officer, as required by section 106, National Historic Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2.

l. With this notice, we are designating Pacific Gas and Electric Company as the Commission's non-federal representative for carrying out informal consultation, pursuant to section 7 of the Endangered Species Act and section 106 of the National Historic Preservation Act.

m. Pacific Gas and Electric Company filed with the Commission a Pre-Application Document (PAD; including a proposed process plan and schedule), pursuant to 18 CFR 5.6 of the Commission's regulations.

n. A copy of the PAD is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's website ( www.ferc.gov), using the “eLibrary” link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at , (866) 208-3676 (toll free), or (202) 502-8659 (TTY). A copy is also available for inspection and reproduction at the address in paragraph h.

Register online at www.ferc.gov/​docs-filing/​esubscription.asp to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

o. With this notice, we are soliciting comments on the PAD and Commission's staff Scoping Document 1 (SD1), as well as study requests. All comments on the PAD and SD1, and study requests should be sent to the address above in paragraph h. In addition, all comments on the PAD and SD1, study requests, requests for cooperating agency status, and all communications to and from Commission staff related to the merits of the potential application must be filed with the Commission.

The Commission strongly encourages electronic filing. Please file all documents using the Commission's eFiling system at www.ferc.gov/​docs-filing/​efiling.asp. Commenters can submit brief comments up to 10,000 characters, without prior registration, using the eComment system at www.ferc.gov/​docs-filing/​ecomment.asp. For assistance, please contact FERC Online Support at . In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. All filings must clearly identify the project name and docket number on the first page: Mokelumne River Hydroelectric Project (P-137-242).

All filings with the Commission must bear the appropriate heading: “Comments on Pre-Application Document,” “Study Requests,” “Comments on Scoping Document 1,” “Request for Cooperating Agency Status,” or “Communications to and from Commission Staff.” Any individual or entity interested in submitting study requests, commenting on the PAD or SD1, and any agency requesting cooperating status must do so on or before 5:00 p.m. Eastern Time on January 4, 2027.

p. Scoping Sessions: Commission staff will hold two scoping sessions in the vicinity of the project. All interested individuals, organizations, and agencies are invited to attend one or both of the sessions to provide oral comments. The dates, times, and locations of the scoping sessions will be provided in a future notice.

Scoping Document 1 (SD1), which outlines the subject areas to be addressed in the environmental document, was mailed to the individuals and entities on the Commission's mailing list. Copies of SD1 will be available at the scoping sessions, or may be viewed on the web at www.ferc.gov, using the “eLibrary” link. Follow the directions for accessing information in paragraph ( printed page 69832) n. Based on all oral and written comments, a Scoping Document 2 (SD2) may be issued. SD2 may include a revised process plan and schedule, as well as a list of issues, identified through the scoping process.

Environmental Site Review

The potential applicant and Commission staff will conduct an Environmental Site Review of the project. The date, time, and location of the Environmental Site Review will be provided in a future notice.

Scoping Session Objectives

The primary goal of these scoping sessions is to have you identify the specific environmental issues and concerns that should be considered in the environmental document. Commission staff will prepare either an environmental assessment (EA) or an environmental impact statement (EIS) that will present Commission staff's independent analysis of the issues. The Commission's scoping process will help determine the required level of analysis and satisfy the NEPA scoping requirements, irrespective of whether the Commission prepares an EA or an EIS.

Scoping session participants should come prepared to discuss their issues and/or concerns. Please review the PAD and SD1 in preparation for the scoping sessions. Directions on how to obtain a copy of the PAD and SD1 are included in item n. of this document.

Meeting Procedures

The scoping sessions will begin promptly at their respective start times listed above. If you wish to speak, Commission staff will hand out numbers in the order of your arrival. If no additional numbers have been handed out and all individuals who wish to provide comments have had an opportunity to do so, staff may conclude the session a half hour earlier than the scheduled time.

Your oral comments will be recorded by a court reporter (with FERC staff or FERC representative present) and become part of the public record for this proceeding. Transcripts will be publicly available on FERC's eLibrary system (see paragraph (n) of this notice for instructions on using eLibrary). If a significant number of people are interested in providing oral comments in the one-on-one settings, a time limit of 5 minutes may be implemented for each commentor. Although there will not be a formal presentation, Commission staff will be available throughout the scoping session to answer your questions about the environmental review process. Representatives from Pacific Gas and Electric Company will also be present to answer project-specific questions.

Proper conduct will help the sessions maintain a respectful atmosphere for attendees to provide comments effectively. Loudspeakers, lighting, oversized visual aids, other visual or audible disturbances, and disruptive video and photographic equipment are not permitted. Recorded interviews are also not permitted within the session space. FERC reserves the right to end the session if disruptions interfere with the opportunity for individuals to provide oral comments or if there is a safety or security risk.

It is important to note that the Commission provides equal consideration to all comments received, whether filed in written form or provided orally at a scoping session.

q. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact the Office of Public Participation at (202) 502-6595 or .

(Authority: 18 CFR 2.1)

Dated: November 2, 2026.

Debbie-Anne A. Reese,

Secretary.

[FR Doc. 2026-22603 Filed 11-4-26; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

91 FR 69831

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Pacific Gas and Electric Company; Notice of Intent To File License Application, Filing of Pre-Application Document (Pad), Commencement of Pre-Filing Process, and Scoping; Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests,” thefederalregister.org (November 5, 2026), https://thefederalregister.org/documents/2026-22603/pacific-gas-and-electric-company-notice-of-intent-to-file-license-application-filing-of-pre-application-document-pad-com.